13/0705/FUL Application for two additional 1 bed apartments at Parcels 10 & 12C Clay Farm
ApprovedPlanning1 paper
Joint Development Control Committee - Cambridge Fringes approved this item on Wednesday 17 July 2013. Below is the council's own wording, with the papers it was decided on.
Resolved (by 9 votes to 1) to accept the officer recommendation to approve planning permission as per the agenda. In line with provisions of the Growth and Infrastructure Act, there is no requirement to provide Reasons for Approval on the decision notice. As such the Reason for Approval on page 46 can be removed.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Joint Development Control Committee - Cambridge Fringes
JOINT DEVELOPMENT CONTROL COMMITTEE (CAMBRIDGE FRINGE SITES)
Report by: Head of Planning Services
Date: 17th July 2013
Application 13/0705/FUL Agenda Item Number
Date Received 21st May 2013 Officer Sophie Pain
Target Date 16th July 2013
Parishes/Wards Trumpington
Site Parcels 10 and 12C, Clay Farm Development Site, Addenbrookes Road, Cambridge
Proposal Formation of two additional 1 bed apartments, one within Parcel 10 and one within Parcel 12C on the Clay Farm Development, pursuant to planning consent 10/1296/REM.
Applicant Countryside Properties UK
Recommendation Approval
Application Type Minor Departure: No
The above application(s) have been reported to the Planning Committee for determination by Members in accordance with the Scheme of Delegation for the Joint Development Control Committee for the Cambridge Fringes 0.0 INTRODUCTION
0.1This is a full application for the creation of two additional affordable 1 bed apartments. These are within 2 BPHA apartments blocks, one in Parcel 10 and one in Parcel 12C, that were approved through the Reserved Matters application (10/1296/REM) approved by the Joint Development Control Committee (JDCC) on 14 July 2011.
0.2These two apartment blocks were originally granted planning approval with a centralised boiler system that was located in a plant room on the ground floor of the block. At the request of the BPHA, the centralised boiler system has now been omitted from both apartment blocks due to concerns that they were uneconomical and would impose a larger service charge for tenants. However, this has left a large space at ground floor that would otherwise be left empty.
0.3The amendments were originally sought as a Non Material Amendment to the Reserved Matters application. However, as the proposal includes additional units beyond the 306 dwellings approved these amendments are material and a formal planning application was invited. The application is brought to this Committee for a decision as it constitutes ancillary development to the previous reserved matters permission under the JDCC Scheme of Delegation.
1.0SITE DESCRIPTION/AREA CONTEXT
1.1The two parcels (10 & 12C) were granted permission as part of a wider Reserved Matters permission, in conjunction with parcels 11 and 12b for the provision of 306 dwellings pursuant to the outline application 07/0620/OUT. The two parcels of land that are the subject of this application are located at the southern end of the Clay Farm site. Parcel 10 is located to the north west of the roundabout on the approach from Shelford Road, while Parcel 12C is located in the south east corner of the same roundabout, facing onto the Addenbrooke’s Spine Road.
1.2Each of the apartment blocks are set within a residential context with a mix of housing and tenure types and associated green spaces. To the north west of Parcel 10 is the existing mature plantation strip with the Cambridge Guided Busway beyond it. The application site area is 0.29 ha.
1.3Whilst construction has started on Parcels 10 and 11, work has not commenced on the area for Apartment Block 10 or the adjacent plots. No construction has taken place on Parcel 12C.
2.0THE PROPOSAL
2.1The planning application seeks approval for the creation of two 1 bed apartments within two individual BPHA apartment blocks. The proposed development does not alter the footprint or massing of the apartments, but only proposes some minor elevational changes, where windows need to be inserted. The appropriate provision for car and cycle parking has also been provided for the two new units.
2.2The application is accompanied by the following documents:
• Design and Access Statement • Plans
3.0RELEVANT SITE HISTORY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Development Control Committee - Cambridge Fringes at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.