Decision of Executive Councillor for Public Places Approved the commencement of the project, which is already included in the Council’s Capital & Revenue Project Plan (SC573). The total cost of the project was £34,480, funded from Reserves, of which £25,000 had been approved. The Executive Councillor approved the additional funding of £9,480. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations Committee did not request this item for pre-scrutiny. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
The project is the installation of an air-cooling unit to lower the internal temperature in the TIC during the summer months in accordance with the Chartered Institution of Building Serves Engineers (CIBSE) recommendation. Target Dates: Start of procurement Mid June Award of Contract End June/Beg July Start of project delivery Mid-August Completion of project End of August Date that project output is expected to End of August become operational (if not same as above)
1.2Anticipated Cost Total Project Cost £ 34,480 Cost Funded from:
Funding: Amount: Details:
Reserves £ 25,000 SC573
Repairs & Renewals £ 0.00
Developer Contributions £ 0.00
Climate Change Fund £ 0.00 Seeking further funding from Other £ 9,480 City Council Reserves
1.3Procurement process Four written quotations will be sought from external specialist suppliers in line with the Council’s Constitution.
2 Project Appraisal & Procurement Report
2.1Project Background
The Tourist Information Centre (TIC) has experienced excessive temperatures during the summer period, since its relocation to the old crown court complex in the Guildhall in 2009. A feasibility study was undertaken by an external Building Services Consultant to determine what options were available to combat the overheating problem. The excessive heat experienced in the centre has not only had an impact on staff working in the TIC, but it has also led to complaints from users of the Tourist Information Centre and in turn reduced dwell time in the centre. This is of particular concern given the pressures on the TIC to achieve challenging income targets.
2.2Aims & objectives The aim of the project is to control the internal summertime temperature in the TIC to those recommended by the Chartered Institution of Building Services Engineers (CIBSE).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.