Item13/31/Env

Resolved

Agreed that there was a need for appropriate cycle ways and parking areas. ii. Raised concerns that cyclists cycled in pedestrian areas and parked anywhere, not just in designated areas eg chaining bikes to lamp posts. This raised safety concerns for visually/mobility impaired people. iii. Asked for street clutter (eg advert boards) to be removed from shopping areas and pavements. iv. Called for a bike ban in the city centre. The Executive Councillor for Planning and Climate Change said bicycles had been banned from the city centre in the past, but the ban had been revoked. The County Council could be petitioned to reinstate the ban. Matter for Decision The project aims to provide one thousand additional secure cycle parking spaces in the heart of the city centre. This is planned to be achieved through the provision of: i. Localised on-street cycle parking throughout the city centre where space allows and the demand for cycle parking is high. ii. A third undercover secure cycle park, similar to those at Park St and Grand Arcade car parks. This report provides an appraisal of the on-street element of the project. Feasibility work is currently underway to look at the options for a third undercover secure cycle park. Decision of Executive Councillor for Planning and Climate Change Financial Recommendation i. Approved the commencement of the on-street cycle parking proposals, which is already included in the Council’s Capital & Revenue Project Plan. The total estimated cost of the on-street proposal is £235,000 funded from the City Centre Cycle Parking Project capital allocation SC549. Procurement Recommendations Approved the carrying out and completion of the procurement of: ii. The construction of the proposed cycle parking locations as listed in table 1.0 and detailed in the package of drawings in Appendix C of the Officer’s report; subject to the following sites being deferred pending further information (ie equality impact assessments and commuted sum) being presented to a future Environment Committee for further consideration: · Pease Hill 014-018/000/102. · Guildhall Street 014-018/000/103. · Kings Parade 014-018/000/004. · Jesus Lane 014-018/000/008. · Wheeler Street. iii. Consultation approved and the results to be presented to a future Environment Committee for the additional new sites included in table 1.0 namely: · St Mary’s Street. · East Road. · Peas Hill/Wheeler Street. Subject to: · The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. · The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Project Delivery & Environment Manager. The Committee made the following comments in response to the report: i. Expressed concern regarding the loss of city centre disabled parking spaces and the impact this would have on members of the public wishing to use them. ii. Suggested the city centre had some existing access issues for people with mobility and visual impairments. For example, street clutter and cycling in pedestrian areas. Increasing cycle parking provision could exacerbate these issues. iii. Expressed concern at the proposed increase of cycle parking provision in heritage areas. In response to Members’ questions the Director of Environment and Project Delivery & Environment Manager said the following: i. The needs of pedestrians, cyclists and motorists needed to be balanced. ii. Various organisations had been included in the parking provision consultation, including Camsight. iii. An old version of the equality impact assessment was included in the agenda pack. Details have since been updated. The new report could be circulated upon request. iv. The impact of advert boards on thoroughfares could be reviewed. v. Disabled parking bays could be kept on Peas Hill if cycle parking provision was reduced. vi. Eden Street was erroneously referred to as Elm Street on P108 of the agenda pack. Councillors requested a change to recommendation (ii). Councillors O’Reilly and Saunders formally proposed to amend the following recommendation from the Officer’s report (amendments shown as bold): ii. (Procurement) The construction of the proposed cycle parking locations as listed in table 1.0 and detailed in the package of drawings in Appendix C of the Officer’s report; subject to the following sites being deferred pending further information (ie equality impact assessments and commuted sum) being presented to a future Environment Committee for further consideration: · Pease Hill 014-018/000/102. · Guildhall Street 014-018/000/103. · Kings Parade 014-018/000/004. · Jesus Lane 014-018/000/008. · Wheeler Street. The Committee unanimously approved this amended recommendation. The Committee resolved unanimously to endorse the recommendations as amended. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Cambridge City Council

Project Appraisal and Scrutiny Committee Recommendation

Project Name: Cambridge City Centre Cycle Parking Project Cllr Tim Ward, Executive Councillor for To: Planning and Climate Change Report by: Simon Payne – Director of Environment Scrutiny committee: ENVIRONMENT 8 October 2013 Wards affected: Market

Recommendations; 1.0 Financial recommendations –

1.1The Executive Councillor is asked to approve the commencement of the on-street cycle parking proposals, which is already included in the Council’s Capital & Revenue Project Plan. 1.2 The total estimated cost of the on-street proposal is £235,000 funded from the City Centre Cycle Parking Project capital allocation SC549. 1.3 There are no on-going revenue costs for the project.

2.0Procurement recommendations: The Executive Councillor is asked to approve the carrying out and completion of the procurement of:

2.1The construction of the proposed cycle parking locations as listed in table 1.0 and detailed in the package of drawings in Appendix C of this report. 2.2 Construction subject to positive consultation of the additional new sites included in table 1.0 namely;  St Mary’s Street  East Road  Peas Hill/Wheeler St

Appraisal Page | 1 2.3 Subject to:

- The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract.

- The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%.

Project Name: Cambridge City Centre Cycle Parking Project

SUMMARY 3.0 The Project

The project aims to provide 1,000 additional secure cycle parking spaces in the heart of the city centre. This is planned to be achieved through the provision of;

 Localised on-street cycle parking throughout the city centre where space allows and the demand for cycle parking is high.

 Introduce a third undercover secure cycle park, similar to those at Park St and Grand Arcade car parks.

This report provides an appraisal of the on-street element of the project. Feasibility work is currently underway to look at the options for a third undercover secure cycle park.

Target Dates: Detailed Design & Production of October to December 2013 Information: Start of Procurement: December 2013 Award of Contract: December 2013 Construction Commencement: January 2014 Construction Completion: March 2014

Appraisal Page | 2 4.0 Anticipated Cost

Total Project Cost £ 235,000

Cost Funded from: Funding: Amount: Details: Reserves £ 235,000 Capital Plan Ref: SC549 Repairs & Renewals £ Developer £ Contributions Climate Change £ Fund Other £

A further breakdown of costs can be found in Appendix A of this report

5.0Procurement process

5.1Procurement for the implementation will be through the Braintree District Framework Agreement, which includes six contractors and is in accordance with the requirements of the City Council’s Contract Procedure Rules. 5.2 Following receipt of tenders, the winning tender will be identified following assessment by a skilled officer panel.

6.0Project Background

6.1A detailed street level study of the city centre has been carried out, to determine the areas of the city centre where there is currently a shortage of secure cycle parking, leading to informal and sometimes obstructive abandonment of cycles. 6.2 The scope of this project was confined to the city centre and did not have a remit to look at wider provision across the city, for example at local centres such as Mill Road. A plan of the scope area can be found in the consultation report in Appendix B of this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/31/EnvAppendix A 58 KB Download
PDF
/31/EnvAppendix B 7 MB Download
PDF
/31/EnvAppendix C 2 MB Download
PDF
/31/EnvAppendix D 81 KB Download
PDF
/31/EnvAppendix E 59 KB Download
PDF
Cambridge Cycle Parking ProjectReport 322 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
KB
Councillor Kevin Blencowe Labour Spokes for Planning and Climate ChangeCommittee Member, present
GM
Councillor Gail Marchant-DaisleyCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
CO
Councillor Carina O'Reilly Labour Spokes for Public PlacesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, present
LH
Councillor Lewis HerbertReserve

On this subject at Cambridge

Search all
  1. Cambridge Cycle Parking ProjectThis decision
  2. Councillor Martinelli: Cambridge Cycle Point TheftsAgreed
  3. 17/1461/REM: Cycleway/footway - Land Adjacent to Cambridge Guided Busway and Adjacent to existing plantation within abode 1 (Parcels 10, 11 and 12), Clay Farm, Trumpington, Cambridge.Decided
  4. Cambridge City Centre Cycle Parking ProjectAgreed
  5. Phase 2 Water Cycle Strategy - Major Growth Areas in and Around CambridgeRefused
  6. Cycle Cambridge updateApproved

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies