Environment Scrutiny Committee agreed this item on Tuesday 8 October 2013. Below is the council's own wording, with the papers it was decided on.

Item13/37/Env

Resolved

Decision The Officer’s report provided details of the proposed project to install additional lighting columns on the two diagonal footpaths across Parker’s Piece. A consultation took place earlier in 2013, which was responded to by over one thousand members of the public. This informed the lighting measures being proposed. Decision of Executive Councillor for Public Places i. Authorised the procurement of specialist lighting design and construction services for the Parker’s Piece Lighting Project, in accordance with the City Council Contract Procedure Rules. ii. Agreed to take the decision to approve the final project appraisal and implementation of the Parker’s Piece Lighting project, out of the Environment Scrutiny Committee cycle, in consultation with the Chair and Spokes, subject to the final proposed project cost not exceeding £60,000. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Project Delivery & Environment Manager. The Committee e xpressed support for lighting on Parker’s Piece. In response to Members’ questions the Project Delivery & Environment Manager said the following: i. Environmental Improvement Project funding was required to implement the lighting as County Council Highway funding could not be rolled over from a previous financial year. ii. Lux light testing would be undertaken to review if four or six light columns were appropriate. iii. If the light scheme proceeds, the Council would have to make a business case to the County Council to put in an additional power supply sufficient for the skating rink (and may be for similar people who would prefer power to generators). The City Council would need to justify the need for a standing charge as the additional power would not always be required. iv. The Project Delivery & Environment Manager was liaising with the Urban Conservation Team to ensure lighting column designs were appropriate for the area, and reflected consultation comments. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

This report provides details of the proposed project to install additional lighting columns on the two diagonal footpaths across Parker’s Piece. The report explains the development of the project to date, including results of a consultation that took place earlier this year, which was responded to by over one thousand members of the public and has informed the lighting measures that are now being proposed.

Recommendations

The Executive Councillor is recommended;

2.1To authorise the procurement of specialist lighting design and construction services for the Parker’s Piece Lighting Project, in accordance with the City Council Contract Procedure Rules. 2.2 To agree to take the decision to approve the final project appraisal and implementation of the Parker’s Piece Lighting project, out of the Environment Scrutiny Committee cycle, in consultation with the Chair and Spokes, subject to the final proposed project cost not exceeding £60,000.

Appraisal Page | 1 3.0 The Project This project proposes the installation of additional lighting columns along the two diagonal path sections that are adopted public highway across Parker’s Piece. Site Location Plan

Image courtesy of Cambridgeshire County Council

Target Project Programme Dates: Consultation 11 October – 8 November Commence Procurement November 2013 Award of Contract December 2013 Commence Construction January 2014 Project Completion February 2014

Appraisal Page | 2 3.1 Anticipated Cost Total Estimated Project Cost £ 60,000

Cost Funded from:

Funding: Amount: Details: Environmental Safety Fund (£16,000.00) Reserves £21,000.00 Safer City Grant (£5,000.00) Repairs & Renewals £0.00 Developer Public Realm Developer £39,000.00 Contributions Contributions (£39,000.00) Climate Change £0.00 Fund Other £0.00

3.2Procurement process Procurement will be through a request for quotations from three specialist lighting contractors in accordance with a written specification. Quotations will be assessed by a skilled officer panel and selected in accordance with a clear evaluation scheme, based on demonstrated quality versus cost.

Background

3.3.1 Parker’s Piece is described as follows in the Cambridge Landscape Character Assessment:

“Parker’s Piece is a large green space to the south east of the historic city core. It is well used as a recreation area. It has tree planting to its boundary, but none with the internal space, making it a unique space in Cambridge. There are two major paths bisecting it, with a Grade II Listed lamp column near the centre. Like New Square and Christ’s Pieces it is closely mown.”

Appraisal Page | 3 3.3.2 The existing Grade II Listed lighting column is at the centre of the two main paths that cross the park diagonally and is known locally as Reality Checkpoint. The Listed Status text for this structure reads:

“Lamp Standard. C.1860. Cast iron. Square-section plinth and base with inscription panels to each side. South-west side with access hatch. Top edges with waterleaf decoration. Base of shaft with 4 intertwined dolphins. Plain shaft of circular section carries 4 candelabra lamp holders by means of scrolled wrought- iron stays. Glazed mantle cages of inverted conical section.”

3.3.3 Parker’s Piece was transferred to the corporation as pasture in perpetuity for the townsfolk in 1612, and has remained relatively unchanged throughout its history. This relative consistency has established a strong landscape character. This site is also within the conservation area and forms part of the city’s historic core.

3.3.4 Having said that, it has still had to evolve with the changing demands for its use, which history shows has taken time to agree by those responsible. Some of the changes include;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Parker's Piece LightingReport 2.8 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
KB
Councillor Kevin Blencowe Labour Spokes for Planning and Climate ChangeCommittee Member, present
GM
Councillor Gail Marchant-DaisleyCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
CO
Councillor Carina O'Reilly Labour Spokes for Public PlacesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, present
LH
Councillor Lewis HerbertReserve

On this subject at Cambridge

Search all
  1. Parker's Piece LightingThis decision
  2. 23-03297-FUL Ice Rink, Parker’s PieceDecided
  3. 22-00801-FUL, Parkers Piece - 10amDecided
  4. 21/01392/FUL Parkers Piece, Parkside 10:30amDecided
  5. North Pole Experience: Parker's PieceAgreed
  6. University Arms Hotel: Temporary Use of Part of Parker's Piece to Facilitate the RedevelopmentNoted

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies