Cambridge City Council
Housing Scrutiny Committee, Thursday 21 September 2017 at 5.30pm

New Social Housing on Housing Revenue Account Infill Site at Colville Road Garages

Approved Scrutiny 4 papers

Housing Scrutiny Committee approved this item on Thursday 21 September 2017. Below is the council's own wording, with the papers it was decided on.

Item17/42/HSC

Resolved

Decision The report requested that the site was to be brought forward in the Council’s social housing programme, to be included in the Housing Revenue Account (HRA) garage and small in-fill sites development programme. The report requested approval for a capital budget for the HRA in relation to the site at Colville Road Garages. Decision of Executive Councillor for Housing i. Noted the indicative mix of the scheme. ii. Approved the scheme capital budget of £692,987 detailed in the report to cover the construction cost of a scheme, professional fees and other costs to deliver a scheme that meets the identified needs in the City. iii. Approved that delegated authority be given to the Strategic Director to enable the site to be developed through Cambridge Investment Partnership (CIP). Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Housing Development Officer . The Business Manager and Financial Accountant confirmed that standard procurement rules would apply and should the spend exceed the budget by 15% or more, it would be brought back to committee for further approval. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendation.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Summary

This scheme includes an area of garages located off Colville Road, which was identified as a potential development site by City Homes Staff.

There are no existing properties on this site.

2. Reason for Investigation:

These garages have become difficult to let and with a high rate of voids. There is potential for a small development of 3 units.

As the Council seeks to provide more affordable housing across the City, small infill sites such as this present good opportunity for potential development.

This scheme was included in the Council’s three year rolling programme of sites to investigate further the feasibility and viability of development.

3. Engagement with Existing Residents

This development does not include the replacement of existing housing.

Consultations

Letters informing garage tenants of the Council’s intentions to start viability assessments were sent in February 2017. Further letters will be sent prior to committee

Should this scheme receive approval to proceed at committee, then the Housing Development Agency (HDA) will continue to work closely with neighbouring residents to ensure they are kept informed on the progress of the development of the garage site. 4. Feasibility:

The Site

The below plan shows the area for the proposed scheme:

The table below shows the proposed mix approved of new homes for the site.

Option Scheme Proposal 1 2 x 3B5P 93 sqm House 1 x 2B4P 81 sqm House

Site Constraints

Advice was sought from planning consultants in relation to the planning opportunities and constraints on this site including, but not limited to flood risk, highways, residential amenity and heritage considerations. In the planning appraisal for the site it was noted that the access road is narrow. However, this is not considered to be a threat to the viability of the development. The proposed layout plan included in appendix 3 of this document is indicative only, reflecting what could be provided on the site. Local Housing Need

There is a recognised need for more affordable housing across the city. The table below demonstrates the number of households on the Housing Needs Register. There are currently 235 households in need of a 3 bedroom property and 734 in need for a 2 bedroom property so the progression of this scheme would help in meeting the needs of those on the list.

Cambridge City 1bed 2 bed 3 bed 4 bed (June 2017) 1746 734 235 51

5. Proposed scheme

The indicative redevelopment scheme proposed for this site is as follows:

2no. 3 bed 4 person house 1no. 2 bed 4 person house

6. Costs, Funding and Viability

The Housing Revenue Account (HRA) Business Plan already allows for the spending of Right to Buy Receipts and funding the balance of costs to be met by Devolution grant. As with all new build developments as details are progressed they will only proceed if they can be funded within borrowing and capital funding parameters in the HRA 30 Business Plan. If a final scheme cannot be delivered within the budget requested then a revised approval will need to be brought back to Committee for scrutiny.

Capital Costs

The total capital budget required to deliver this scheme is estimated at £692,987. This sum includes planning fees, professional cost fees and other associated on costs, broken down as follows. Works costs £587,278

Contingency £17,618

On costs including professional fees £88,091

Viability – A benchmark used by Registered Providers whether a new scheme is viable is when the scheme breaks even in revenue terms (typically 12 years) and when the total capital used is paid back (typically 30 years). This benchmark relates particularly to vacant sites.

Pay-back period –

Year 1 with Devolution Grant

If this scheme were to be assessed on a pre-devolution basis, assuming that the authority used HRA resources to provide the 70% of funding alongside retained right to buy receipts, it would pay back in year 44.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Apendix 2 Project Appraisal Colville Garages /42/HSCReport 341 KB DownloadRead as text
PDF
Site Location /42/HSCAppendix 1 2.5 MB Download
PDF
Site Layout /42/HSCAppendix 3 889 KB Download
PDF
New Social Housing on Housing Revenue Account Infill Site at Colville Road GaragesReport 150 KB Download

At this meeting

Whole meeting

Who was there

14 of 15 attended
MT
Councillor Mike Todd-JonesChair, present
DB
Councillor Dave BaigentCommittee Member, present
GB
Councillor Gerri BirdVice-Chair, apologies
RC
Councillor Rod Cantrill Lib Dem Spokes for HousingCommittee Member, present
NG
Councillor Nigel GawthropeCommittee Member, present
MH
Councillor Marie-Louise Holland Independent/Green Group SpokesCommittee Member, present
JP
Councillor Jennifer Page-CroftCommittee Member, present
PS
Councillor Patrick SheilCommittee Member, present
MA
Councillor Margery AbbottCommittee Member, present
LA
Lulu Agate Tenant RepresentativeCo-Optee, present
DB
Diane Best Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris Tenant RepresentativeCo-Optee, present

All 15 on the meeting page

On this subject at Cambridge

Search all
  1. New Social Housing on Housing Revenue Account Infill Site at Colville Road GaragesThis decision
  2. New Social Housing – Meadows Centre & Buchan StreetApproved
  3. New Social Housing – Colville Road 2Approved
  4. New Social Housing, Community Centre and Commercial Units on Akeman StreetApproved
  5. New Social Housing on Markham Close Garage SiteApproved
  6. New Social Housing on Gunhild Way Garage SiteApproved

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies