Combined Authority Board, Wednesday 28 January 2026 at 11.00am

Q2 Corporate Performance Report

Decided Committee 3 papers

AI summaryCambridgeshire and Peterborough Combined Authority Board noted Q2 2025/26 performance against 27 KPIs, with none rated Red. The Board also noted progress on the Gateway Review of the £20 million per annum Devolution Deal Investment Fund, whose Final Report was submitted to MHCLG in December 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedIOF KPIs, programmes and Gateway Review progress
Money£20 million per annumDevolution Deal Investment Fund over 30 years
What happens nextQ3 2025/26 performance reportUpdates due for many KPIs in Q3 2025/26
Who it affectsCombined Authority and regionPerformance monitoring across growth, jobs, homes, connectivity

What was decided

The Board noted performance information on 27 Key Performance Indicators in the Interim Outcomes Framework, covering growth, connectivity, jobs, homes, resilience and performance objectives. Report P1, 2.1

The Board noted performance information for the Combined Authority's Most Complex Programmes and Projects, where three were rated Amber and one Green, with none rated Red. Report P1

The Board noted progress on the Gateway Review of the Devolution Deal Investment Fund, with the Final Report submitted to MHCLG in December 2025. Report P1, 6.1

Why

To strengthen scrutiny and accountability in line with the English Devolution Accountability Framework, with KPIs linked to the Corporate Plan 2025-2029. Report P5, 1.1

The Interim Outcomes Framework replaces the previous Balanced Scorecard approach, with greater focus on outcomes aligned to the Corporate Plan and future Integrated Settlement. Report 1.1

The Gateway Review is a five-yearly independent assessment required under the Devolution Deal, evaluating investment impact on local economic growth. Report 6.1

What happens next

A Challenge Session with senior Government officials is being organised, with conclusion of the second Gateway Review expected in early to mid-2026. Report 6.1

The outcome, Final Report and lessons learned will be shared with the Board following confirmation of the outcome from MHCLG. Report 6.1

From the Q4 2025/26 report, progress on the Annual Business Plan 2026/27 will be reported quarterly using milestone-based tracking.

The money

  • £20 million per annum Devolution Deal Investment Fund (Gainshare) over 30 years, subject to Gateway Reviews Report 6.1

Options considered

  • Chosen: Scrutinise then note performance information (as recommended in the report). Board resolved to note, with the original recommendation wording using 'scrutinise' modified in the decision Report P1

Implications

  • Financial: No immediate financial implications from this report. Future Investment Fund funding depends on a successful Gateway Review outcome. Report P37, 6.1
  • Legal: Section 3 of the Local Government Act 1999 duty of continuous improvement applies; no direct legal implications from this performance report. Report P37
  • Staffing: Two new roles (Remediation Manager and Remediation Inspector) funded from 1 January and hosted by Cambridgeshire Fire and Rescue Service.
  • Other: No direct public health, environmental and climate change, or equality, diversity and inclusion implications from this report. Report P37
  • Risk: Three of four Most Complex Programmes and Projects are rated Amber, meaning successful delivery is in doubt without action.

Who and where

  • Cambridgeshire and Peterborough Combined Authority Report P5, 2.1
  • Residents and businesses in the Cambridgeshire and Peterborough region Report 2.1
  • Ministry of Housing, Communities and Local Government (MHCLG) Report 6.1
  • Natural Cambridgeshire and The Wildlife Trust for Bedfordshire, Cambridgeshire and Northamptonshire

Timeline

  • December 2025: Interim Outcomes Framework and Performance Management Framework 2025-2029 adopted by Board Report P5, 1.1
  • December 2025: Final Report on Devolution Deal Gateway Review submitted to MHCLG Report 6.1
  • Q2 2025/26: Performance data period reported Report P5, 2.1
  • January 2026: Annual Business Plan 2026/27 due to be noted by Board
  • Early to mid-2026: Expected conclusion of the second Gateway Review following Challenge Session Report 6.1
  • Q3 2025/26: Next updates due for many KPIs including bus, employment, homes and contract waivers Report P16, P17, P19, P21, P22, P23, P24, P28
  • Q1 2026/27: Connect to Work programme commences; KPI 12 first update due
  • 28 January 2026: Board noted Q2 Corporate Performance Report

Plain English for the jargon

  • IOF: Interim Outcomes Framework, the new KPI reporting model replacing the Balanced Scorecard
  • KPI: Key Performance Indicator
  • CPCA: Cambridgeshire and Peterborough Combined Authority
  • MHCLG: Ministry of Housing, Communities and Local Government
  • EDAF: English Devolution Accountability Framework
  • PMF: Performance Management Framework 2025-2029
  • RAG: Red, Amber, Green rating used to indicate performance status
  • Gainshare: The Combined Authority's Investment Fund under the Devolution Deal
  • Gateway Review: Five-yearly independent assessment of the impact of the Investment Fund on local economic growth
  • NEET: Not in Employment, Education or Training
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

It was resolved to : A Note performance information relating to the Combined Authority’s Key Performance Indicators in the Interim Outcomes Framework (IOF). B Note performance information relating to the Combined Authority’s Most Complex Programmes and Projects. C Note progress to evaluate the impact of the Devolution Deal Investment Fund in a Gateway Review.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Combined Authority Board

Recommendations

A Scrutinise performance information relating to the Combined Authority’s Key Performance Indicators in the Interim Outcomes Framework (IOF). B Scrutinise performance information relating to the Combined Authority’s Most Complex Programmes and Projects. C Note progress to evaluate the impact of the Devolution Deal Investment Fund in a Gateway Review.

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☒ Jobs ☒ Resilience

☒ Connectivity ☒ Homes ☒ Performance The performance information presented in this report includes results for Corporate Key Performance Indicators (KPIs) at the end of Q2 2025/26 and is intended to strengthen scrutiny and accountability in line with expectations outlined in the English Devolution Accountability Framework (EDAF). These KPIs are linked to the Corporate Plan 2025-2029’s objectives, as set out in the IOF adopted in December 2025. The authority’s approach to Corporate Performance Reporting is set out in the Performance Management Framework 2025- 2029 (PMF), which was also adopted in December 2025.

1. Purpose

1.1The introduction of an Interim Outcomes Framework (IOF), as approved by Board in December 2025, is an important step in developing the Combined Authority’s approach to measuring, reporting and improving performance. It marks the transition from the previous Balanced Scorecard approach to an outcomes-based model aligned with the Corporate Plan and future Integrated Settlement. The Outcomes Framework replaces the previous Balanced Scorecard approach to selecting Key Performance Indicators (KPIs), with a greater focus on outcomes to help ensure performance data directly evidences the Combined Authority’s delivery on Corporate Plan objectives for people and places in the region. A logic model has been produced to show how reporting on the IOF KPIs aligns with other CPCA reporting mechanisms. This can be seen below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q2 202526 Outcomes Framework Corporate KPIs DashboardAppendix A 1.2 MB Download
PDF
Most Complex Projects Performance DashboardAppendix B 161 KB Download
PDF
Q2 Corporate Performance ReportReport 526 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 21 attended
PB
Paul Bristow Cambridgeshire and Peterborough Combined AuthorityChair, present
AB
Councillor Anna Bailey East Cambridgeshire District CouncilCommittee Member, apologies, sent representative
CB
Councillor Chris Boden Fenland District CouncilCommittee Member, present
SC
Councillor Sarah Conboy Huntingdonshire District CouncilCommittee Member, present
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, present
SQ
Councillor Shabina Qayyum Peterborough City CouncilCommittee Member, present
AS
Councillor Anna Smith Cambridge City CouncilCommittee Member, present
BS
Councillor Bridget Smith South Cambridgeshire District CouncilCommittee Member, apologies, sent representative
DP
Darryl Preston Police and Crime CommissionerCo-Optee, apologies
RP
Robin Porter Central East Integrated Care BoardCo-Optee, apologies, sent representative
CM
Councillor Christopher Morris Cambridgeshire and Peterborough Fire AuthorityCo-Optee, apologies
JH
Councillor Julia Huffer East Cambridgeshire District CouncilCommittee Member, present as substitute

All 21 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Q2 Corporate Performance ReportThis decision
  2. Q1 26/27 Corporate Performance ReportApproved
  3. Corporate Performance Report, Q1 2026/27Noted
  4. Q4 Corporate Performance ReportDecided
  5. Corporate Performance Report Q4 2025/26Noted
  6. Q3 Corporate Performance ReportDecided

More from Cambridgeshire and Peterborough Combined Authority Combined Authority Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti... Approved Open
23 Sep 2026 Public QuestionsOne public question was received. The question is published . Decided Open
23 Sep 2026 Forward PlanIt was resolved to : A Approve the Forward Plan for September 2026 Approved Open
23 Sep 2026 CPCA Meetings CalendarIt was resolved to : A Approve the proposed amendments to the calendar of meetings for the 2026/27 Municipal Year B A... Approved Open
23 Sep 2026 Updates to the ConstitutionIt was resolved to : A Approve the changes to the Constitution as proposed in Sections 4 and 5 of the report and asso... Approved Open