12/4067M-Replacement service reservoir and valve house building, together with a temporary material storage area and a temporary contractor's parking area, Jacksons Edge Service Reservoir, Jacksons Edge Road, Disley for United Utilities
ApprovedPlanning1 paper
Strategic Planning Board approved this item on Wednesday 20 February 2013. Below is the council's own wording, with the papers it was decided on.
RESOLVED That for the reasons set out in the report and in the update to Board the application be approved subject to the following conditions:- 1. A03FP - Commencement of development (3 years) 2. A01AP - Development in accord with approved plans 3. A06EX - Materials as application 4. A15LS - Submission of additional landscape details 5. A04LS - Landscaping (implementation) 6. A16LS - Submission of landscape/woodland management plan 7. A13LS - Erection of fencing / wall as required 8. A22GR - Protection from noise during construction (hours of construction) 9. Development in accordance with accompanying statements 10. Submission of a scheme which demonstrates how surface water is to be disposed of 11. Temporary Material Storage Area to be used for storage of excavated materials and materials for the construction of the service reservoir only 12. Light Alders field to be fully restored to the satisfaction of the LPA following the completion of development 13. Submission of a programme of archaeological work in accordance with a written scheme of investigation 14. Footpath No. 5 to be fully restored following the completion of the development 15. Removal / amendment of the existing traffic calming on Carr Brow 16. Reinstatement traffic calming arrangements on Carr Brow 17. Resurfacing / reconstruction of Carr Brow, if required, following completion of the works 18. Wheel wash facilities at either end of the temporary road closures. Road sweeper to be available on site for daily cleaning of Jacksons Edge Road throughout the duration of the road closure 19. Traffic Management Plan for diverted traffic to appropriate routes, avoiding Light Alders Lane 20. Creation of a Community Liaison Group 21. Submission of a Construction Method Statement (Prior to consideration of the following application, Councillors D Brown and P Hoyland left the meeting and did not return).
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
ADDITIONAL COMMITTEE REPORT FOR 20TH FEBRUARY 2013 STRATEGIC PLANNING BOARD ______________________________________________________________
Application No: 12/4067M
Location: JACKSONS EDGE SERVICE RESERVOIR, JACKSONS EDGE ROAD, DISLEY
Proposal: Replacement service reservoir and valve house building, together with a temporary material storage area and a temporary contractor's parking area.
Applicant: United Utilities
REASON FOR THE REPORT
Members will recall that this application was deferred from the 9th January 2013 Strategic Planning Board for the following reasons:
1. For further information in respect of the discounted sites 2. Consideration of the impact of using the disused quarry for the temporary material storage area 3. Clarification of the number of motorists that would be displaced as a result of the road closures
APPLICANT’S SUBMISSION
United Utilities have provided the following summary in respect of the discounted sites:
Jacksons Edge Service Reservoir site • Not enough room on site
Disley Amalgamated Sports Club • Could not reach agreement with the landowner • Would cause disturbance to playing field users • Would still need the road closure
Field to East of Disley Amalgamated Sports Club • Could not reach agreement with landowner • Would cause disruption to the properties to the north of Jacksons Edge Road • Would still need the road closure Golf Course • Could not reach a satisfactory agreement with the landowner that would have: 1. ensured to the landowners satisfaction that viability of the Golf Course business could be maintained 2. enabled the timely replacement of Jacksons Edge SR (a strategically important part of the water supply network serving 40,000 customers). 3. Use of the golf course would also cause disruption to the properties on the northern side of Hilton Road
Quarry • Would require the complete clearance of the quarry, and filling of voids, to use the site as a temporary material storage area • Would destroy protected habitats, woodland and harm the character of the landscape, which would take 20-30 years to rejuvenate • Unacceptable in planning policy terms • Need to separate the topsoil, subsoil & mudstone for re-use • Extremely impractical due to the 10 metre change in levels between the quarry edge and the quarry base • Would still require the closure of Jacksons Edge Road for up to 25 weeks to move material from the reservoir to quarry and back, therefore this option would not be of any benefit over the field option • Would require an internal haul road, which would cause permanent harm to the heathland • Public opposition to this site would be likely
Any Site Beyond Jacksons Edge Road
• Discounted due to sustainability considerations and highway impacts
Impact on the use of the disused quarry
United Utilities consider that the use of the quarry may raise different objections, for example in respect of the loss of amenity, biodiversity, woodland and landscape.
Mitigation measures would reduce the impact of the development on the field. It would be returned to its former condition, with little or no impact on trees, protected species or landscape. The use of the quarry could cause long term or permanent damage to protected trees, habitats, protected species and its landscape value and would take 20-30 years to rectify.
The NPPF aims to conserve and enhance biodiversity and recognises the importance of the natural environment to our wellbeing. Policy protection for the natural environment is clear within the Macclesfield Local Plan and runs throughout the NPPF. In the NPPF, the emphasis has moved beyond legally protected species to all national and local priority species.
Traffic Impact
In respect of the traffic impacts United Utilities advise: • They are agreeable to banksmen at either end of Light Alders Lane to manage the periods of closure to allow residential access only, with half barriers
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
12/4067M-Replacement service reservoir and valve house building, together with a temporary material storage area and a temporary contractor's parking area, Jacksons Edge Service Reservoir, Jacksons Edge Road, Disley for United UtilitiesMinutes
14912/4067M-Replacement service reservoir and valve house building, together with a temporary material storage area and a temporary contractor's parking area, Jacksons Edge Service Reservoir, Jacksons Edge Road, Disley for United UtilitiesThis decision
12/4067M-Replacement service reservoir and valve house building, together with a temporary material storage area and a temporary contractor's parking area, Jacksons Edge Service Reservoir, Jacksons Edge Road, Disley for United UtilitiesThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.