Resolved
RESOLVED That for the reasons set out in the report the application be approved subject to the following conditions:- 1. Standard conditions 2. Time limit until 2027 and restoration of site by 2028 3. Control of waste and overall throughput of 75,000tpa 4. All waste unloading/handling to take place within the building 5. Roller shutter doors to remain closed, aside from when in use by vehicles 6. Control over hours of working and receipt of waste 7. Construction management plan 8. Control of pile foundations and method statement 9. Control of floor floating operations and method statement 10. Hours of construction and operation 11. Details of lighting and restrictions on use 12. Noise mitigation scheme 13. Noise levels 14. Scheme of noise monitoring 15. Scheme for dust and litter control 16. Contaminated land investigation 17. Reptile mitigation method statement 18. Pre-commencement badger survey 19. Safeguarding of breeding birds 20. Method statement for invasive species 21. Detailed design of enlarged surface water lagoon 22. Scheme for foul and surface water 23. Control of vehicle movements and limit on total cumulative vehicle movements with landfill operational 24. Access arrangements 25. Sheeting of vehicles 26. Submission of details of building materials 27. Control of water pollution 28. Landscape scheme (whilst building in operation) 29. Final restoration scheme (once building is removed In the event of any changes being needed to the wording of the Board’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Interim Planning and Place Shaping Manager has delegated authority to do so in consultation with the Chairman of the Strategic Planning Board, provided that the changes do not exceed the substantive nature of the Board’s decision. Should this application be the subject of an appeal, authority be delegated to the Interim Planning and Place Shaping Manager in consultation with the Chairman of the Strategic Planning Board to enter into a planning agreement in accordance with the S106 Town and Country Planning Act to secure the Heads of Terms for a S106 Agreement.