Northern Planning Committee, Wednesday 5 April 2017 at 10.00am

16/5475M-The retention of existing moveable ground based communications equipment for a temporary period of nine months, Telephone exchange, 22 Moss Lane, Alderley Edge for Mr Matthew Waugh, Arqiva Ltd (for EE Ltd & Hutchison 3G UK)

Approved Planning 1 paper

Northern Planning Committee approved this item on Wednesday 5 April 2017. Below is the council's own wording, with the papers it was decided on.

Item105

Resolved

RESOLVED That for the reasons in the report the application be approved subject to the following conditions:- 1. Temporary period - 9 months from the date the application was submitted. The equipment shall only be used until 31 August 2017 and then removed from the site by 30 September 2017. 2. Development in accord with approved plans In order to give proper effect to the Committee’s intentions and without changing the substance of the decision, authority is delegated to the Planning and Enforcement Manager, in consultation with the Chairman (or in his absence the Vice Chairman) of Northern Planning Committee to correct any technical slip or omission in the wording of the resolution, between approval of the minutes and issue of the decision notice. (The meeting adjourned for a short break).
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Northern Planning Committee

Summary

This application seeks full planning permission for “the retention of existing moveable ground based communications equipment for a temporary period of nine months.”

The site is positioned within a sustainable but residential location in Alderley Edge.

It is considered that the retention at this location is only acceptable on the basis that meaningful progress has now taken place on identifying a permanent site and therefore satisfies the three threads of ‘sustainability’ as stipulated within the NPPF (2012).

RECOMMENDATION: Approve for a final nine months, subject to conditions

REASON FOR REPORT

The application is to be presented at Northern Planning Committee because it has been ‘called-in’ to committee at the request of Cllr Browne on the 8th February due to the local concerns:

“The residents of Moss Lane/Orchard Green have previously been very understanding with the telephone company (Arquiva Limited). They received written assurance from the applicant that the mast would be temporary in nature and in good faith, have accepted its presence for over two years. The latest application for a further temporary extension has provoked a strong reaction from those residents and the Parish Council. The application should therefore be considered by Northern Planning Committee to enable residents to speak and feel that their concerns are being heard by Cheshire East Council.”

DESCRIPTION OF SITE AND CONTEXT The site is that of the existing traditional exchange on Moss Lane in Alderley Edge which is situated within an established residential area.

DETAILS OF PROPOSAL

The retention of existing moveable ground based communications, a telecommunications mast, equipment for a temporary period of nine months.

RELEVANT HISTORY

15/5502M - The retention of existing moveable ground based communications equipment for a temporary period of six months. – Approved 12 May 2016

POLICIES

Macclesfield Borough Local Plan – saved policies

BE1 (Design principles for new developments) DC3 (Protection of the amenities of nearby residential properties) DC60 (Telecommunications Equipment)

The saved Local Plan policies are consistent with the NPPF and should be given full weight.

Other Material Considerations

National Planning Policy Framework (NPPF) National Planning Practice Framework (NPPG)

National Policy:

The National Planning Policy Framework establishes a presumption in favour of sustainable development. Of particular relevance are chapters 5, 7 and 8.

Cheshire East Local Plan Strategy – Submission Version (CELP)

The following are considered relevant material considerations as indications of the emerging strategy: MP1 (Presumption in Favour of Sustainable Development) SD1 (Sustainable Development in Cheshire East) SD2 (Sustainable Development Principles) SE1 (Design)

CONSULTATIONS (External to Planning)

EHO – No objections VIEWS OF THE PARISH / TOWN COUNCIL

The PC recommends refusal. This will have been in place for a number of years with ongoing renewals. It is unsightly and needs to be removed. It should be considered for a call in to the Northern Planning Committee.

OTHER REPRESENTATIONS

Strong objections from 6 different addresses on the basis of:-

 Unsightly and too close to houses  Ugly blight  Dominates landscape  18 months delay  Further 9 month totally unacceptable  If extended fixed guarantee required  Mast been in pace for two years and CEC should not support further extensions of time as per previous report.

Full contents can be viewed on CEC website

OFFICER APPRAISAL

Key Issues

 Visual Impact on the character of the area,  Impact on the amenity of neighbouring properties

Principle of Development

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
16/5475M-The retention of existing moveable ground based communications equipment for a temporary period of nine months, Telephone exchange, 22 Moss Lane, Alderley Edge for Mr Matthew Waugh, Arqiva Ltd (for EE Ltd & Hutchison 3G UK)Minutes 878 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. 16/5475M-The retention of existing moveable ground based communications equipment for a temporary period of nine months, Telephone exchange, 22 Moss Lane, Alderley Edge for Mr Matthew Waugh, Arqiva Ltd (for EE Ltd & Hutchison 3G UK)This decision
  2. 22/0872M - LAND BETWEEN JUNCTIONS 7 AND 8 OF THE M56: Erection of a Motorway Service Area (MSA), demolition of all existing buildings except for the retention and conversion of one residential building (existing farmhouse) and the part reteApproved
  3. 21/0482N - LITTLE ISLAND LIVERY, HAYMOOR GREEN ROAD, WYBUNBURY, CW5 7HG: Retention of building for use as offices, reception, staff facilities and storage in connection with the existing equine business activities.Approved
  4. 16/3464N Land Adjacent To Chorlton Lane, Chorlton: Change of use of land from agricultural to part agricultural and part keeping of horses. Retention of existing septic tank, stable and field shelter, dog kennel, chicken house and associated hard standing (retrospective) for Ms JonesDeferred
  5. 10/0401M-Revised Application Persuant to Refusal of Application 09/3285m for the Proposed Demolition of a Single Partially Detached Garage and Construction of Two Storey Detached Dwelling and Retention/Alteration of the Existing Dwelling anRefused
  6. 09/0259/FUL - Retention of Hardcore Area for the Storage of Waste Disposal Skips as an Extension to the Existing Skip Hire Business at Betchton Cottage Farm, Cappers Lane, Betchton.Refused

More from Cheshire East Northern Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 Minutes of the Previous MeetingThat the minutes of the meeting held on 24 June 2026 be approved as a correct record. Approved Open
19 Aug 2026 25/2053/FUL - Land Of The Former Knowle House, Sagars Road, Handforth, SK9 3EAThat for the reasons set out in the report the application be APPROVED subject to a Section 106 Agreement to secure t... Approved Open
19 Aug 2026 26/0581/FUL - The Cave, 91 - 95 Mill Street, Macclesfield, SK11 6NNThat the application be REFUSED as detailed in the Officer recommendation for the following reasons; 1. The proposals... Refused Open
19 Aug 2026 25/4532/FUL - LAST ORDERS, 116 - 118 Park Lane, Macclesfield, Cheshire East, SK11 6UAThat the application be delegated back to Officers to REFUSE the application for the following reason; 1. The submitt... Refused Open
19 Aug 2026 Tree Preservation Order 2026 - Alderley Edge - Brocklands, Brook LaneThat the Tree Preservation Order at Brocklands , Brook Lane, Alderley Edge be confirmed with no modifications. The Or... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies