16/5475M-The retention of existing moveable ground based communications equipment for a temporary period of nine months, Telephone exchange, 22 Moss Lane, Alderley Edge for Mr Matthew Waugh, Arqiva Ltd (for EE Ltd & Hutchison 3G UK)
ApprovedPlanning1 paper
Northern Planning Committee approved this item on Wednesday 5 April 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED That for the reasons in the report the application be approved subject to the following conditions:- 1. Temporary period - 9 months from the date the application was submitted. The equipment shall only be used until 31 August 2017 and then removed from the site by 30 September 2017. 2. Development in accord with approved plans In order to give proper effect to the Committee’s intentions and without changing the substance of the decision, authority is delegated to the Planning and Enforcement Manager, in consultation with the Chairman (or in his absence the Vice Chairman) of Northern Planning Committee to correct any technical slip or omission in the wording of the resolution, between approval of the minutes and issue of the decision notice. (The meeting adjourned for a short break).
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
This application seeks full planning permission for “the retention of existing moveable ground based communications equipment for a temporary period of nine months.”
The site is positioned within a sustainable but residential location in Alderley Edge.
It is considered that the retention at this location is only acceptable on the basis that meaningful progress has now taken place on identifying a permanent site and therefore satisfies the three threads of ‘sustainability’ as stipulated within the NPPF (2012).
RECOMMENDATION: Approve for a final nine months, subject to conditions
REASON FOR REPORT
The application is to be presented at Northern Planning Committee because it has been ‘called-in’ to committee at the request of Cllr Browne on the 8th February due to the local concerns:
“The residents of Moss Lane/Orchard Green have previously been very understanding with the telephone company (Arquiva Limited). They received written assurance from the applicant that the mast would be temporary in nature and in good faith, have accepted its presence for over two years. The latest application for a further temporary extension has provoked a strong reaction from those residents and the Parish Council. The application should therefore be considered by Northern Planning Committee to enable residents to speak and feel that their concerns are being heard by Cheshire East Council.”
DESCRIPTION OF SITE AND CONTEXT The site is that of the existing traditional exchange on Moss Lane in Alderley Edge which is situated within an established residential area.
DETAILS OF PROPOSAL
The retention of existing moveable ground based communications, a telecommunications mast, equipment for a temporary period of nine months.
RELEVANT HISTORY
15/5502M - The retention of existing moveable ground based communications equipment for a temporary period of six months. – Approved 12 May 2016
POLICIES
Macclesfield Borough Local Plan – saved policies
BE1 (Design principles for new developments) DC3 (Protection of the amenities of nearby residential properties) DC60 (Telecommunications Equipment)
The saved Local Plan policies are consistent with the NPPF and should be given full weight.
Other Material Considerations
National Planning Policy Framework (NPPF) National Planning Practice Framework (NPPG)
National Policy:
The National Planning Policy Framework establishes a presumption in favour of sustainable development. Of particular relevance are chapters 5, 7 and 8.
Cheshire East Local Plan Strategy – Submission Version (CELP)
The following are considered relevant material considerations as indications of the emerging strategy: MP1 (Presumption in Favour of Sustainable Development) SD1 (Sustainable Development in Cheshire East) SD2 (Sustainable Development Principles) SE1 (Design)
CONSULTATIONS (External to Planning)
EHO – No objections VIEWS OF THE PARISH / TOWN COUNCIL
The PC recommends refusal. This will have been in place for a number of years with ongoing renewals. It is unsightly and needs to be removed. It should be considered for a call in to the Northern Planning Committee.
OTHER REPRESENTATIONS
Strong objections from 6 different addresses on the basis of:-
Unsightly and too close to houses Ugly blight Dominates landscape 18 months delay Further 9 month totally unacceptable If extended fixed guarantee required Mast been in pace for two years and CEC should not support further extensions of time as per previous report.
Full contents can be viewed on CEC website
OFFICER APPRAISAL
Key Issues
Visual Impact on the character of the area, Impact on the amenity of neighbouring properties
Principle of Development
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
16/5475M-The retention of existing moveable ground based communications equipment for a temporary period of nine months, Telephone exchange, 22 Moss Lane, Alderley Edge for Mr Matthew Waugh, Arqiva Ltd (for EE Ltd & Hutchison 3G UK)Minutes
10516/5475M-The retention of existing moveable ground based communications equipment for a temporary period of nine months, Telephone exchange, 22 Moss Lane, Alderley Edge for Mr Matthew Waugh, Arqiva Ltd (for EE Ltd & Hutchison 3G UK)This decision
16/5475M-The retention of existing moveable ground based communications equipment for a temporary period of nine months, Telephone exchange, 22 Moss Lane, Alderley Edge for Mr Matthew Waugh, Arqiva Ltd (for EE Ltd & Hutchison 3G UK)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.