CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Chorley Borough Council
Executive Cabinet, Wednesday 13 September 2023 at 6.30pm

Chorley Quarter One Performance Monitoring Report 2023-24

Noted Executive 1 paper

Executive Cabinet noted this item on Wednesday 13 September 2023. Below is the council's own wording, with the papers it was decided on.

Item23.EC.22

Resolved

That the report be noted. That the report be noted. Reasons for recommendations: To ensure the effective performance monitoring of the Corporate Strategy and safeguard its delivery across 2023/24. Other options considered and rejected: No other options have been considered or rejected. This is because the report does not present any items for decision.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of the report

1. This monitoring report sets out the performance against the delivery of the Corporate Strategy and key performance indicators during the first quarter of 2023/24, covering 1 April 2023 to 30 June 2023

Recommendations to Executive Cabinet

2. That the report be noted.

Reasons for recommendations

3. To ensure the effective performance monitoring of the Corporate Strategy and safeguard its delivery across 2023/24.

Other options considered and rejected

4. No other options have been considered or rejected. This is because the report does not present any items for decision.

Executive summary

5. This report sets out the performance against the Corporate Strategy and key service delivery measures for the first quarter of 2023/24. Performance is assessed based on the delivery of the 2022 Corporate Strategy along with the key service delivery measures for individual services.

6. Overall performance of the Corporate Strategy projects is excellent with 95% (18) rated as complete or green, meaning they are progressing according to schedule. One project (5%) has been rated amber, which provides an early warning sign of potential delays. An action plan for this project is contained within this report. 7. Performance of the Corporate Strategy indicators and key service delivery measures continues to be closely monitored, with 75% of Corporate Strategy measures and 100% of key service delivery measures performing on or above target or within the 5% threshold.

Corporate priorities

8. The report relates to the following corporate priorities:

Housing where residents can live well A green and sustainable borough

An enterprising economy with vibrant Healthy, safe, and engaged communities local centres in urban and rural areas

Background to the report

9. The Corporate Strategy is the key strategic document for the authority and includes performance indicators and projects that focus in delivering the Council’s four priorities.

10. The Corporate Strategy was approved by the Council in November 2022 and includes 19 corporate projects. This includes projects with a focus on the delivery of large-scale ambitious schemes that will have a significant impact on local outcomes and ensuring that Chorley is in the best possible position for the future.

11. Key performance measures for each service have been set so that targets remain challenging and reflective of the Council’s ambitions. These are reviewed annually as part of the service level business planning process. Housing where residents can live well Our commitments: • Deliver affordable and energy efficient housing, • Strive for good quality housing for all, • Work with partners supporting new ways to prevent homelessness, • Support our most vulnerable residents Delivering our Commitments in Quarter One

12. Since the completion and official opening of the new extra care facility at Tatton Gardens in quarter four, the project was shortlisted for three awards in this year’s North West Regional Construction Awards and was awarded Sub-regional Project of the Year Lancashire. This is an outstanding achievement for everyone involved in what is now a fantastic facility providing extra care accommodation for the over 55’s, healthcare provisions, and community facilities, whilst transforming the area and most of all bringing value to the local community. A community event has also been planned to take place during quarter two where residents will have the opportunity to help shape the activities and services that are run from the new Tatton Community Centre. Remaining snagging issues, including to the recreation ground, will continue over the coming quarters.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Chorley Quarter One Performance Monitoring Report 2023-24Report 320 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 25 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present, as expected, virtual
BM
Councillor Beverley MurrayCommittee Member, present
TH
Councillor Terry HowarthCommittee Member, present
AM
Councillor Alistair MorwoodCommittee Member, present
MF
Councillor Margaret FranceCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
CS
Chris SinnottOfficer, expected
CM
Chris MoisterOfficer, in attendance
DW
Dave WhelanOfficer, expected
LM
Louise MattinsonOfficer, expected
NH
Neil HaltonOfficer, expected

All 25 on the meeting page

On this subject at Chorley

Search all
  1. Chorley Quarter One Performance Monitoring Report 2023-24This decision
  2. Chorley Quarter One Performance Monitoring Report 2026/27Noted
  3. Chorley Quarter Four Performance Monitoring Report 2025/26Decided
  4. Chorley Quarter Four Performance Monitoring Report 2025/26Decided
  5. Chorley Quarter Three Performance Monitoring Report 2025-26Decided
  6. Chorley Quarter Three Performance Monitoring Report 2025-26Noted

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies