Queens Road Car Park Enhancement Scheme - Procurement Strategy

Approved Executive 1 paper

Executive Cabinet approved this item on Wednesday 13 September 2023. Below is the council's own wording, with the papers it was decided on.

Item23.EC.23

Resolved

To approve the procurement strategy and evaluation criteria for the enhancement works. 2. To delegate the award of the contract for the Queens Road car park scheme to the Executive Member for Resources. 1. To approve the procurement strategy and evaluation criteria for the enhancement works. 2. To delegate the award of the contract for the Queens Road car park scheme to the Executive Member for Resources. Reasons for recommendations: To provide a modern car parking facility for members of the public which maximises the use of space whilst providing an improved experience for visitors. Other options considered and rejected: To carry out no enhancement works and undertake essential maintenance such as patch repairing. This option was rejected due to the requirement for improved parking facilities, wider parking bays and current on-site hazards.
Word for word from the decision Chorley published for this meeting. Source: democracy.chorley.gov.uk

Follow this further

Built from Chorley's papers

What the report saysPro

Report to Executive Cabinet

Purpose of the report

1. To seek approval for the procurement strategy and delegate contract award for the Queens Road car park enhancement scheme.

Recommendations to Executive Cabinet

2. To approve the procurement strategy and evaluation criteria for the enhancement works.

3. To delegate the award of the contract for the Queens Road car park scheme to the Executive Member for Resources.

Reasons for recommendations

4. To provide a modern car parking facility for members of the public which maximises the use of space whilst providing an improved experience for visitors.

Other options considered and rejected

5. To carry out no enhancement works and undertake essential maintenance such as patch repairing. This option was rejected due to the requirement for improved parking facilities, wider parking bays and current on-site hazards.

Corporate priorities

6. The report relates to the following corporate priorities:

Housing where residents can live well A green and sustainable borough

An enterprising economy with vibrant Healthy, safe and engaged communities local centres in urban and rural areas Background to the report

7. The procurement of the contract is being undertaken in accordance with Chorley Councils procurement regulations for high value contracts.

8. The procurement and evaluation criteria proposed comprise a single stage open tender with suitability questionnaire 60% cost, 25% quality and 15% Social Value split.

9. A competitive open tender is being undertaken through the Chest. All the requirements of CPRs will be followed. Subsequently a formal contract will be entered into with the successful bidder.

10. The tender is currently live on the Chest based on the proposed procurement strategy in order to meet desired timescales as stipulated in the July 2023 Council report. 11. Contract award is to be delegated to the Executive Member for Resources.

Funding

12. The Council approved the budget for the scheme in July 2023.

Climate change and air quality

13. The work noted in this report impacts positively on the following areas of climate change and sustainability targets of the Councils’ Green Agenda.:

a. net carbon zero by 2030 b. limiting or improving air quality, c. improving green areas and biodiversity.

Equality and diversity

14. An impact assessment has been completed with the scheme providing positive Equality, Health, Social and Environmental impacts.

Risk

15. The key risks are summarised below:

Risk Mitigation measures

Health & Safety Appoint a contractor to undertake the enhancement works to mitigate any health and safety risks due to the current condition of the car park surface. Construction Costs Procure contractor in a timely manner after approval to avoid an increase in overall construction costs due to market volatility. Disruption to town centre car parking Clear public communications will be provision undertaken to direct users to other available car parks. Monitoring will take place during the construction period to identify any car parks that are reaching capacity to direct users to other car parks. Comments of the Statutory Finance Officer

16. The costs of these works are within the existing, approved, capital programme as part of the Public Realm Town Centre schemes.

Comments of the Monitoring Officer

17. What is proposed here is high value procurement as classified by our Contract Procurement Rules (CPRs). We will undergo a competitive open tender through the Chest. All the requirements of CPRs will be followed. Subsequently a formal contract will be entered into with the successful bidder.

Report Author: Email: Telephone: Date:

Adam Nickson (Head of [email protected] Property and Development)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Queens Road Car Park Enhancement Scheme: Procurement StrategyReport 92 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 25 attended
AB
Councillor Alistair BradleyExecutive Leader, present
PW
Councillor Peter WilsonDeputy Leader, present, as expected, virtual
BM
Councillor Beverley MurrayCommittee Member, present
TH
Councillor Terry HowarthCommittee Member, present
AM
Councillor Alistair MorwoodCommittee Member, present
MF
Councillor Margaret FranceCommittee Member, present
AL
Councillor Adrian LoweCommittee Member, present
CS
Chris SinnottOfficer, expected
CM
Chris MoisterOfficer, in attendance
DW
Dave WhelanOfficer, expected
LM
Louise MattinsonOfficer, expected
NH
Neil HaltonOfficer, expected

All 25 on the meeting page

On this subject at Chorley

Search all
  1. Queens Road Car Park Enhancement Scheme - Procurement StrategyThis decision
  2. 18/00603/FUL - 1 Queens Road, ChorleyDecided
  3. 3h, 17/00490/FULMAJ - Garside and Son Plumbers, 5-9 Queens Road, Chorley, PR7 1JUApproved
  4. 17/00490/FULMAJ - Garside and Son Plumbers, 5 - 9 Queens Road, Chorley PR7 1JUApproved
  5. 14/00705/FUL - 1 Queens Road, ChorleyApproved
  6. 14/00704/FUL - 3 Queens Road, ChorleyApproved

More from Chorley Executive Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Minutes of meeting Thursday, 9 July 2026 of Executive Cabinetthat the minutes of the Executive Cabinet meeting held on Thursday, 9 July 2026 be confirmed as a correct record for ... Decided Open
17 Sep 2026 Social Value Position Statement 25/26To approve the report and note the impact of Social Value in the Borough. Approved Open
17 Sep 2026 Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther... Noted Open
17 Sep 2026 Capital and Balance Sheet Monitoring Report Q1To approve the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £1.... Approved Open
17 Sep 2026 Chorley Quarter One Performance Monitoring Report 2026/27To note the report and provide feedback where required. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies