To approve the revised capital programme as attached at Appendix A, which includes an amendment to the programme of £5.684m, as detailed at point 11 of this report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report); 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 31st July 2023. 1. To approve the revised capital programme as attached at Appendix A, which includes an amendment to the programme of £5.684m, as detailed at point 11 of this report. 2. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report); 3. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 31st July 2023. Reasons for recommendations: To ensure the Council’s Capital Programme is monitored effectively. Other options considered and rejected: None.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To report the outturn financial position of the Council in respect of the capital programme at 31st July 2023, highlighting key issues and explaining key variances, and to provide an overview of various elements of the Council’s Balance Sheet at 31st July 2023.
Recommendations to Executive Cabinet
2. To approve the revised capital programme as attached at Appendix A, which includes an amendment to the programme of £5.684m, as detailed at point 11 of this report.
3. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report);
4. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances and debtors, at 31st July 2023.
Reasons for recommendations
5. To ensure the Council’s Capital Programme is monitored effectively.
Other options considered and rejected
6. None
Corporate priorities 7. The report relates to the following corporate priorities:
An enterprising economy with vibrant Green and sustainable Borough local centres in urban and local areas
Housing where residents live well Healthy, safe and engaged communities
Background to the report
8. The capital budget for 2023/24 was set at £21.103m at Council in February 2023. This was increased following approval of the 2022/23 outturn to £22.998m.
Section A: Capital Programme
Key issues
9. The total cost of the Council’s capital investment programme for 2023/24 has decreased since the 2022/23 outturn report approved by Cabinet, from £22.998m to £18.191m as at 31st July 2023. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.
10. The breakdown of the net decrease in the programme of £4.807m is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme
11. Budget variations approved since the last monitoring report have resulted in a total increase of £5.580m to the capital programme. The table below details the changes. Table 1: Approved budget changes since the last monitoring report Increase / Increase / (Reduction) Virement (Reduction) Virement To Date ` 2024/25 and From Approved by 2023/24 approved future years £’000 £’000
Asset Improvements (85) This report N/A Strawberry Fields 85 This report N/A Queens Road Car Park 321 Council 18/07/23 Public Realm Town Centre (321) Council 18/07/23 Relocation of the Bengal St 2,000 1,750 Council 18/07/23 Depot Leisure Centre Transfer (244) This report N/A Leisure Centre Improvements 244 This report N/A Play, Recreation and Open Space 75 This report N/A Projects This report Chorley Adaptation Grant 775 increase in N/A grant Tatton Gardens 980 Council 18/07/23 TOTAL 3,055 2,525 (650) 650
12. A re-profiling of budgets from 2023/24 to future years has been undertaken. The total movement of budgets from 2023/24 amounts to £7.862m. The movements are shown in Appendix B and explanations are contained in the major variations section that follows.
Table 2: Slippage and reprofiling across years
Scheme Slippage and Reprofiling £'000 Buckshaw Village Rail Station 696 Chapel St and Surrounding Public Realm 2,297 Public Realm Town Centre 2,379 Town Hall and White Hart Works 1,000 Chorley Health Centre 250 Leisure Centres Improvements - New 1,240 Contract
Total 7,862
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.