AI summaryChorley Council's Executive Cabinet noted the revised 2025/26 capital programme of £15.159m, approving a £63k cut to a shared finance system and £157k more for a hockey pitch.
Written from the decision and the officer reportPDF Pro
OutcomeNotedBudget changes in Table 1 also approved
Money£15.159mRevised total 2025/26 capital programme
What happens next5 working daysImplementation after publication, subject to call-in
Who it affectsCapital projects and finances2025/26 capital programme and balance sheet
What was decided
Cabinet noted the revised capital programme, attached at Appendix A, which includes an amendment of £0.388m since the November 2025 report. Report P3
Cabinet approved budget changes: a £63k reduction in the Technology One Finance System and a £157k increase for the hockey pitch at Buckshaw Village. Report P4, P32, P35
Cabinet noted variations to the programme detailed by scheme at Appendix B and the balance sheet position at 31 December 2025. Report P5, P6
Why
To ensure the Council's capital programme is monitored effectively. Report P9
The Council is required to report quarterly on capital and balance sheet budget monitoring. Report P11
What happens next
The decision will come into force and may be implemented five working days after publication, subject to call-in. Report P70
The Scrutiny Committee is asked to review the capital programme, balance sheet and virements. Report P8
The money
£0.388m Amendment to capital programme since November 2025 Report P3
£63k Reduction in Technology One Finance System (shared with South Ribble) Report P4, P32
£157k Increase to Play, Recreation and Open Space Projects for hockey pitch at Buckshaw Village Report P4, P35
£15.159m Total revised 2025/26 capital programme Report P16, P19
£2.423m Net decrease in 2025/26 capital programme Report P20
£3.492m Actual capital expenditure as at 31 December 2025 Report P22
£2.654m Slippage and reprofiling of budgets from 2025/26 to future years Report P21
£0.040m Forecast underspend on debt interest payable Report P43
£0.216m Forecast over-recovery on interest and investment income Report P43
£0.035m Underspend on Minimum Revenue Provision (MRP) Report P43
Options considered
Rejected: Not reporting (no alternative considered). It is a requirement to report quarterly on capital and balance sheet budget monitoring Report P11
Implications
Financial: Current year council tax collection rate was 85.35% and business rates 81.73%. Report P48, P49
Financial: Commercial sundry debt reduced after a significant single debt write off approved in September 2025. Report P52
Risk: Inflation impact on individual projects must be closely monitored and reported if needed. Report P59
Risk: Non-payment of debt is a significant risk, with a bad debt provision calculated by age. Report P59
Climate: The report has no impact on climate change and environmental considerations are in place. Report P41
Who and where
Council tax payers in Chorley Report P48, P50
Business rates payers in Chorley Report P48, P50
Residents benefiting from capital projects (hockey pitch, flood protection, Astley Hall) Report P34, P35, P37
South Ribble Borough Council (joint finance system partner) Report P32
Timeline
February 2025: Capital budget for 2025/26 set at £46.838m by Council Report P15
After 2025/26 outturn: Capital budget increased to £52.991m Report P15
September 2025: Cabinet approved a decrease of the Capital Programme to £15.975m in quarter one Report P15
November 2025: Cabinet approved an increase of the Capital Programme to £17.582m Report P15
31 December 2025: Balance sheet position and actual capital expenditure of £3.492m reported Report P22, P44
04 February 2026: Report dated Report P69
12 February 2026: Executive Cabinet decision taken
Plain English for the jargon
Capital Programme: The Council's planned spending on long term assets such as buildings, vehicles and infrastructure.
MRP: Minimum Revenue Provision, an amount the Council sets aside each year to repay debt.
Virement: A transfer of budget between spending headings within the capital programme.
S106 contributions: Payments from developers towards local infrastructure, agreed through planning obligations under Section 106 of the Town and Country Planning Act.
Slippage: Budget moved from the current year to a future year because planned spend will not happen this year.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item76
Resolved
To note the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £0.388m since the last capital monitoring report was approved by Cabinet in November 2025, as detailed at Table 1 of this report. 2. To approve the budget changes in Table 1 noted for this report. Approval for this report relates to a £63k reduction in the Technology One Finance System as these costs are shared with South Ribble and an increase to the Play, Recreation and Open Space Projects of £157k to fund the hockey pitch at Buckshaw Village. 3. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report). 4. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 31 December 2025.
Word for word from the decision Chorley published for this meeting.Source: democracy.chorley.gov.uk
1. To report the outturn financial position of the Council in respect of the capital programme at 31 December 2025, highlighting key issues and explaining key variances, and to provide an overview of various elements of the Council’s Balance Sheet at 31 December 2025.
Recommendations to Executive Cabinet
2. To note the revised Capital Programme, attached at Appendix A, which includes an amendment to the programme of £0.388m since the last capital monitoring report was approved by Cabinet in November 2025, as detailed at Table 1 of this report.
3. To approve the budget changes in Table 1 noted for this report. Approval for this report relates to a £63k reduction in the Technology One Finance System as these costs are shared with South Ribble and an increase to the Play, Recreation and Open Space Projects of £157k to fund the hockey pitch at Buckshaw Village.
4. To note the variations to the programme (which are detailed by scheme at Appendix B and referenced within the body of the report).
5. To note the position in the Balance Sheet monitoring section of the report, in respect of cash, investment and loan balances, and debtors, as at 31 December 2025.
Recommendations to Scrutiny
6. The Committee is asked to review the Capital Programme and the Balance Sheet, based on the position as at 31 December 2025 and to comment on the report. 7. The Committee is asked to review the virements made to the Capital Programme during the period, as detailed in Appendix B of the report.
Reasons for recommendations
8. To ensure the Council’s Capital Programme is monitored effectively.
Other options considered and rejected
9. None, it is a requirement to report quarterly on the Capital and Balance Sheet budget monitoring.
Corporate priorities
10. The report relates to the following corporate priority: Housing where residents can live well A green and sustainable borough An enterprising economy with vibrant local centres in urban and rural areas Healthy, safe and engaged communities
Background to the report
11. The Capital Budget for 2025/26 was set at £46.838m by Council in February 2025. This was increased following approval of the 2025/26 outturn to £52.991m. Then decreased to £15.975m in quarter one following Cabinet approval in September 2025. In November 2025, Cabinet approved an increase of the Capital Programme to £17.582m.
12. Following the changes detailed in this report, the total programme for 2025/26 now stands at £15.159m the details of which are shown in Appendix B.
Section A: Capital Programme
Key issues
13. The total cost of the Council’s capital investment programme for 2025/26 has decreased since the last report from £17.582m to £15.159m. The change reflects variations approved since the last report, along with those contained within this report. A summary of the total costs of the programme, and the funding of this, is detailed at Appendix A.
14. The breakdown of the net decrease in the programme of £2.423m in 2025/26 is detailed in Appendix B. The net variation includes those variations approved since the previous monitoring report and variations in respect of the reprofiling of budgets within the existing programme net increase. 15. Budget variations approved since the previous monitoring report are shown in the table below; there has been an increase in the 2025/26 capital programme of £0.231m and for 2026/27 and increase of £0.157m. Virements between the schemes totals £0.000m. The table below details the changes.
16. A slippage and re-profiling of budgets from 2025/26 to future years has been undertaken. The total movement of budgets from 2025/26 amounts to £2.654m. The movements are shown in Appendix B and explanations are contained in the major variations section that follows.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Monitoring Report Q1To note the 2026/27 forecast outturn for revenue and reserves, based on the position at 31 July 2026. 2. To note ther...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.