Resolved
RESOLVED that, having considered the summary findings of the key audit reviews set out at Appendix One, the performance as at quarter three against the Internal Audit Plan for 2016-17 be noted.
Audit and Procurement Committee noted this item on Monday 20 February 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that, having considered the summary findings of the key audit reviews set out at Appendix One, the performance as at quarter three against the Internal Audit Plan for 2016-17 be noted.
The purpose of this report is to provide the Audit and Procurement Committee with an update on the internal audit activity for the period April to December 2016, against the Internal Audit Plan for 2016-17.
Audit and Procurement Committee is recommended to:
1. Note the performance as at quarter three against the Internal Audit Plan for 2016-17.
2. Consider the summary findings of the key audit reviews (attached at Appendix One).
1 List of Appendices included:
Appendix One - Summary Findings from Key Audit Reports Completed between October and December 2016
Other useful background papers:
None
Has it or will it be considered by scrutiny?
No other scrutiny consideration other than the Audit and Procurement Committee
Has it, or will it be considered by any other council committee, advisory panel or other body?
No
Will this report go to Council?
No
2 Report title: Quarter Three Internal Audit Progress Report 2016-17
1. Context (or background)
1.1This report is the second monitoring report for 2016-17, which is presented in order for the Audit and Procurement Committee to discharge its responsibility 'to consider summaries of specific internal audit reports as requested' and 'to consider reports dealing with the management and performance of internal audit'.
2. Options considered and recommended proposal
2.1Delivering the Audit Plan
The key target facing the Internal Audit Service is to complete 90% of its work plan by the 31st March 2017. The chart below provides analysis of progress against planned work for the period April to December 2016.
Chart One: Progress against delivery of Internal Audit Plan 2016-17
As at the end of December 2016, the Service had completed 63% of the Audit Plan against a planned target of 70%. Whilst the annual target is to complete 90% of the work plan, the quarterly targets which are set in quarters one, two and three are based on completing 100% of the plan, which reflects that the Service will always strive to achieve this. However, from a practical perspective, achieving 100% is generally unfeasible. The reasons for this are largely down to customers requesting a change in the timing of a review, or the focus of a review being super-ceded by other events. As a result, the formal target is 90%. Consequently, whilst the Service is slightly behind the quarter three target, it remains broadly on track to achieve the formal annual target of 90% by the end of 2016-17.
3 2.2 Other Key Performance Indicators (KPIs)
The table overleaf shows a summary of the performance of Internal Audit for 2016-17 to date against five KPIs, with comparative figures for the financial year 2015-16. There are two indicators (i.e. draft report to deadline and audit delivered within budget days) where the Service’s current performance is currently below expectations. Targeted actions to make improvements in these areas remain on-going. These include team development sessions, weekly progress meetings and an increased focus on time planning within individual audits. Whilst it is management’s view that progress is being made, the results of this will take time to embed in a sustained way.
Table One: Internal Audit Key Performance Indicators 2016-17
Performance Measure Target Performance Performance Q3 2016-17 2015-16
Planned Days Delivered 100% 71% 96% (Pro rota against agreed plan)
Productive Time of Team 90% 88% 88% (% of work time spent on audit work)
Draft Report to Deadline 80% 74% 74% (Draft issued in line with date agreed)
Final Report to Deadline 80% 96% 91% (Final issued within 4 weeks of draft)
Audit Delivered within Budget Days 80% 70% 68%
2.3Audits Completed to Date
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarter Three Internal Audit Progress Report 2016-17Report | 124 KB | DownloadRead as text |
Follow Audit and Procurement Committee at Coventry and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | Internal Audit Plan 2026/27RESOLVED that, the Audit and Procurement Committee considered and approves the draft Internal Audit Plan for 2026-27,... | Approved | Open |
| 22 Jun 2026 | Outstanding IssuesRESOLVED that the Audit and Procurement Committee notes the report. | Decided | Open |
| 22 Jun 2026 | Work Programme 2026/2027RESOLVED that the Audit and Procurement Committee notes the Work Programme for 2026-27. | Decided | Open |
| 16 Mar 2026 | Exclusion of Press and PublicRESOLVED that the Audit and Procurement Committee agrees to exclude the press and public under Sections 100(A)(4) of ... | Agreed | Open |
| 16 Mar 2026 | 2025/26 Third Quarter Financial Monitoring Report (to December 2025)RESOLVED that, the Audit and Procurement Committee note the content of the report and confirms that it has no recomme... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.