REGINA ROAD PROJECT - PROJECT UPDATE AND NEXT STEPS

Agreed Executive 3 papers

Cabinet agreed this item on Monday 15 July 2024. Below is the council's own wording, with the papers it was decided on.

Item172/24

Resolved

Cabinet RESOLVED to: 2.1. To agree an updated approach to phasing to ensure the delivery of 225 grant funded new Council homes in respect of planning, demolition, and construction. The redevelopment will only include 2 phases being: 2.1.1 Phase 1, comprising 225 new Council homes (minimum 200 social rented and up to 25 leaseholder/freeholder products) and kindergarten/ community facility (previously phases 1 & 2). 2.1.2 Phase 2, comprising a minimum 155 private homes. 2.2 To note that the procurement of a demolition contractor is being progressed in line with delegations set out in the Annual Procurement Plan
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

Recommendation

For the reasons set out in the report and its appendices, Cabinet is recommended: 2.1. To agree an updated approach to phasing to ensure the delivery of 225 grant funded new Council homes in respect of planning, demolition, and construction. The redevelopment will only include 2 phases being:

2.1.1. Phase 1, comprising 225 new Council homes (minimum 200 social rented and up to 25 leaseholder/freeholder products) and kindergarten/ community facility (previously phases 1 & 2).

2.1.2. Phase 2, comprising a minimum 155 private homes.

2.2To note that the procurement of a demolition contractor is being progressed in line with delegations set out in the Annual Procurement Plan

Reasons for recommendations

3.1Following the decision of Cabinet on 25 October approving the direct delivery of 225 new homes at Regina Road by the Council, the Council was successfully awarded affordable housing grant funding by the Greater London Authority (GLA). In order to achieve grant milestones a re-ordering of phasing has been considered which has informed a new planning and construction strategy.

3.2The recommendation for rephasing ensures a more streamlined approach to the delivery of 225 new Council homes (minimum 200 social rented and up to 25 leaseholder/freeholder products). A masterplan planning approach, covering the entirety of the site also supports this updated approach.

3.3The Council is currently engaged in the procurement of a demolition contract for part of Phase 1. The procurement of the demolition contractor is being progressed in line with the Annual Procurement Plan. The northern half of the estate will be cleared through demolition works over a period of approximately a year. The last remaining households will either be rehoused by the Council or remaining existing leaseholder’s properties will be purchased during this period. The sub-phasing of Phase 1 which relate specifically to the forthcoming Demolition Construction Contract are:

3.3.1. Phase 1a - The first Tower no.s 1 to 87 Regina Road and;

3.3.2. Phase 1b - 89 to 99 and 101 to 123 Regina Road.

3.4A phasing plan for Demolition Construction Phases 1a and 1b is included in Appendix 1, outlined in red.

4. BACKGROUND AND DETAILS

4.1This report follows on from the statutory consultation undertaken with residents over the period 13 December 2022 to 26 January 2023, as authorised by Cabinet on 16 November 2022 (Key Decision ref 5122EM) in accordance with Section 105 of the Housing Act 1985 and, to the extent relevant, under section 137 of the Housing Act 1996 on proposals to refurbish or demolish and redevelop the three tower blocks and certain other properties within the Regina Road estate.

4.2Cabinet subsequently agreed on 22 March 2023 (Key decision ref 8622EM), based on the outcome of the statutory and other consultations, that a Landlord Offer be put to a Ballot of residents eligible to vote under the rules of the GLA.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Demolition Construction Phasing Plan /24Appendix 1 201 KB Download
PDF
Equality Analysis Form /24Appendix 2 391 KB Download
PDF
REGINA ROAD PROJECT: PROJECT UPDATE AND NEXT STEPSReport 231 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 14 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, present
MG
Councillor Maria GatlandCommittee Member, present
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, present
SR
Councillor Scott RocheCommittee Member, present
AS
Councillor Andy StranackCommittee Member, present
KK
Katherine KerswellOfficer, present
EJ
Elaine JacksonOfficer, present
DJ
Debbie JonesOfficer, present

All 14 on the meeting page

On this subject at Croydon

Search all
  1. REGINA ROAD PROJECT - PROJECT UPDATE AND NEXT STEPSThis decision
  2. Regina Road Redevelopment Project Update (Part A)Agreed
  3. Update on Regina Road (Part A)Agreed
  4. 25/02016/OUT - Regina Road Estate, Regina Road and Sunny Bank, South Norwood, London, SE25 4TTDecided
  5. Regina Road Project - Selection of Delivery Model - Part AAgreed
  6. Regina Road Project – Outcome of Ballot and Next StepsAgreed

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies