London Borough of Croydon
Cabinet, Wednesday 19 November 2025 at 6.30pm

Update on Regina Road (Part A)

Agreed Executive 1 paper

AI summaryCroydon Cabinet noted the November 2025 update on the Regina Road estate redevelopment, with demolition underway, planning consent secured for up to 340 new homes, and main build contract award due February 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet noted the Regina Road redevelopment update
Money£166m project budgetBudget approved February 2025 within HRA plan
What happens nextCPO decision winter 2025/26Main build contract award due February 2026
Who it affectsRegina Road estate residentsAbout 100 households still living on estate

What was decided

The Executive Mayor and Cabinet agreed to note the contents of the project update report on the Regina Road redevelopment. Report 2.1, P7

The update covered demolition of the first tower block, a unanimous resolution to grant planning permission, procurement of a main build contractor, and ongoing rehousing of residents. Report 1.5, P26, P29, P36

Why

To support the provision of information to Cabinet, Members and Croydon residents on a major regeneration project. Report P9

The redevelopment contributes to Executive Mayor's Priority 4, demonstrating significant investment in new Council housing stock and safe, well-designed homes. Report 1.6

What happens next

A Key Decision on whether to proceed with a Compulsory Purchase Order covering all interests in the red-line redevelopment area is expected in winter 2025/26. Report P38

The Pre-Construction Services Agreement with the preferred main contractor is anticipated in November 2025, with the Design and Build contract award due February 2026. Report P29

Full planning consent is targeted by end November 2025 and the formal start on site of Phase 1 new build works is targeted by end March 2026. Report P26, P45

The money

  • £166m Approved project budget for Regina Road Phase 1 within the 2025-26 HRA business plan Report P53
  • £53.508m Total confirmed grant funding in the 2025-26 HRA business plan Report P41
  • £52.25m Greater London Authority affordable housing grant funding for Regina Road Report P42
  • £1.258m Grant from the Ministry of Housing, Communities and Local Government's Brownfield Land Release Fund Report P42, P60
  • £9.6m Spend from project inception to March 2025 Report P58
  • £2.5m Spend from April 2025 to August 2025 Report P58
  • £11.5m Forecast spend for the remainder of the financial year Report P58

Options considered

  • Rejected: Consider alternative approaches to the redevelopment. The report is a project update for information only, so no alternative options were considered. Report P54

Implications

  • Financial: Project is funded by £52.25m GLA grant, £1.258m Brownfield Land Release Fund grant, and Council resources, with significant cost risks including contractor pricing, unforeseen works and price inflation. Report P42, P53
  • Legal: Council may need to use Compulsory Purchase Order powers under the Acquisition of Land Act 1981 if agreements with leaseholders and freeholders cannot be reached, with compensation disputes handled by the Upper Tribunal. Report P68, P69
  • Legal: Council must continue to comply with the approved Landlord Offer and the GLA Affordable Housing Capital Funding Guide to avoid grant being terminated or reclaimed. Report P65, P71, P72
  • Equalities: Public Sector Equality Duty applies; an Equality Impact Assessment completed in 2023 and updated in 2025 identifies older people, disabled residents, families with young children, and minoritised households as affected groups, with targeted mitigations including accessible rehousing, translation support and trauma-informed engagement. Report P74, P75, P76
  • Risk: Key monitored risks are GLA grant funding delivery requirements, timely rehousing and vacant possession, project management and governance, and financial control of contractor pricing and inflation. Report P50, P51, P52, P53
  • Staffing: Twice-weekly drop-in sessions on the estate and dedicated Housing team officers are supporting tenants and leaseholders through rehousing and decant. Report P51

Who and where

  • Approximately 100 households remaining on the Regina Road estate within the red-line redevelopment area Report P36
  • Leaseholders and freeholders on the estate, who the Council is seeking to buy back from, with compulsory purchase powers being considered as a last resort Report P37, P38
  • Secure tenants, who may be rehoused by agreement or via possession proceedings under Ground 10 of Schedule 2 of the Housing Act 1985 if agreement is not reached Report P70
  • Users of the Portland Bill nursery on the estate, proposed to be temporarily relocated to a nearby Council-owned premises Report P39
  • Future residents of the 225 affordable Council homes in Phase 1 and up to 115 private sale homes in Phase 2 Report P25, P29

Timeline

  • 2021: ITV news report drew national attention to unacceptable living conditions on Regina Road, including severe damp and mould Report 1.2
  • 16 November 2022: Cabinet approved the Residents' Charter providing a framework for consultation Report 1.3
  • 13 December 2022 to 26 January 2023: Statutory consultation on refurbishment or demolition and redevelopment of the three tower blocks and certain other properties Report 5.4
  • 22 March 2023: Cabinet agreed that a Landlord Offer be put to a Ballot of eligible residents under GLA rules Report 5.5
  • 26 April and 22 May 2023: Ballot held in which 88.1% of eligible voters supported the Landlord Offer to redevelop their homes Report 1.4
  • 26 July 2023: Cabinet approved demolition of existing buildings and a redevelopment project including 225 affordable Council homes
  • 25 October 2023: Cabinet approved the direct delivery of the redevelopment by the Council Report 5.7
  • 15 July 2024: Last Cabinet project update approved a revised phasing approach, condensing three phases into two, following GLA allocation of circa £54m Report 5.1, 5.8, P80
  • November 2024: £1.258m grant received from the Brownfield Land Remediation Fund Report P60
  • January 2025: Demolition contractor Colemans took site possession of block 1-87 Regina Road Report P45
  • June 2025: Planning application submitted to the Local Planning Authority for up to 340 new homes across two phases Report P24, P25
  • August 2025: Structural demolition of block 1-87 commenced Report P45
  • 16 October 2025: Planning Committee unanimously resolved to grant planning permission for the redevelopment Report P26
  • November 2025: Anticipated award of the Pre-Construction Services Agreement to the preferred main contractor Report P29
  • end November 2025: Full planning consent targeted once legal agreement is completed and any direction by the London Mayor is concluded Report P26
  • December 2025/January 2026: Full demolition of block 1-87 anticipated to be complete Report P45
  • winter 2025/26: Key Decision expected on whether to proceed with a Compulsory Purchase Order Report P38
  • February 2026: Design and Build contract award for the main contractor due Report P29
  • end March 2026: Formal start on site of Phase 1 new build works targeted for grant funding purposes Report P45
  • spring 2026: Targeted start of new build works and delivery of a temporary office and community use space on the estate Report P45, P47

Plain English for the jargon

  • LPS: Wates Large Panel System, the construction type used for the original Regina Road tower blocks in the 1960s
  • CPO: Compulsory Purchase Order, a legal process allowing the Council to acquire land for redevelopment where owners are unwilling to sell by agreement
  • GLA: Greater London Authority, which provides affordable housing grant funding
  • MUGA: Multi-Use Games Area, an outdoor sports facility included in the redevelopment proposals
  • LPA: Local Planning Authority, which is Croydon Council in its separate planning function from its role as applicant
  • HRA: Housing Revenue Account, the ring-fenced account that funds Council housing
  • EQIA: Equality Impact Assessment, completed in 2023 and updated in 2025 for the redevelopment
  • PSED: Public Sector Equality Duty under Section 149 of the Equality Act 2010
  • PCSA: Pre-Construction Services Agreement, a preliminary contract with the main contractor
  • MHCLG: Ministry of Housing, Communities and Local Government, which awarded the Brownfield Land Release Fund grant
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item84/25

Resolved

For the reasons set out in the report and its appendices, the Executive Mayor and Cabinet AGREED 2.1 To note the contents of this project update report.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The last Regina Road project update report to Cabinet was provided on 15 July 2024. This November 2025 update report is provided to inform of latest progress and key considerations.

1.2In 2021 Regina Road gained national attention following an ITV news report revealing serious concerns about the living conditions on the estate. Reports informed that conditions were unacceptable, highlighting major health and safety concerns including severe damp and mould. The issues were noted to have arisen owing to a range of factors including failure to resolve key maintenance issues, failings in the response to the worsening conditions highlighted by residents, and the estate suffering from a lack of investment over many years. It was deemed that there was a need for urgent intervention to address the issues and provide safe, high quality homes.

1.3The Council subsequently committed to take action to address past failures and ensure that this is done in consultation with residents. The Residents’ Charter was produced and approved at Cabinet on 16 November 2022, providing a framework for the consultation.

1.4In 2023, 88.1% of eligible residents voted in favour of demolishing and rebuilding the estate through a formal ballot. The proposed redevelopment is one of the biggest regeneration projects in Croydon in recent years and reflects the Council’s commitment to building high quality new council homes. The redevelopment process is advancing swiftly, and several major milestones have recently been achieved.

1.5Key areas of progression on the project since the last Cabinet update include commencement of demolition of the first tower block, obtaining unanimous approval from Planning Committee for the planning application to redevelop the estate, and a successful major procurement process to identify the main build contractor for Phase 1 in anticipation of starting new build works in spring 2026. The detail of these major project milestones and associated activities are outlined in the report.

1.6The Regina Road redevelopment contributes to the Executive Mayor’s Priority 4 by demonstrating significant investment into new Council housing stock and providing safe, well-designed new homes that are in keeping with the local area.

Recommendations

For the reasons set out in the report and its appendices, the Executive Mayor and Cabinet is recommended to agree:

2.1To note the contents of this project update report.

Reasons for recommendations

To support the provision of information to Cabinet, Members and Croydon residents. 4. CONTRIBUTION TO EXECUTIVE MAYOR’S BUSINESS PLAN

Outcome 1: The Outcome 2: Outcome 3: Outcome 4: Outcome 5: Council balances Croydon is a place Children and Croydon is a People can lead its books, listens of opportunity for young people in cleaner, safer healthier and to residents and business, earning Croydon have and healthier independent delivers good and learning. the chance to place, a borough lives for longer. sustainable thrive, learn and we’re proud to services. fulfil their call home. potential.

✓

5. BACKGROUND AND DETAILS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on Regina Road (Part A)Report 161 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 15 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, present
MG
Councillor Maria GatlandCommittee Member, present
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, present
SR
Councillor Scott RocheCommittee Member, apologies
AS
Councillor Andy StranackCommittee Member, present
EJ
Elaine JacksonOfficer, expected
AM
Annette McPartlandOfficer, expected
DA
Doutimi AsehOfficer, expected

All 15 on the meeting page

On this subject at Croydon

Search all
  1. Update on Regina Road (Part A)This decision
  2. Regina Road Redevelopment Project Update (Part A)Agreed
  3. 25/02016/OUT - Regina Road Estate, Regina Road and Sunny Bank, South Norwood, London, SE25 4TTDecided
  4. Regina road project - project update and next stepsAgreed
  5. Regina Road Project - Selection of Delivery Model - Part AAgreed
  6. Regina Road Project – Outcome of Ballot and Next StepsAgreed

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies