Cabinet, Wednesday 24 June 2026 at 7.30pm

Regina Road Redevelopment Project Update (Part A)

Agreed Executive 1 paper

AI summaryCabinet noted a progress update on the Regina Road estate redevelopment. The £171m Phase 1 project to build 225 affordable Council homes has begun on site, with first handovers expected from 2028 and full completion estimated by 2032.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedInformation only, no substantive resolution
Money£171m revised Phase 1 budgetExcludes inflation, up 3% on February 2025 figure
What happens nextFirst new build handovers from 2028Final sub-phase of Phase 1 currently anticipated by 2032
Who it affectsRegina Road estate residents and CroydonAround 90 households still to rehouse from 191 homes

What was decided

The Executive Mayor and Cabinet agreed to note the Regina Road Redevelopment Project Update, with a separate Part B report also considered. Report 2.1

Why

The report is a project update for information only, covering progress since the last Cabinet update on 19 November 2025. Report P6, P10, P50

What happens next

Lovell Partnerships will deliver Phase 1 in multiple sub-phases, starting with 30 new homes in Block A, due to complete in 2028. Report P24, P29, P30

A temporary office and community space is due on the estate by autumn 2026, with the procurement programme having slipped from spring 2026. Report P25, P30

The Council will continue negotiated property acquisitions while progressing the Compulsory Purchase Order made on 23 March 2026 as a last resort. Report P36, P37, P63

The money

  • £171m Revised Phase 1 project budget approved in February 2026, excluding inflation Report P48
  • £166m Previous project budget included in February 2025 HRA business plan, excluding inflation Report P48
  • £52.25m Adjusted GLA affordable housing grant allocation to Regina Road Report P41
  • £54m Original GLA grant allocation, including element for Malton House decant site Report 5.8, P41
  • £53.508m Total confirmed grant funding included in 2026-27 HRA business plan Report P40
  • £1.258m Brownfield Land Release Fund grant from MHCLG Report P41
  • £9.6m Cumulative project spend from inception to March 2025 Report P54
  • £7.4m Forecast additional spend in 2025-26 Report P54
  • £10.3m 2025-26 in-year project budget Report P54

Options considered

  • Chosen: Note the project update. Report is a project update for information only Report P50

Implications

  • Financial: Revised £171m Phase 1 budget excludes inflation; an additional provision for cost inflation is held in the HRA business plan and under ongoing review. Report P48, P53, P54
  • Legal: Council made a Compulsory Purchase Order on 23 March 2026 to acquire all legal interests on the estate, as a last resort if negotiations fail; compensation disputes can run up to 6 years. Report P37, P63
  • Legal: Council must comply with the GLA grant funding agreement and the Affordable Housing Capital Funding Guide; material deviations from the Landlord Offer risk grant clawback. Report P65, P66, P67
  • Equalities: Updated 2025 Equality Impact Assessment identifies impacts on older people, disabled residents, families with young children and minoritised households, with mitigations including personalised rehousing, accessible design and the right to return for secure tenants. Report P70, P71
  • Risk: Principal risk of failing to start on site by end of March 2026 has been resolved through start on 30 March 2026, but ongoing delivery risk to grant retention remains. Report P45
  • Risk: Financial risks include mains works contractor pricing, unforeseen costs from physical due diligence, and price inflation; cost consultant Pellings is monitoring. Report P48
  • Staffing: Lovell contract includes social value commitments: 35% of jobs to Croydon residents, one in ten construction workers as apprenticeships or training, 5% of vacancies for vulnerable or disadvantaged residents, and 20% of sub-contract value from borough-based firms. Report P26

Who and where

  • Around 90 households still on the estate (75 tenant, 15 leasehold/freehold), down 10 since November 2025 Report P35
  • Leaseholders and freeholders, with 10 buy-back purchases completed and discussions ongoing with most of the remaining 15 Report P36
  • A utility provider that had lodged a holding objection to the CPO, which has now been withdrawn Report P37
  • Future occupants of the 225 affordable Council homes in Phase 1 and up to 115 homes proposed for private sale in Phase 2 Report P20, P24

Timeline

  • November 2022: Cabinet decision to progress the project Report P76
  • 13 December 2022 to 26 January 2023: Statutory consultation on refurbishment versus demolition and redevelopment Report 5.4
  • April-May 2023: Landlord Offer put to ballot of residents Report 5.6, P76
  • 26 July 2023: Cabinet approved demolition and redevelopment to 225 affordable Council homes following 88.1% vote in favour Report 5.6, P59
  • 25 October 2023: Cabinet approved direct delivery of the redevelopment by the Council Report 5.7, P82
  • 15 July 2024: Cabinet approved revised two-phase approach after GLA grant allocation of around £54m Report 5.8, P82
  • January 2025: Demolition contractor took possession of 1-87 Regina Road tower Report P28, P76
  • June 2025: Planning application submitted to the Local Planning Authority Report P19, P76
  • October 2025: Planning Committee voted unanimously in support Report P19, P78
  • January 2026: Full planning consent secured following GLA approval; demolition of 1-87 tower completed Report P19, P28, P78
  • February 2026 (half term): Portland Bill Nursery relocated to Carmichael Road Report P38
  • Autumn 2026: Planned delivery of temporary office and community space on the estate Report P25, P30, P79
  • 2028: First new build residential handovers expected Report P29, P30, P80
  • 2032: Final sub-phase of Phase 1 currently anticipated to complete, subject to review Report P30
  • 12 March 2026: Executive Mayor approved making of a Compulsory Purchase Order Report P37
  • 23 March 2026: CPO made by the Council; main build contract entered with Lovell Report P24, P37, P63
  • 27 March 2026: Pre-Construction Services Agreement and Design and Build Contract signed with Lovell Report P24
  • 30 March 2026: Formal start on site of Phase 1 new build works, meeting GLA grant requirement Report P29, P45

Plain English for the jargon

  • LPS: Wates Large Panel System, the construction method used for the original tower blocks in the 1960s
  • CPO: Compulsory Purchase Order, a legal mechanism allowing the Council to acquire land needed for the redevelopment
  • GLA: Greater London Authority, the main grant funder for the affordable homes
  • HRA: Housing Revenue Account, the Council's ringfenced landlord account for council housing
  • MUGA: Multi-Use Games Area, an outdoor sports facility included in the plans
  • LPA: Local Planning Authority, the body that determines planning applications (in Croydon, the Council itself, acting in a separate role from the applicant)
  • EQIA: Equality Impact Assessment, assessing effects of the scheme on groups with protected characteristics
  • Landlord Offer: The Council's formal proposal put to residents in ballot, covering rehousing terms, leaseholder offers and design commitments
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43/26

Resolved

For the reasons set out in this report and Part B report, the Executive Mayor and Cabinet resolved to AGREED to note the Regina Road Redevelopment Project Update.
Word for word from the decision Croydon published for this meeting. Source: democracy.croydon.gov.uk

Follow this further

Built from Croydon's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1In 2021 Regina Road gained national attention following an ITV news report revealing serious concerns about the living conditions on the estate. Reports informed that conditions were unacceptable, highlighting major health and safety concerns including severe damp and mould. The issues were noted to have arisen owing to a range of factors including failure to resolve key maintenance issues, failings in the response to the worsening conditions highlighted by residents, and the estate suffering from a lack of investment over many years. It was deemed that there was a need for urgent intervention to address the issues and provide safe, high quality homes. 1.2 In May 2022 the Executive Mayor committed to take action to address past failures and ensure that this was done in consultation with residents. The Residents’ Charter was produced and approved at Cabinet on 16 November 2022, providing a framework for the consultation.

1.3In 2023, 88.1% of eligible residents voted in favour of demolishing and rebuilding the estate through a formal ballot. The proposed redevelopment is one of the biggest regeneration projects in Croydon in recent years, and reflects the Council’s commitment to building high quality new Council homes.

1.4The redevelopment process is advancing swiftly, and several major milestones have recently been achieved. Key areas of progression on the project since the last Cabinet update include completing demolition of the first tower block, obtaining planning consent for the estate redevelopment following unanimous approval from Planning Committee, procuring and entering into a contract with the main contractor for Phase 1, and commencing works on site by March 2026 in line with GLA grant funding requirements. The detail of these major project milestones and associated activities are outlined in the report.

1.5The Regina Road redevelopment contributes to the Executive Mayor’s Priority 4 by demonstrating significant investment into new Council housing stock and providing safe, well-designed new homes that are in keeping with the local area, and residents are proud to call home.

Recommendations

2.1For the reasons set out in this report and Part B report, the Executive Mayor and Cabinet is recommended to AGREE to note the Regina Road Redevelopment Project Update.

Reasons for recommendations

To provide a progress update to Cabinet, Members and Croydon residents on the Regina Road Development Project.

4. CONTRIBUTION TO EXECUTIVE MAYOR PERRY’S BUSINESS PLAN

Outcome 1: The Council Outcome 2: Croydon is Outcome 3: Children Outcome 4: Croydon Outcome 5: People balances its books, a place of opportunity and young people in is a cleaner, safer and can lead healthier listens to residents and for business, earning Croydon have the healthier place, a and independent delivers good and learning. chance to thrive, learn borough we’re proud lives for longer. sustainable services. and fulfil their to call home. potential.

✓

5. BACKGROUND AND DETAILS 5.1 This report provides an update on core aspects of the project covering the period from the last Cabinet update report on 19 November 2025.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Regina Road Redevelopment Project Update (Part A)Report 172 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
MJ
Mayor Jason PerryChair, present
JB
Councillor Jeet BainsCommittee Member, present
JC
Councillor Jason CummingsCommittee Member, apologies
LH
Councillor Lynne HaleCommittee Member, present
YH
Councillor Yvette HopleyCommittee Member, present
OK
Councillor Ola KoladeCommittee Member, present
AS
Councillor Andy StranackCommittee Member, apologies
AS
Councillor Alasdair StewartCommittee Member, present
RW
Councillor Robert WardCommittee Member, present
EJ
Elaine JacksonOfficer, expected
HC
Hannah CretneySecretary, expected
AM
Adrian MaySecretary, expected

On this subject at Croydon

Search all
  1. Regina Road Redevelopment Project Update (Part A)This decision
  2. Update on Regina Road (Part A)Agreed
  3. 25/02016/OUT - Regina Road Estate, Regina Road and Sunny Bank, South Norwood, London, SE25 4TTDecided
  4. Regina road project - project update and next stepsAgreed
  5. Regina Road Project - Selection of Delivery Model - Part AAgreed
  6. Regina Road Project – Outcome of Ballot and Next StepsAgreed

More from Croydon Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Croydon Youth Justice Plan 2026/27For the reasons set out in the report and its appendix the Executive Mayor and Cabinet AGREED : The plan (Appendix A)... Agreed Open
23 Sep 2026 Temporary Accommodation Strategy and Action PlanFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED : 3.1 Approve the Temporary Accommodati... Agreed Open
23 Sep 2026 Crisis Resilience FundFor the reasons set out in this report and its appendices the Executive Mayor and Cabinet AGREED to: 3.1 Accept the a... Agreed Open
23 Sep 2026 Review of Council Tax Support Scheme 2027-28For the reasons set out in the report and its appendices the Executive Mayor and Cabinet RESOLVED : 2.1 to agree to a... Agreed Open
23 Sep 2026 2026-27 Period 3 Financial Performance ReportFor the reasons set out in the report, the Executive Mayor and Cabinet AGREED to: 2.1 Note the General Fund revenue b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies