RESOLVED to: 1) Note the current Regeneration Programme and likely future projects resulting from recent funding announcements; 2) Note the current review of governance arrangements for the Regeneration Programme and the proposed report for consideration by Cabinet members in due course. 3) Agree to the proposed role of the County Council as an agent and commissioner of works in support of the Long Eaton Town Deal programme; and 4) Agree to the reallocation of previously committed capital funding to the nominated projects as set out in the report and tabulated in Appendix 1 to the report.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Regeneration Programme Pipeline (Cabinet Member for Infrastructure and Environment)
1. Divisions Affected
1.1County-wide
2. Key Decision
2.1This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To provide Cabinet with an overview of progress on key projects within the current Regeneration Programme, to seek approval for critical requirements on one of these projects and to agree reallocation of programme funding.
4. Information and Analysis
4.1Derbyshire County Council has an active Regeneration Programme consisting of a pipeline of over 50 major projects, framed around four broad programme areas which are:
Market Towns Derwent Valley Corridor Growth Zone South Growth Zone North 4.2 Projects within the Programme have been initiated either by the Council (e.g. transport schemes such as Ashbourne Relief Road), by Government (e.g. town deal proposals) or by district/borough councils (e.g. Hollis Lane Link Road). A copy of the current Regeneration Programme is provided at Appendix 2 and has an associated capital cost of over £500m; it is worth noting, however, the regeneration pipeline itself is a subset of the Council’s wider capital programme of works that consists of over 300 projects.
4.3The projects which make up the Regeneration Programme are at varying stages of preparation; some such as Swarkestone and Shirebrook Access are at very early stages of development (Stage 0) whilst others are more advanced at either outline business case stage (Stage 2 to 3) or beyond (detailed design and construction etc).
4.4The Council has a key role to play either as a direct sponsor or as a delivery partner in these projects, some of which have been subject to separate Cabinet reports and approvals; for example, agreement of match funding or submission of business cases to Government; others may not have needed approvals to date, due to their early state of feasibility preparation. Also, the Council’s role in a project may vary over time, for example, from lead sponsor and enabler to ‘delivery partner’ when perhaps a district/borough council may pick up lead responsibility.
4.5Given the inevitable impact of Government grant funding announcements, plus the emergence of district and borough council policies and priorities, the exact content of the regeneration pipeline will always be fluid. As a result, ensuring a strong focus on the risks, opportunities and progress associated with each project is essential to the success of the overall Programme, and to ensuring the best use of Council staff and financial resources.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.