RESOLVED to approve: 1) The inclusion of the proposed access to the new Infinity Park Spencer Academy within the scope of the South Derbyshire Growth Zone project; 2) The allocation of £892,000 from the balance of the Children’s Services 2018-19 Basic Need/School Condition Allocation; 3) The preparation and submission of a planning application, including carrying out public consultation; and 4) The procurement of project management, property, planning, design and construction resources.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Joint Report of the Executive Director - Place and the Executive Director – Childrens Services
Regeneration Pipeline Programme - South Derbyshire Growth Zone – Infinity Park Spencer Academy Access (Cabinet Member for Infrastructure and Environment and Cabinet Member - Education)
1. Divisions Affected
1.1Aston.
2. Key Decision
2.1This is not a Key Decision.
3. Purpose
3.1To seek Cabinet approval to include the proposed access to the Infinity Park Spencer Academy within the scope of the South Derbyshire Growth Zone project; add the creation of the access to the capital programme; authorise the preparation and submission of a planning application including carrying out public consultation; to initiate procurement of project management, property, planning, design and construction resources; and to enter into necessary legal agreements with Derby City Council over highway adoption. 4. Information and Analysis
Background 4.1 Cabinet is familiar with the Southern Derbyshire Growth Zone (SDGZ) project, with the Council’s role currently comprising delivery of enabling highway infrastructure for major housing and commercial development within the defined Growth Zone and Infinity Garden Village (IGV). The infrastructure comprises a new junction on the A50 Trunk Road and a link to existing roads within Infinity Park Derby (IPD). The proposed scheme has planning consent and provisional funding of £49.6 million from the Government’s Levelling Up Fund. It has received Strategic Outline Business Case approval from Government, and its Outline Business Case is currently being assessed.
4.2At its meeting on 27 July 2023, Cabinet approved the making of Compulsory Purchase and Side Roads Orders necessary to progress the project (Minute No. 117/23 refers).
4.3Separate, but linked, to the above SDGZ project, the Council is involved in the planning of the Infinity Park Spencer Academy which will provide additional secondary education provision for the area around SDGZ/IGV. This is a collaborative project with Government (through the Department for Education) under which the Council will not take responsibility for creation of the Academy itself but will have responsibility for providing the means of access to the school, to be in place by January 2026. The cost of the access road has been estimated at £892,000. It is proposed to fund the work from the balance of the Children’s Services 2018-19 Basic Need/School Condition Allocation. The Developer has agreed to reimburse the County Council 50% of the access road upon its completion and adoption which, when received, will repay the 2018-19 Basic Need/School Condition Allocation budget. Work towards land assembly is already underway, with Heads of Terms agreed with the single landowner involved.
4.4The proposed means of access to the new Academy is shown in Figure 1. This links to the existing Infinity Park Way (in Derby City) and will also, in due course, form part of an east-west highway link within SDGZ. This east-west link currently falls outside the scope of the work for which the County Council takes responsibility and will mostly be delivered by private-sector partners in due course. However, there are two strong reasons for the delivery of its eastern section (coloured on Figure 1) to be managed by the Council: • This fulfils the Council’s obligations in relation to delivery of the Academy. • It ensures that the Council is in full control of securing continued access to Lea Farm (west of the Academy site) and which is affected by the construction of the SDGZ enabling infrastructure (the north- south link between the A50 and IPD).
Figure 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.