RESOLVED to: 1) Note the issues set out in the report and in Appendices 1 and 2; 2) Delegate authority to the Executive Director – Place, in consultation with the Cabinet Portfolio Holder, Infrastructure and Environment and Section 151 Officer to undertake final amendments to the draft Outline Business Case, prior to submission; 3) Approve the submission the Outline Business Case for the Chesterfield-Staveley Regeneration Route to Government for access to grant funding; 4) Approve the release of £2 million capital receipts, as allocated to the project in June 2022, to fund the next stages of project preparation work; and 5) Authorise officers to commence work on collaboration agreements with public and private sector partners over project funding and risk.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Regeneration Programme Pipeline – Chesterfield-Staveley Regeneration Route (Cabinet Member for Infrastructure and Environment)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To seek Cabinet approval to: submit the Outline Business Case for the Chesterfield-Staveley Regeneration Route (CSRR) to Government for consideration and access to grant funding; to approve the release of further resources to support the next stages of project preparation; and, to the commencement of work towards collaboration agreements with public and private-sector partners.
CONTROLLED 4. Information and Analysis
4.1The CSRR constitutes the single, largest project within the Council’s Regeneration Pipeline (part of the Growth Zone North Programme), creating a highway link of 6km that will parallel the A619 between Tapton and Staveley and open up to the east of Chesterfield along the ‘Staveley Corridor’ and support the delivery of up to 1,800 homes and 3,400 jobs.
4.2The scheme has a provisional grant allocation through the Government’s Large Local Majors (LLM) element of the Roads Investment Strategy (RIS) programme which is managed by the Department for Transport (DfT). Currently, the scheme is at preparatory stage – Outline Business Case (OBC) - and is targeted for construction between 2025 and 2027. Derbyshire County Council (DCC) is the scheme sponsor on behalf of DfT, working closely with Chesterfield Borough Council (CBC) who is a committed delivery partner.
4.3Ahead of construction, the scheme requires planning consent - for which preparatory work is underway - and land assembly, for which Cabinet approvals will be sought in due course. All affected landowners are already engaged in the preparation process through matters such as access to land for surveys, but no negotiations have yet commenced over land acquisition.
4.4The project has strong governance in place which reflects the partnership nature of delivery. In addition to focused working groups involving officers from DCC and CBC framed around key themes/issues, the governance arrangements are:
• The Project Control Board - meets weekly, is chaired by DCC and attended by all key professional officers from both the County and Borough councils, supported by external project management and contractor input. • The advisory Programme Board – meets monthly and comprises senior officers and DCC portfolio holders. • The Joint Growth Board – meets every two months and is attended by the Leaders, portfolio holders and senior officers of both the County and Chesterfield Borough councils to address the key relationship and delivery issues across an agreed programme of projects, including the CSRR.
4.5It is considered that the current governance arrangements provide senior officers and portfolio holders with sufficient oversight of the various workstreams to ensure that the project remains on track for
CONTROLLED successful delivery or to quickly identify and address issues during the lifespan of the project.
Current Position 4.6 Cabinet approval is required at key gateways across the delivery timetable; notably, the next key decision gateway is to agree formal submission of the OBC to Government which is the subject of this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.