RESOLVED to: 1) Note the continued progress made across the current regeneration pipeline and the addition of Ashbourne Reborn; 2) Approve the County Council acting in a delivery role for highway and public realm works under the Ashbourne Reborn programme; 3) Agree to the addition of Ashbourne Reborn works to the capital programme and, in principle, to the Council acting as applicant for planning consent, carrying out procurement of contractors and carrying out public consultation as required; 4) Authorise the Executive Director – Place, in liaison with the Cabinet Member for Infrastructure and Environment and the Director of Legal Services, to enter into legal agreements with Derbyshire Dales District Council over Ashbourne Reborn; 5) Note that an additional Programme Board to oversee Ashbourne Reborn is to be established by Derbyshire Dales District Council to have appropriate membership from elected members of County, District and Town Councils as well as Members of Parliament; and 6) Approve the receipt of £750,000 of grant funding for delivery of walking and cycling infrastructure within Markham Vale.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Regeneration Programme Pipeline – Levelling Up Projects (Cabinet Member for Infrastructure and Environment)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To provide Cabinet with a progress update on the current programme of regeneration projects and set out additional projects to be added to the programme; to seek approval for the Council acting in a delivery role for Ashbourne Reborn; adding public realm and highway works to the capital programme, approving the initiation of procurement of contractors and authorising the making of planning applications and the carrying out of consultation, and to seek approval to the acceptance of grant funding to deliver walking and cycling infrastructure within Markham Vale. 4. Information and Analysis
4.1At its meeting of 13 October 2022, Cabinet received an update on the Council’s active regeneration programme (Minute No. 180/22 refers) consisting of a pipeline of 50+ major projects, framed around four broad programme areas which are:
• Market Towns • Enabling Infrastructure • Growth Zone South • Growth Zone North
4.2Projects within the programme have been initiated either by the County Council (e.g. transport schemes such as Ashbourne Relief Road), by Government (e.g. town deal proposals) or by district/borough councils (e.g. Hollis Lane Link Road).
4.3The projects which make up the regeneration programme are at varying stages of preparation; some, such as Swarkestone and Shirebrook Access, are at very early stages of development (Stage 0) whilst others are more advanced at either outline business case stage (Stage 2 to 3) or beyond (detailed design and construction etc).
4.4The Council has a key role to play either as a direct sponsor or as a delivery partner in any of these projects, some of which have been subject to separate reports and approvals (e.g. for match funding of submission of business cases to Government); others may not have needed approvals to date due to their state of preparation i.e. the projects are at an early stage of development. Also, the Council’s role in a project may vary over time; for example, from lead sponsor and enabler to ‘delivery partner’ when perhaps a district authority may pick up lead responsibility.
4.5Given the inevitable changes over time in the release of Government grant funding, plus the emergence of district and borough council policies and priorities, the exact content of the pipeline will always be fluid. In order to ensure that Cabinet remains sighted on the entire regeneration programme, it is proposed that each project update (such as this report) also provides an overview of the programme as it stands at that point in time, with all committed and anticipated projects tabulated (see below). NB: Cabinet will note that some projects are close to completion with regard to the Council’s delivery role but will be retained in the programme update to report on the achievement of wider project outcomes such as the delivery of homes or commercial premises. 4.6 The current programme overview is provided in the table below:
Project (and Current Position Decision Status approximate gross Required Rating infrastructure cost) Stage: Delivery (DCC role as lead sponsor)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.