Drakelow Primary New School Initial request for approval
ApprovedExecutive2 papers
AI summaryDerbyshire County Council Cabinet approved £128,000 from the Dedicated Schools Grant to start recruiting staff for the new Drakelow Park Flying High Academy, scheduled to open in September 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£128,000
What happens nextFurther Cabinet report
Who it affectsDrakelow area pupils and familiesFamilies from the Drakelow Park housing development on the Derbyshire-Staffordshire border
What was decided
Cabinet noted the new Drakelow Park Flying High Academy is scheduled to open in September 2026. Report P12
Cabinet approved the agreement of revenue support for a Minimum Viable Number of pupils, with a detailed request and amount to follow in a later report. Report P12, 6.1
Cabinet approved £128,000 of revenue funding from the Schools Block of the Dedicated Schools Grant to allow the academy partnership to begin recruitment. Report P12, 1.2
Why
Without a Minimum Viable Number commitment and Funding Agreement in place, the school cannot open in September 2026, which would result in significant transport costs for the council and disruption for families. Report 6.1, P3, 11.1
A timely recruitment process is needed to install a Head Teacher; without it, there is a high risk the school will not open due to a lack of staffing. Report 11.2, 6.2
Existing primary schools in both Burton on Trent and Derbyshire are at capacity, their sites cannot be expanded, and the 2,239 new dwellings at Drakelow Park are forecast to require 448 additional primary places. Report P30, P31
What happens next
A further report to Cabinet will set out the full breakdown of revenue and capital costs and the required funding amount. Report 7.1, 1.2, P18
The Academy Partnership will run the recruitment process to appoint a Head Teacher and other staff ahead of the September 2026 opening. Report 11.2, 6.2
The developer, Countryside, will build the school under Section 106 obligations to the specification agreed with the local authority. Report 1.1, 2.1, 2.2
The money
£128,000 Revenue funding from the Schools Block of the Dedicated Schools Grant to enable initial recruitment by the Academy Partnership Report P12, 1.2
Options considered
Rejected: Do not approve the Minimum Viable Number and recruitment funding. The school would not be able to open in September 2026, causing significant transport costs and disruption for families Report 6.1, P3, 11.1
Implications
Financial: £128,000 released from the Schools Block of the DSG; further revenue and capital contributions and a full breakdown will be set out in a later Cabinet report. Report 1.2, P18, 7.1
Legal: The project is being delivered in line with Developer Section 106 obligations and the school will be built to a specification agreed with the local authority. Report 2.1, 2.2, P21
Equalities: An equalities assessment of the new provision and its impact on existing schools and pupil groups has been carried out, with cross-boundary planning with Staffordshire County Council. Report P28
Who and where
Families and pupils from the Drakelow Park housing development, on the boundary of Burton on Trent (Staffordshire) and Derbyshire Report P30, P28
Existing primary schools in Burton on Trent and Derbyshire, including Rosliston Primary and The William Allitt School, which are at capacity Report P30, P31
Derbyshire County Council as the local authority, including the Children's Services Development Section Report 8.1, P17
The developer Countryside, which is building the school under Section 106 obligations Report 1.1
Timeline
26 July 2016: Cabinet originally gave approval for the new school Report P32
May 2024: Department for Education guidance 'Establishing a new academy: the free school presumption route' was used as the basis for consultation Report 5.1
2025-10-16: Cabinet approved £128,000 in revenue funding and the Minimum Viable Number revenue support
September 2026: Drakelow Park Flying High Academy scheduled to open Report P12
Plain English for the jargon
Minimum Viable Number: The minimum number of pupils required to make the new school financially and operationally viable
DSG: Dedicated Schools Grant, the central government funding ringfenced for schools
Section 106: Legal agreements between a developer and a local authority requiring the developer to mitigate the impact of a development, for example by funding new school places
Free school presumption: The Department for Education route that allows a local authority to seek proposals for a new academy where a new school is needed
Flying High Academy: The Academy Partnership identified to run the new Drakelow Park school
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item121/25
Resolved
RESOLVED to: 1) Note that the new School Drakelow Park Flying High Academy is scheduled to open in September 2026; 2) Approve the agreement of revenue support, (a detailed request with amount to follow) for a Minimum number of pupils to enable the school to open as planned; and 3) Approve the revenue funding of £128,000 which is funded from within the Schools Block of the Dedicated Schools Grant to enable the initial recruitment process by the academy partnership.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Report of the Executive Director of Children’s Services
NEW PRIMARY SCHOOL AT DRAKELOW – DRAKELOW PARK FLYING HIGH ACADEMY – FLYING HIGH PARTNERSHIP
1. Divisions Affected
1.1Linton, South Derbyshire.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is significant having regards to the budget for the service or function concerned. This level is set at £500,000. It is also significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To update Cabinet of progress with the new Primary School at Drakelow Park and to seek Cabinet approval for the agreement of revenue support for a Minimum Viable Number of pupils to enable the school to open as planned in September 2026.
3.2To seek approval for £128,000 funding which is funded from within the Schools Block of the Dedicated Schools Grant (DSG) to enable the school to carry out the recruitment process for a Head Teacher in readiness for the opening of the school in September 2026. The figure requested is for recruitment and associated costs. .
4. Information and Analysis
4.1Under the South Derbyshire District Council Local Plan, reference H6, a total of up to 2239 dwellings are approved for the development at Drakelow Park. A new 2 form entry (2FE) Primary School is being delivered by the Developer as part of their Section 106 obligations and will be opened in September 2026 by the Flying High Partnership. The 2FE school will ensure future proofing in proceeding years to enable children within their local area to access a school place in line with the Local Authority’s Statutory Duty within the Education Act 1996.
The new school will initially open as a 1FE to accommodate Reception intake only. The school will continue to admit pupils from reception age as the earlier reception year pupils transition through the key stages, creating accommodation for Year 1, then Year 2 and so forth, eventually accommodating all year groups phasing over a period of 7 years. Thereafter, at a mutually agreed point to meet demographic sufficiency and demand, the intake capacity (Pupil Admission Number (PAN)) of the school will be increased from 30 to 60. A detailed analysis of demographics has been undertaken, affirming the need for the school to open in 2026.
As per the Presumption process in 2017, (attached and marked Appendix 2), Flying High Partnership were approved as the preferred Trust to operate the new school at Drakelow Park and the proposal was subsequently confirmed by the Department for Education (DfE). Following that decision, extensive discussions have taken place with the Trust and the housing developer, ‘Countryside’. Under the current programme, the school is due to open in September 2026. Capital support through allocated funding will be required to equip the school building.
To enable the Trust to enter into a funding agreement with the DfE, the project development funding requires agreement with the Local Authority (LA). For new schools where the LA is leading the process, it is the LA that must provide revenue funding to allow the Academy to carry out the task as necessary before the opening of the school. This revenue funding will incorporate initial pre-opening costs such as recruitment of staff, plus the underwriting of a ‘Minimum Viable Number’, to ensure the financial viability of the school in the initial years of opening. The agreement of the Minimum Viable Number, and funding to start the initial recruitment process are the critical items at this point to enable progression of this project as planned.
A full breakdown of additional funding required for both revenue and capital expenditure will form the basis of a proceeding report to Cabinet for approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.