AI summaryDerbyshire Cabinet approves Digital Connectivity Delivery Plan 2025-2027 and releases £0.900m from reserves to fund two rural broadband grant schemes.
Written from the decision and the officer reportPDF Pro
OutcomeNotedTwo rural grant schemes delegated for sign off
Money£0.900m from earmarked reserves£0.500m reallocated plus £0.400m allocated
What happens nextExecutive Director to finaliseSign off with Director of Finance and Cabinet Member
Who it affectsRural Derbyshire communitiesHard-to-reach premises without gigabit broadband
What was decided
Cabinet noted the previous Digital Derbyshire scheme overview and approved the Digital Connectivity Delivery Plan for 2025-2027 as set out in Appendix 2. Report P15, 9.2
Cabinet agreed to relocate £0.500m of earmarked reserves as the Council's contribution to Building Digital UK's Gigabit Broadband Voucher Scheme top-up element. Report P15, 1.1
Cabinet agreed to allocate the remaining £0.400m from Digital Derbyshire reserves and delegated finalisation of the two grant schemes to the Executive Director for Place. Report P15, P19, 3.1
Why
To keep rural gigabit rollout moving where national schemes, including BDUK, have not reached hard-to-reach premises. Report 11.1, 6.1
To use uncommitted funding and build on the success of earlier Digital Derbyshire programmes. Report 11.2
To provide a foundation for wider regional investment, including from the East Midlands Combined County Authority. Report 11.3
What happens next
The Executive Director for Place will finalise the two grant schemes in the Rural Digital Connectivity Grant Programme, in consultation with the Director of Finance and the Cabinet Member for Net Zero and Environment, before implementation. Report P15, P19
All suppliers with active services in Derbyshire have been contacted for expressions of interest in signing up as suppliers to the Gigabit Fibre Connectivity Grant scheme. Report 5.2
There is no plan to waive the call-in period for this decision. Report P19, 12.1
The money
£0.500m Earmarked reserves relocated as the Council's contribution to the BDUK Gigabit Broadband Voucher Scheme top-up element Report P15, 1.1
£0.400m Remaining Digital Derbyshire reserves allocated to the two grant schemes in the Rural Digital Connectivity Grant Programme Report P15, 1.1
£0.900m Total estimated cost of delivering the Rural Digital Connectivity Grant Programme Report 1.1
Options considered
Rejected: Do nothing. The £0.500m would likely remain unused and hard-to-reach premises would stay unserved by fast broadband until 2030 or beyond. Report 6.1
Rejected: Use interim and wireless solutions such as satellite, 4G and fixed wireless. High equipment and monthly costs, weather and signal issues, need for extra gear, and not future-proof compared with fibre. Report 6.2
Chosen: Approve the Delivery Plan and allocate £0.900m from reserves to two rural grant schemes. Maintains rural gigabit rollout momentum and uses uncommitted funding successfully demonstrated by earlier programmes. Report 11.1, 11.2
Implications
Financial: The £0.900m total is held in an earmarked reserve, mainly from BT Superfast Gainshare, and each grant will comply with the Subsidy Control Act 2022. Report 1.1, 1.2, 1.3
Legal: Each grant award will carry binding terms covering subsidy compliance, monitoring, clawback and public procurement rules where applicable. Report 2.1, P27
Equalities: A programme-wide Equality Impact Assessment has been carried out, prioritising rural and deprived areas with low broadband take-up, high free school meals indicators, or known social exclusion factors; the Social Broadband Inclusion Pilot targets families and children facing multiple digital barriers. Report 5.1, 5.2, 5.3, P34
Staffing: The programme will be run within the existing Digital Derbyshire team, led by the Digital Connectivity Manager with support from the Senior Economic Development Officer. Report 3.1, P29
Other: Improved connectivity is expected to support remote access to education and public services and may reduce future demand on the Council's IT services; IT Services will support any application portals or grant tracking in collaboration with the Transformation Team. Report 4.1, 4.2, P31
Who and where
Hard-to-reach rural premises and digitally excluded communities in Derbyshire that the national BDUK programme is not expected to reach Report 6.1, P4
Vulnerable and protected groups in those communities, including families and children facing multiple digital barriers Report 5.1, 5.3
Local businesses, district and borough councils and commercial broadband suppliers in Derbyshire Report 5.1, 5.2
The Council's Digital Derbyshire team, which will manage the programme within existing structures Report 3.1
Timeline
11 March 2021: Cabinet report on Rural Gigabit Broadband Top Up Voucher Scheme (Minute No. 46/21) Report 8.3
9 September 2021: Cabinet report on Gigabit Voucher Top Up Scheme (Minute No. 147/21) Report 8.2
25 July 2024: Cabinet report on Derbyshire Digital Connectivity Strategy (Minute No. 117/24) Report 8.1
2025-2027: Period covered by the Digital Connectivity Delivery Plan in Appendix 2 Report 9.2, P15
2025-2029: Period of the Council Plan 2025-2029 that the proposals support Report P38
Plain English for the jargon
BDUK: Building Digital UK, the national body running the Gigabit Broadband Voucher Scheme.
GBVS: Gigabit Broadband Voucher Scheme, the UK government voucher programme for gigabit-capable broadband.
Digital Derbyshire: The Council's earlier broadband programme, with reserves mainly funded by BT Superfast Gainshare.
Earmarked reserves: Money set aside by the Council for a specific purpose, here for digital connectivity work.
EMCCA: East Midlands Combined County Authority, a regional body the Council hopes will add investment.
Subsidy Control Act 2022: UK law setting rules on public subsidies to businesses, which each grant must follow.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item125/25
Resolved
RESOLVED to: 1) Note the overview of the previous Digital Derbyshire scheme and current issues; 2) Approve the Digital Connectivity Delivery Plan for 2025-2027 as set out in Appendix 2 to the report; 3) Approve to relocate £0.500m of earmarked reserves as a contribution towards the top up element of Building Digital UK’s Gigabit Broadband Voucher Scheme to enable delivery of the two grant schemes in the Rural Digital Connectivity Grant Programme; 4) Approve to allocate the remaining £0.400m from the Digital Derbyshire reserves to enable delivery of the two grant schemes in the Rural Digital Connectivity Grant Programme; and 5) Delegate finalisation and sign off of the detailed grant schemes to the Executive Director for Place, in consultation with the Director of Finance and Cabinet Member for Net Zero and Environment, prior to implementation.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Digital Connectivity Strategy Budget and Delivery (Cabinet Member for Net Zero and Environment)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are, significant having regard to the budget for the service or function concerned (this is currently defined as £500,000).
3. Purpose
3.1The purpose of this report is to enable further implementation of the Derbyshire Digital Connectivity Strategy by:
• Providing an overview of the previous Digital Derbyshire scheme and current issues. • Seeking Cabinet approval of the 2025-2027 Digital Connectivity Delivery Plan attached at Appendix 2. • Seeking Cabinet approval to reallocate £0.500m of earmarked reserves as a contribution towards the top-up element of Building Digital UK’s (BDUK) Gigabit Broadband Voucher Scheme (GBVS) to enable delivery of the Rural Digital Connectivity Grant Programme.
CONTROLLED • Seeking Cabinet approval to allocate the remaining £0.400m from the Digital Derbyshire reserves to enable delivery of the Rural Digital Connectivity Grant Programme.
4. Information and Analysis
Background: Digital Programmes in Derbyshire 4.1 Supporting efficiency through digitalisation is a key strand of the current Council Plan (2025-2029) and critical to success, is ensuring that up to date, reliable digital infrastructure is available across the county.
4.2Digital connectivity is not just a utility, it is a key enabler of economic resilience, enhanced service delivery and inclusive communities.
4.3The Council has had an ambition to achieve as close to 100% broadband coverage as possible across the County area, including making sure the hardest-to-reach locations are connected to fast and reliable broadband. To this end, the Council has previously worked in partnership with the Department for Digital, Culture, Media & Sport (DCMS) and Openreach to deliver its Superfast programme (known as Digital Derbyshire). The aim of this programme was to upgrade full copper lines (also known as asymmetrical digital subscriber line (ADSL)) to ‘fibre-to-the-cabinet’ (FTTC) technology, with the threshold being set at 24mbps to classify as ‘Superfast’.
4.4The Digital Derbyshire work has taken place over a nine-year period, split over two pieces of work:
• This first contract ran from 2014 to 2016 and was successful in improving broadband access to over 90,000 homes and businesses across the County that would not have received an improved service without intervention. The total value of the contact was £13.5m. • The second contract with Openreach ran from 2016 to 2023 and has resulted in over 25,000 additional premises receiving better broadband. The contract value was £10.4m. • Combined funding for both Contracts 1 and 2 was £23.97m resulted in 120,412 premises receiving an improved broadband service, 109,838 of which, exceeded the Superfast download Speed target of 24Mbps.
4.5Both contracts for the Superfast programme made provision for the Council to receive a proportion of Openreach revenue generated by the infrastructure installed. This is based on the percentage take up of the
CONTROLLED digital service. This revenue takes the form of a Gainshare fund held with BT and is what now makes up the Digital Derbyshire financial reserves.
4.6Using the success of the Superfast programme as a platform it was agreed that a ‘connectivity strategy’ for the County was needed. Although the two Superfast programmes were successful, technology had already started to move on. ‘Superfast’ connections were becoming outdated, with Gigabit (up to 1Gbps download speed) being the new industry standard. In 2023, 50% of the County had access to a gigabit- capable broadband connection - as of August 2025, 87% of the County has access.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.