Cabinet, Thursday 16 October 2025 at 12.00pm

Regeneration Project Pipeline

Approved Executive 4 papers

AI summaryDerbyshire Cabinet approves its regeneration project pipeline and 2025-26 EMCCA funding allocations, but holds back the Avenue site Phase 3 pending further talks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAvenue site Phase 3 excluded, can be added later
MoneyNot stated
What happens nextOfficers to seek and accept grantsExecutive Director for Place given delegated authority
Who it affectsEconomy and Regeneration, Highways, Legal teamsWorkload implications across council services

What was decided

Cabinet approved the Regeneration Pipeline and list of prioritised projects in Appendix 2, with the Avenue site Phase 3 (commercial development and new Southern access on the A61) held back. Report 10.1

Cabinet approved the allocation of 2025-26 EMCCA funding and other specific approvals set out in Figure 1 and Appendix 3, again excepting the Avenue site Phase 3. Report 10.1

Cabinet delegated authority to the Executive Director for Place, working with the Cabinet Member for Economic Development and Regeneration, to apply for funding, accept grants, add projects to capital and procurement programmes, run consultation, and later add the Avenue site subject to further discussions. Report P14

Why

To allow rapid mobilisation of projects for which grant funding is offered, to be spent during 2025-26 and 2026-27. Report 11.1

The pipeline supports key priorities in the Council Plan, particularly the Place objective of enabling prosperous, green and sustainable places. Report 6.1, P36

Approval negates the need for project-by-project Cabinet approvals for grants over £500,000, speeding up delivery. Report 2.1, P29

What happens next

No public consultation has been carried out on the recommendations, but consultation is expected on each funded project in due course. Report 5.1

Business cases for projects will need to confirm that any council match funding is available from existing commitments or via separate approval. Report 1.6

The call-in period is not being waived. Report 12.1

The money

  • £70.8m Total EMCCA transport funding confirmed for 2025-26 Report 1.2
  • £21.454m From EMCCA Transport for City Regions fund for 2025-26 Report 1.2
  • £7.775m From EMCCA Bus Service Improvement Plan for 2025-26 Report 1.2
  • £37.5m From EMCCA Highways Maintenance for 2025-26 Report 1.2
  • £3.67m From EMCCA Integrated Transport Block for 2025-26 Report 1.2
  • £0.422m From EMCCA Active Travel for 2025-26 Report 1.2
  • £0.245m Already accepted for EMIZ Sprint Report 1.1
  • £2.5m Already accepted from EMCCA Investment Fund for Chesterfield Staveley Regeneration Route ground investigation Report 1.1
  • £1.5m Already accepted for SDGZ from Transport for City Regions fund Report 1.1
  • £500,000 Constitution threshold above which Cabinet approval is needed to accept grants Report 2.1

Options considered

  • Rejected: Discontinue the Regeneration Pipeline. Council has no statutory duty to run one, but the programme supports Council Plan priorities Report 6.1
  • Rejected: Adopt different priorities to those in Appendix 2. Cabinet is free to choose other priorities, but has chosen to approve the list as recommended Report 6.2
  • Chosen: Approve the pipeline and EMCCA allocations as set out in Appendix 2, Figure 1 and Appendix 3. Allows rapid mobilisation of funded projects during 2025-26 and 2026-27 Report 10.1, 11.1

Implications

  • Financial: Proposals do not affect the council's own budget as requests are to seek and accept additional grant funding; business cases must confirm any match funding is available. Report 1.3, 1.6
  • Financial: The council faces current financial challenges and limited Kick Start resources, so EMCCA funding is particularly welcome. Report 1.5
  • Legal: Cabinet approval is required under the Constitution for grants over £500,000 not in the Service Plan; this report covers that need for pipeline projects. Report 2.1, P29
  • Staffing: Significant workload implications for Economy and Regeneration, Highways, Legal, Property and Finance staff, with external support and new in-house capacity being brought in. Report 3.1
  • Equalities: No direct equalities impact, but Equality Impact Assessments are usually needed for individual business cases. Report 5.1, P34
  • Risk: No direct IT implications, and no direct procurement implications, though some activity may need adding to the commercial pipeline. Report 4.1, 7.1, P40

Who and where

  • Economy and Regeneration Service staff Report 3.1
  • Highways, Legal, Property and Finance services Report 3.1
  • Communities across Derbyshire, through projects on the pipeline Report P36
  • East Midlands Combined County Authority as funding body Report 1.2, 1.4

Timeline

  • 2025-26: EMCCA transport funding allocations of £70.8m apply Report 1.2
  • 2025-26 and 2026-27: Grant funding for approved projects to be defrayed Report 11.1
  • 2025-10-16: Cabinet decision taken
  • Not specified: Avenue site Phase 3 may be added to the pipeline after further discussions conclude

Plain English for the jargon

  • EMCCA: East Midlands Combined County Authority, the body providing transport and other funding streams mentioned in the report.
  • EMIZ Sprint: A project already accepted with £0.245m of funding, not otherwise described in the papers.
  • SDGZ: A project already accepted with £1.5m from the Transport for City Regions fund, not otherwise described in the papers.
  • TCR: Transport for City Regions, an EMCCA funding stream.
  • Connectivity North / Connectivity South: Project development work previously supported by EMCCA funding, not otherwise described in the papers.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item122/25

Resolved

RESOLVED to: 1) Approve the Regeneration Pipeline and list of prioritised projects as set out in Appendix 2 of the report except for the Avenue site – Phase 3 (including commercial development and new Southern access on the A61); 2) Approve the allocation of 2025-26 EMCCA funding and other specific approvals for projects set out in Figure 1 and Appendix 3 to the report, except the Avenue site – Phase 3 (including commercial development and new Southern access on the A61); 3) Delegate authority to the Executive Director for Place, in liaison with the Cabinet Member for Economic Development and Regeneration, to: a) Make any suitable application for funding in support of the development process for those projects set out in Appendix 2 of the report; b) Accept grant in relation to projects and programmes included on the Regeneration Pipeline where offered; c) Add projects to the capital and commercial (procurement) programme as appropriate; d) Authorise any engagement and consultation necessary in relation to projects and programmes on the Regeneration Pipeline; and e) Add the Avenue site to the Regeneration Pipeline, subject to the satisfactory conclusion of further discussions.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

16 October 2025

Report of the Executive Director - Place

Regeneration Project Pipeline (Cabinet Member for Economic Development and Regeneration)

1. Divisions Affected

1.1County-wide.

2. Key Decision

2.1This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1The purpose of this report to provide Cabinet with an updated pipeline of regeneration projects, setting out proposed priorities for individual projects and seeking approval to progress activity, including adding projects to the Capital Programme, the acceptance of grant, undertaking procurement and initiating project delivery when funding becomes available.

4. Information and Analysis

Background 4.1 The Regeneration Pipeline comprises a portfolio of both capital and revenue projects, framed around a number of programme areas, in pursuit of improving the social and economic health of Derbyshire. In

CONTROLLED doing this, activity spans a range of interventions across regeneration ‘zones’, town centres and improvements to infrastructure, needed to bring sites forward.

4.2The Council has an approved Pipeline of existing activity that has been in place for a while but recent events such as establishment of the East Midlands Combined County Authority (EMCCA) and the early mobilisation of substantial funds means the time is right to refresh the pipeline and confirm the Council’s commitments.

4.3Cabinet may be aware of recent pipeline projects that either have been, or are in the process of being, developed. These include:

• The completed 1km Woodville-Swadlincote Regeneration Route which unlocked brownfield land bringing forward land for housing and commercial development. • The current South Derbyshire Growth Zone (SDGZ) which is a £70m+ proposal, supported by £49.5m from Government, to create a new access and link road off the A50 adjacent Infinity Park, facilitating a new school, 320,000m2 of employment space and 4,500 houses. • A number of town centre renewal schemes such as Ashbourne Reborn, Staveley Town Deal and Chesterfield New Plans for Neighbourhoods which are looking to revitalise urban centres, improve connectivity and the quality of public realm.

Refreshing the Regeneration Pipeline 4.4 Cabinet will appreciate that projects within the Regeneration Pipeline will almost always involve a need for external grant funding. Virtually, all will also require planning consent, assembly of land and a contractual relationship with land and asset owners (including district and borough councils).

4.5Projects also require ‘due diligence’ to confirm that public-sector intervention is necessary, that ‘local’ financial contributions can be secured (usually from developers), and clarify the role the County Council is playing in delivery e.g. as project sponsor, delivery partners etc.

4.6It can often take several years to move from project inception through to practical completion and, depending upon the nature of project funding, there may be obligations to monitor outcomes (such as the delivery of jobs) that extend the Council’s interests over a longer period. A robust forward plan, the ‘pipeline’, is therefore essential to ensure that

CONTROLLED appropriate resources (professional expertise and funding) are in place to take each project through its development process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Regeneration Pipeline and List of Project Priorities /25Appendix 2 679 KB Download
PDF
Details of Market Towns and Active Travel programmes /25Appendix 3 74 KB Download
PDF
Details of Market Towns and Active Travel programmes /25Appendix 3 74 KB Download
PDF
Regeneration Project PipelineReport 150 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
AG
Councillor Alan GravesChairman, present
RR
Councillor Robert ReaneyVice-Chairman, present
DA
Councillor Dawn AbbottCommittee Member, present
JB
Councillor Joss BarnesCommittee Member, present
JB
Councillor Jack BradleyCommittee Member, apologies
CH
Councillor Charlotte HillCommittee Member, present
JL
Councillor John LawsonCommittee Member, present
SR
Councillor Sam RedfernCommittee Member, present
SR
Councillor Stephen ReedCommittee Member, present
CW
Councillor Carol WoodCommittee Member, present
EA
Emma AlexanderOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance

All 19 on the meeting page

On this subject at Derbyshire

Search all
  1. Regeneration Project PipelineThis decision
  2. Regeneration Programme Pipeline – Levelling Up ProjectsNoted

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies