Decision It was proposed by Cllr Pothecary, seconded by Cllr Jones and agreed that the application be:- A. GRANTED subject to the completion of a legal agreement under Section 106 of the Town and Country Planning Act 1990 (as amended) in a form to be agreed by the Legal Services Manager including the provisions and conditions set out in the appendix to these minutes; or B. REFUSED permission for failing to secure the transfer of the hall if the agreement is not completed by (6 months from the date of committee) or such extended time as agreed by the Head of Planning.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Location: Land At, Chaffeymoor Farm, New Road, Bourton, Dorset
Proposal: Develop land by the erection of a village hall and 9 No. dwellings, form vehicular and pedestrian access. (Outline application to determine access).
Ward: Gillingham, Cllr V Pothecary Cllr B Ridout Cllr D Walsh
2.0Recommendation Summary:
A) GRANT, SUBJECT TO THE COMPLETION OF A LEGAL AGREEMENT UNDER SECTION 106 OF THE TOWN AND COUNTRY PLANNING ACT 1990 (AS AMENDED)IN A FORM TO BE AGREED BY THE LEGAL SERVICES MANAGER TO SECURE THE FOLLOWING:
The permitted site shall provide an area of at least 2.1 ha to be apportioned as follows:
0.3 ha to the village hall and a parking and manoeuvring area, and; 1.5 ha to amenity space of a reasonably level gradient and quality immediately adjacent to the village hall building, and; 0.3 ha to the housing development. The land for the village hall and amenity space, if not already transferred to the ownership of the Parish Council shall prior to any grant of planning permission on any part of the site for any aspect of the proposed development be transferred to the ownership of the parish Council. The land to be transferred to the Parish Council shall be transferred in a cleared state with services and access road provided to the site entrance point or there shall be a legal agreement on such provision.
And the following conditions (and their reasons) listed at the end of the report.
B) REFUSE PERMISSION FOR FAILING TO SECURE THE TRANSFER OF THE HALL IF THE AGREEMENT IS NOT COMPLETED BY (6 months from the date of committee) OR SUCH EXTENDED TIME AS AGREED BY THE HEAD OF PLANNING 3.0 Reason for the Recommendation:
Compliance with policy 5 of the Neighbourhood Plan Para 14 of the National Planning Policy Framework (NPPF) sets out that permission should be granted for sustainable development unless specific policies in the NPPF indicate otherwise The location is considered to be sustainable and the proposed access is There is not considered to be any significant harm to neighbouring residential amenity The ecology impact of the proposal is acceptable There are no material considerations which would warrant refusal of this application
4.0Table of Key Planning Issues
Issue Conclusion Principle of development The principle of the development is considered to be acceptable; the site is allocated for the development of a hall, residential development and amenity space within the Neighbourhood Plan. Access and Highway impact The access arrangements are sufficient to serve the development and there is adequate visibility onto New Road. Historic Conservation The application is considered to result in a neutral impact upon the setting of the adjacent listed buildings. The public benefit of providing a hall, 9 dwellings and amenity space is considered to weigh in favour of the application, and there is no identified historic conservation related harm that would outweigh this benefit. Landscape and Visual The proposal could be accommodated on the site Impact without significant impact on landscape character and visual amenity. Amenity The level of amenity of surrounding land users would be safeguarded at an acceptable level. Ecology The application is supported by an approved Biodiversity Mitigation and Enhancement Plan. Drainage The lower part of the land has been subject to surface flooding however there is no development proposed within this area. There are no drainage concerns, subject to a foul and surface water drainage condition.
5.0Description of Site
The proposed scheme is located on the western extent of the village of Bourton in the parish of Bourton. The site comprises part of a 3.9 hectare agricultural field. The site slopes gently down from the north to the south and west. There is a sparse hedge along the northern boundary to New Road and a more species rich quality hedgerow with occasional mature trees around the rest of the site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.