South and East Devon Habitat Regulations Executive Committee approved this item on Tuesday 14 July 2020. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1. that the (Appendix A to the report) be approved and the commitments an actions set out therein. 2. that the updated 5 Year Delivery Plan also shown in Appendix A be noted. 3. that the potential disruption to delivery of the ABP and 5 Year Delivery plan as a result of COVID-19 be noted. 4. that a report be received by July 2021 relating to ant proposed changes to the mitigation strategy regarding Dawlish Warren and the Exe Estuary in relation to the Dawlish Warren Beach Management Scheme.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Report to South and East Devon Habitat Regulations Executive Committee
Summary
1.1This paper sets out the principles for the projects which have been recommended as a priority for delivery over the next 12 months by the Habitat Regulations Delivery Manager. These recommendations have been reviewed and agreed by the respective organisations which constitute the Officer Working Group. These projects are contained within the attached Appendix A as the Annual Business Plan (ABP).
1.2The impacts of the Covid-19 pandemic to the delivery of the mitigation strategy continue to be felt and are difficult to fully quantify at this point in time. There continue to be significant impacts to our normal site operations and it is clear that significant financial implications are to be expected due to the lockdown in March- May 2020. Added to changing ways of working across the board and the potential for consultants and contractors to have reduced operational capacity, it is anticipated that there will be delays to delivery as a result. Therefore the ABP and 5 year plan is considered as the most appropriate course of action with the best available information at this point in time.
2020/21 Annual Business Plan / 5Yr Delivery Plan – July 2020 3 of 10 1.3 Timely and regular monitoring of projects, close liaison with partners and accurate reporting of any changes in housing delivery (with associated changes to income forecasting) will ensure that any delays to delivery of the Strategy are minimised, well understood and accounted for.
1.4The ABP has been incorporated into an updated 5 year delivery plan, also contained within the attached Appendix A. This therefore sets out an indicative programme and budget forecast for the short and medium term. Due to anticipated changes in housing delivery forecasts as a result of Covid-19, it is recommended that current income projections (see Financial Report) are updated and reported to the next meeting of the Committee. As this is likely to change the budget predicted in the 5 year delivery plan it is also recommended that the plan is also reviewed at the next meeting.
1.5As with previous business plans, it is important to note that a number of measures included in the 5 year plan are dependent on the success (or otherwise) of established measures, such as the Exe Estuary wildlife refuges. Therefore, projects earmarked for 2021-25 of the 5 year plan should be read in this context, as an indicative guide, rather than a prescription.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow South and East Devon Habitat Regulations Executive Committee at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.