South and East Devon Habitat Regulations Executive Committee decided this item on Thursday 29 April 2021. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Executive Committee: 1. Notes the progress made in delivering the 2020/21 Annual Business Plan; 2. Notes the status of mitigation measures from previous annual plans, as well as explanations given for measures subject to delay and revised completion dates; 3. Records its thanks to the site based staff for the ongoing dedication and adaptability they have shown in meeting the challenges presented during the coronavirus pandemic 4. Received a report on the impact of, and the lessons learned from the pandemic on the use of the estuary and protected areas to the Committee before the next scheduled meeting 5. Ask for measures of success that relate to significant investments set out in the plan (for example website and car park improvements) for the next scheduled meeting of the Committee. 6. Would like to see outstanding work not delivered in the 2020/21 Annual Business Plan go forward for inclusion in the 2021/22 Annual Business Plan
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Report to South and East Devon Habitat Regulations Executive Committee
South East Devon Habitat Regulations Executive Committee
2020-21 Annual Business Plan – Annual Report
Andy Wood, Service Lead
Growth, Development & Prosperity, East Devon District Council April 2021 Legal comment/advice:
The legal considerations are included within the report. Legal Services will assist with any further issues on which advice may be needed as they are raised.
Finance comment/advice:
The financial implications are set out in the report.
2020/21 Annual Business Plan - Annual Report April 2021 2 of 10 Public Document: Yes Exemption: None Review date for None release Recommendations It is proposed that the Executive Committee:
1. Notes the progress made in delivering the 2020/21 annual business plan. 2. Notes the status of mitigation measures from previous annual plans, as well as explanations given for measures subject to delay and revised completion dates. 3. Records its thanks to site based staff for the ongoing dedication and adaptability they have shown in meeting the challenges presented during the coronavirus pandemic.
Equalities impact: Low
Risk: Medium.
This report is an update on the progress made in delivery of ongoing mitigation measures set out in previous annual business plans and ongoing measures established in the Plan. It is important that progress continues to be made, or this would put the delivery of the partner Authorities’ Local Plans at risk due to the continued legal duties under the Habitat Regulations.
1. Summary/Overview. 1.1 The 2020/21 annual business plan (ABP) was approved at a virtual meeting of the Executive Committee on July 14th 2020. Additional recommendations relating to staff resources were approved at the November 18th meeting of the Executive. 1.2 The measures had been debated and endorsed by the Officer Working Group. The plan outlined the delivery of ongoing measures established in previous ABPs as well as a range of additional measures. In total, the plan earmarked expenditure of an estimated £411K. 1.3 Projects included the continued funding of keystone mitigation measures such as the Delivery Manager, Habitat Mitigation Officers and Project Officer (Devon Loves Dogs (DLD)). Other significant measures approved as part of the plan included phase 1 of the visitor access improvements on the East Devon Pebblebed Heaths and associated signage/interpretation, a new branded gazebo and display equipment for the Habitat Mitigation Officers, replacement signage at Exmouth Imperial Recreation ground and a redesigned website for the “South East Devon Wildlife” brand.
2020/21 Annual Business Plan - Annual Report April 2021 3 of 10 1.4 Tables 1 & 2 report the status of mitigation measures identified in the 2019/20 ABP.
Table 1. 2020/21 Annual Business Plan – ongoing mitigation measures. 1 Site Measure Status
Cross Site Delivery Manager Completed (ongoing) Cross Site Two Habitat Mitigation Officers Completed (ongoing) Cross Site Warden vehicle Completed (ongoing) Cross Site Dog project Completed (ongoing) Exe Estuary Wildlife refuge monitoring Monitoring complete. Awaiting report 2 Exe Estuary Patrol boat Completed (ongoing) Pebblebed Heaths Dog bins Completed (ongoing) SANGS Dawlish Countryside Park Completed (ongoing) 3 Phase 1 complete, open to the public SANGS South West Exeter (ongoing) 4
Table 2. 2020/21 Annual Business Plan - “new” mitigation measures.
Site Measure Status
All Website redesign In progress 5 All Gazebo for HMOs Complete All Change of vehicle for HMOs Complete Signage at the Imperial Exe Estuary Complete 6 Recreation Ground Pebblebed Heaths Interpretation & signage design In progress 7 Visitor access improvements – Pebblebed Heaths In progress 8 phase 1 works
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow South and East Devon Habitat Regulations Executive Committee at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.