South and East Devon Habitat Regulations Executive Committee decided this item on Tuesday 17 May 2022. Below is the council's own wording, with the papers it was decided on.
Resolved that the Executive Committee: Notes the progress made in delivering the 2021/22 annual business plan. Notes the status of mitigation measures from each of the plans, as well as explanations given for measures subject to delay and revised completion dates.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Report to South and East Devon Habitat Regulations Executive Committee
South East Devon Habitat Regulations Executive Committee
2021-22 Annual Business Plan – Annual Report
Neil Harris & Naomi Harnett Growth, Development & Prosperity, East Devon District Council April 2022 Legal comment/advice:
There is no direct comment to be made in relation to this report, each and any individual issue will need to be considered as it arises.
Finance comment/advice:
The financial implications are set out in the report.
2021/22 Annual Business Plan - Annual Report April 2022 2 of 7 Public Document: Yes Exemption: None Review date for None release Recommendations It is proposed that the Executive Committee:
1. Notes the progress made in delivering the 2021/22 annual business plan. 2. Notes the status of mitigation measures from each of the plans, as well as explanations given for measures subject to delay and revised completion dates.
Equalities impact: Low
Risk: Medium.
This report is an update on the progress made in delivery of ongoing mitigation measures set out in previous annual business plans and ongoing measures established in the Plan. It is important that progress continues to be made, or this would put the delivery of the partner Authorities’ Local Plans at risk due to the continued legal duties under the Habitat Regulations.
1. Summary/Overview. 1.1 The 2021/22 annual business plan (ABP) was approved at a virtual meeting of the Executive Committee on 29th April 2021. 1.2 The measures had been debated and endorsed by the Officer Working Group. The plan outlined the delivery of ongoing measures established in previous ABPs as well as a range of additional measures. In total, the plan released funding for projects estimated at £369,954. 1.3 Projects included the continued funding of keystone mitigation measures such as the Delivery Manager, Wildlife Wardens (previously “Habitat Mitigation Officers” and Project Officer (Devon Loves Dogs) (DLD). 1.4 New measures approved as part of the plan included phase 2 of the visitor access improvements on the East Devon Pebblebed Heaths and associated signage/interpretation. Measures at Dawlish Warren included the instigation of specialist contractor works required to safeguard petalwort, improvements and repairs to spur fencing near the Bight high tide bird roost and redesign of signage at Soft Sand Bay relating to landing by boat.
2021/22 Annual Business Plan - Annual Report April 2022 3 of 7 1.4 Tables 1 & 2 report the status of mitigation measures identified in the 2021/22 ABP.
Table 1. 2021/22 Annual Business Plan – ongoing mitigation measures. 1 Site Measure Status
Cross Site Delivery Manager Completed (ongoing) Cross Site Two Wildlife Wardens Completed (ongoing)2 Cross Site Warden vehicle Completed (ongoing) Cross Site Dog project Completed (ongoing) Exe Estuary Patrol boat Completed (ongoing) Pebblebed Heaths Dog bins Completed (ongoing) SANGS Dawlish Countryside Park Completed (ongoing) 3 Phase 1 complete, open to the public SANGS South West Exeter (ongoing) 4
Table 2. 2021/2 Annual Business Plan - “new” mitigation measures.
Site Measure Status
Dawlish Warren Petalwort translocation. Complete/In progress.5 Dawlish Warren Spur fencing in Bight. Complete Dawlish Warren Signage at Soft Sand Bay. Complete Pebblebed Heaths Interpretation & signage design In progress 6 Visitor access improvements – Pebblebed Heaths In progress 7 phase 2 works
1.5Tables 3 & 4 reflect the status of mitigation measures from all previous annual business plans.
1 Staffing and associated resources approved by HREC November 2020. 2 Two new staff now in post. 3 Land Trust assumed management (999 year lease) Dec 2021. 4 HREC approved funding arrangements November 2020. 5 Funding provided for consultant site visit. EA funded report. Further funding required, see (2.4) of
this report. 6 Signs for Phase 1 car park s have been installed. Remaining phases expected summer 2022. 7 Planning application submitted, work s expected summer/autumn 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow South and East Devon Habitat Regulations Executive Committee at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.