RESOLVED that Cabinet: 1. Agree to increase the maximum contractor contract from £3.5m to £3.8m. 2. Approves the full scheme value for approval of £6.275m (No further EDDCs funds are required at this time, with additional project budget found from external sources). REASON: 1. Additional works had been identified which could push the value up above £3.5m, however savings and risks not being realised may reduce this cost. 2. That the overall cost of works would rise above the previous approval, to £6.275m.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
1. Additional works have been identified which could push the value up above £3.5m, however savings and risks not being realised may reduce this cost. 2. That the overall cost of works will rise above the previous approval, to £6.275m
Portfolio(s) (check which apply): ☒ Climate Action and Emergency Response ☒ Coast, Country and Environment ☐ Council and Corporate Co-ordination ☐ Communications and Democracy ☐ Economy ☐ Finance and Assets ☐ Strategic Planning ☐ Sustainable Homes and Communities ☐ Culture, Leisure, Sport and Tourism Equalities impact Low Impact Climate change Medium Impact Risk: Low Risk; There is no further financial or other risks to EDDC. Links to background information N/A Link to Council Plan Priorities (check which apply) ☐ A supported and engaged community ☐ Carbon neutrality and ecological recovery ☒ Resilient economy that supports local business ☒ Financially secure and improving quality of services
Report in full 1. Project Updates 1.1. EDDC has signed a contract with Kier Integrated services for (sub) £3.5m to deliver the final phase of Feniton Flood Defence Scheme. 1.2. They started mobilising on site on 9 th September 2024, with major construction works starting late September 2024. 1.3. They have two gangs, one starting at the outfall, and working upstream, another, starting in the Feniton play park area, and then working upstream. 1.4. It is hoped that the majority of the works will be complete by September 2025, with the scheme being operational for the winter 25/26
2. Total contract value limit to be raised to £3.8m from £3.5m 2.1. As the precontract work nears completion, the additional costs have been identified above the previous construction value. 2.1.1. Winter working (slower progress, more street sweeping, lighting provision, additional de watering requirements) 2.1.2. Increased cost of design due to hydraulic improvements regarding backdrop manhole chambers, and thrust loading on corners 2.1.3. Further delays in getting to site (from prior May start date) 2.1.4. Adding of the work required to make good Network Rails framework designers issues. (£130k) 2.1.5. Its worth noting the above do not currently equal £300k, but it is prudent to ask for an increase to allow for any further CE’s (compensation events) 2.1.6. For clarity any further CE’s would come out of the project’s £619k risk budget
2.2We have identified savings or negative CE’s (compensation events) which should bring the construction below the £3.5m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.