South and East Devon Habitat Regulations Executive Committee decided this item on Thursday 24 October 2024. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Executive Committee 1. Notes the progress made in delivering the 2023/24 annual business plan; 2. Notes the status of mitigation measures from each of the plans, as well as explanations given for measures subject to delay and revised completion dates.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Report to South and East Devon Habitat Regulations Executive Committee
South East Devon Habitat Regulations Executive Committee
2023-24 Annual Business Plan – Annual Report
Neil Harris & Naomi Harnett Growth, Development & Prosperity, East Devon District Council October 2024 Legal comment/advice:
EDDC Legal Services have read this report and have no comment.
DEM.1-0007/October/RAH
Finance comment/advice:
Any financial implications are set out in the report.
2023/24 Annual Business Plan - Annual Report October 2024 2 of 7 Public Document: Yes Exemption: None Review date for None release Recommendations It is proposed that the Executive Committee:
1. Notes the progress made in delivering the 2023/24 annual business plan. 2. Notes the status of mitigation measures from each of the plans, as well as explanations given for measures subject to delay and revised completion dates.
Equalities impact: Low
Risk: Medium.
This report is an update on the progress made in delivery of ongoing mitigation measures set out in previous annual business plans and ongoing measures established in the Plan. It is important that progress continues to be made, or this would put the delivery of the partner Authorities’ Local Plans at risk due to the continued legal duties under the Habitat Regulations.
1. Summary/Overview. 1.1 The 2023/24 annual business plan (ABP) was approved at a meeting of the Executive Committee on 27th April 2023. 1.2 The measures had been debated and endorsed by the Officer Working Group. The plan outlined the delivery of ongoing measures established in previous ABPs as well as a range of additional measures. In total, the plan released funding for new projects estimated at £36,000. 1.3 Projects included the continued funding of keystone mitigation measures such as the Delivery Manager, Wildlife Wardens and Project Officer (Devon Loves Dogs) (DLD). 1.4 New measures approved as part of the plan included the redesign and rebuilding of the DLD website, a footbridge crossing point to safeguard southern damselfly habitat, development of educational resources for GCSE/A level students and Nightjar productivity modelling on the East Devon Pebblebed Heaths. At Dawlish Warren, funding for improvements/repairs to fencing along the front and at the distal end was identified. 1.5 Table 1, below, reports the status of ongoing mitigation measures previously approved by the Executive Committee 1.
1 Measures approved in previous annual business plans, designed to operate over multiple years (and therefore not requiring annual approval by the Executive).
2023/24 Annual Business Plan - Annual Report October 2024 3 of 7 Table 1. Ongoing mitigation measures from previous business plans approved by the Executive Committee. Site Measure Status
Cross Site Delivery Manager Completed (ongoing) Cross Site Two Wildlife Wardens Completed (ongoing) Cross Site Warden vehicle Completed (ongoing) Cross Site Dog project Completed (ongoing) Exe Estuary Patrol boat Completed (ongoing) Pebblebed Heaths Dog bins Completed (ongoing) SANGS Dawlish Countryside Park Completed (ongoing) Phase 1 complete, open to the public SANGS South West Exeter (ongoing) 2
1.6Table 2, below, reports the status of new mitigation measures approved as part of the 2023/24 annual business plan.
Table 2. 2023/24 Annual Business Plan - “new” mitigation measures.
Site Measure Status
All Devon Loves Dogs website Completed rebuild Fencing for access Dawlish Warren Completed management Footbridge crossing point Pebblebed Heaths Delayed3 (Southern damselfly habitat) Educational resources Pebblebed Heaths Delayed4 (GCSE and A level) Pebblebed Heaths Nightjar productivity modelling Near completion5
2 First car park opened 1 March 2023. 3 On hold pending sourcing of contractors to quote for work . Work ing with site manager to resolve. Completion expected Spring 2025. 4 Staff changes at the Pebblebed Heaths Conservation Trust resulted in a delay to completion of
this work . Completion expected Summer 2025 5 Modelling work completed, awaiting final report from consultants, winter 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow South and East Devon Habitat Regulations Executive Committee at East Devon and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.