East Devon District Council
Cabinet, Wednesday 4 March 2026 at 6.00pm

Sidmouth and East Beach Coastal Defence Scheme - Contract above £100k

Decided Executive 1 paper

AI summaryEast Devon Cabinet gives officers delegated authority to award the Sidmouth and East Beach coastal defence contract, worth an estimated £21m overall, once a preferred supplier is chosen from the current tender.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedDirector of Place, with two portfolio holders, to choose supplier
Money£21,040,000 total scheme fundingStage 1 tendered at about £1.8m
What happens nextIdentify preferred supplier in April 2026After tender deadline of Thursday 9 April
Who it affectsSidmouth residents, businesses and coastlineProtection from coastal flooding and erosion

What was decided

Cabinet gave the Director of Place delegated authority to award the Sidmouth and East Beach coastal defence contract to the preferred supplier, following consultation with the Environment Operations and Finance portfolio holders. Report P4

The contract is a two stage design and build deal covering detailed design, modelling, consenting and consultation in stage one, with an option to move to construction in stage two. Report P3

Why

The current tender closes on Thursday 9 April 2026 and a preferred supplier needs to be appointed quickly so that stage one design work can begin in mid May 2026 and programme targets are met without a further cabinet paper. Report 1.1, P4

Sidmouth faces worsening coastal flooding and erosion from climate change, with major overtopping events in 2014, 2017, 2020 and 2022, and the scheme is designed to meet 2100 sea level and climate standards. Report P7, P8

What happens next

Tender submissions will be evaluated after the 9 April 2026 deadline and a preferred supplier identified in April 2026. Report 1.1

Stage one design, modelling and consenting work is scheduled to start in mid May 2026, with detailed design due to complete in July 2027 ahead of any decision to move to construction. Report P17, P18

If stage two proceeds, construction is programmed to run from August 2027 to August 2028, with a break clause allowing the council to retender the construction element. Report P20, P21

The money

  • £17,540,000 Environment Agency FDGiA funding Report P11
  • £500,000 Local Levy Funding Report P11
  • £1,700,000 East Devon District Council primary budget Report P12
  • £500,000 East Devon District Council risk budget Report P12
  • £50,000 Housing contribution Report P12
  • £500,000 Devon County Council Highways Report P12
  • £100,000 Sidmouth Town Council Report P13
  • £100,000 Sidmouth Lifeboat Report P14
  • £50,000 CRAG contribution Report P15
  • £21,040,000 Total scheme funding Report P15
  • £21m Overall estimated works value Report 1.1
  • £1.8m Stage one design element value

Options considered

  • Chosen: Award contract to preferred supplier following tender. Allows contract to be entered without a further Cabinet paper and keeps the programme on track Report P4
  • Rejected: Re-tender the construction element if stage two is not taken forward. Available under the contract but not the current plan

Implications

  • Financial: Total scheme funding of £21,040,000 is already approved, with all contributions carrying conditions that the project currently plans to meet; the Environment Agency funding is still subject to programme allocation approval. Report 1.5, P11, P12, P13, P14, P15, P23
  • Legal: The procurement has been run with Devon County Council's procurement service to meet procurement law and the council's contract procedure rules, with further checks by Bevan Brittan solicitors. Report P23
  • Climate: The scheme has a high climate impact in both directions: it is designed to protect Sidmouth from worsening coastal flooding and erosion to 2100 standards, but the rock, concrete and transport needed will have a high carbon footprint. Report P7
  • Risk: Sidmouth is classed as high risk, with at least 14 overtopping incidents since 1981 and climate change expected to increase the frequency and severity of coastal storms. Report P8
  • Equalities: The report records a low equalities impact. Report P7

Who and where

  • Residents and businesses in Sidmouth, particularly along the Esplanade, York Street, Ham Car Park, Bedford Square and Chapel Road Report P8
  • Sidmouth Town Council, as a £100,000 scheme contributor Report P13
  • Sidmouth Lifeboat, as a £100,000 scheme contributor Report P14
  • Devon County Council Highways, as a £500,000 scheme contributor Report P12
  • Environment Agency, as the lead funder with £17,540,000 in FDGiA funding Report P11
  • Bidders responding to the live tender through the Supplying the South West portal Report 1.1

Timeline

  • 23 January 2026: Competitive tender went live on the council's electronic portal Report 1.1
  • April 2026: Preferred supplier to be identified after evaluation Report 1.1
  • Thursday 9 April 2026: Deadline for tender submissions Report 1.1
  • mid May 2026: Stage one design, modelling and consenting starts with early contractor involvement Report 1.1, P17
  • July 2027: Detailed design complete and notice to proceed to stage two issued Report P18
  • July 2027: Lead time and mobilisation period for construction Report P19
  • Aug 2027: Stage two construction phase commences if approved Report P20
  • Aug 2028: Construction phase completion Report P21

Plain English for the jargon

  • FDGiA: Flood Defence Grant in Aid, the Environment Agency's main grant programme for flood and coastal erosion risk management.
  • Two Stage Contract: A contract split into a design and pre-construction stage and a separate construction stage, with an option rather than an obligation to proceed to construction.
  • CRAG: Coastal Risk Assessment Group, a contributor of £50,000 to the scheme (not defined in the papers).
  • Supplying the South West portal: The electronic procurement portal used to run the open tender to the whole market.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item168

Resolved

RESOLVED that Cabinet: Grant delegated authority to the Director of Place in consultation with the Portfolio Holder Environment Operations and Portfolio Holder Finance to award the contract to the preferred supplier. REASON: To enable the award of contract to the preferred supplier following completion of the tender exercise. The delegation would allow the contract to be entered without a further Cabinet paper, to ensure programme targets were met.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet

Date of Meeting 4 March 2026 Document classification: Part A Public Document Exemption applied: None Review date for release N/A

Sidmouth and East Beach Coastal Defence Scheme – Authority to award the contract Report summary: This report is to seek delegated authority to award the Sidmouth and East Beach Coastal Defence Scheme Two Stage Contract involving the Detailed Design, Modelling, Consenting & Statutory Consultation within Stage One, with the option to progress to Stage Two, Construction Phase thereafter.

Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: 1. That Cabinet grant delegated authority to the Director of Place in consultation with the Portfolio Holder Environment Operations and Portfolio Holder Finance to award the contract to the preferred supplier. Reason for recommendation: 1. To enable the award of contract to the preferred supplier following completion of the tender exercise. The delegation will allow the contract to be entered without a further cabinet paper, to ensure programme targets are met.

Officer: Tom Buxton-Smith [email protected] 01395 571630

Portfolio(s) (check which apply): ☒ Assets and Economy ☐ Communications and Democracy ☐ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☒ Environment - Nature and Climate ☒ Environment - Operational ☐ Finance ☐ Place, Infrastructure and Strategic Planning ☐ Sustainable Homes and Communities

Equalities impact Low Impact Climate change High Impact Information about storm intensity and sea level risk is included in the risk section below, but also relates to climate change and is the reason for this being high impact. Without improved coastal defences. Sidmouth faces the prospect of increased frequency and magnitude of damage and flooding from coastal storms. The scheme will be designed to meet 2100 standards (sea level and climate change) as outlined in DEFRAs Flood and Coastal Erosion Risk Management Strategy to provide protection to Sidmouth from coastal erosion and flooding. The project is also high impact from a climate perspective as the rock and concrete required and transport of the same will have a high carbon footprint.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sidmouth and East Beach Coastal Defence Scheme: Contract above £100kReport 177 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 23 attended
MW
Melanie WellmanOfficer, in attendance
PA
Councillor Paul ArnottChair, present
SH
Councillor Sam HawkinsCommittee Member, present
PH
Councillor Paul HaywardCommittee Member, present
NH
Councillor Nick HookwayCommittee Member, present
SJ
Councillor Sarah JacksonCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, apologies
JL
Councillor John LoudounVice-Chair, present
TO
Councillor Todd OliveCommittee Member, present
RJ
Councillor Richard JefferiesCommittee Member, present
AC
Amanda CoombesOfficer, in attendance

All 23 on the meeting page

On this subject at East Devon

Search all
  1. Sidmouth and East Beach Coastal Defence Scheme - Contract above £100kThis decision
  2. Sidmouth and East Beach BMP - OBC approval, Risk Gap Funding, Project Board Reinstatement and Detailed Design Tender StageAgreed
  3. Sidmouth and East Beach BMP: Direction for OBC development and submissionApproved
  4. Sidmouth and East Beach BMPApproved
  5. Sidmouth and East Beach BMP Exemption to standing ordersNoted

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies