Towards a Delivery Vehicle for Marlcombe and Wider Growth Corridor

Decided Executive 1 paper

AI summaryEast Devon Cabinet backs shared delivery team and joint governance for the 10,000 home Marlcombe new community and wider growth corridor.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedInterim Growth Board, joint committee and shared team
MoneyMet from existing budgetBut £2.4m MHCLG ask pending for 2026/27
What happens nextFurther reports to CabinetOn consultation response and development corporation
Who it affectsMarlcombe and growth corridor10,000 home new community near Exeter

What was decided

Cabinet supports the proposed governance structure and the formation of a shared delivery team, drawn from the District and County Councils and Homes England. Report P4, 6.2

The Portfolio Holder for Place, Infrastructure and Strategic Planning is nominated to the Interim Growth Board; the Leader and the same Portfolio Holder are nominated to a joint committee with Devon County Council. Report P6

Authority is delegated to the Director of Place, with others, to finalise terms of reference for both bodies and to recruit the independent Chair of the Interim Growth Board. Report 5.7

Why

To put effective governance and place leadership in place while work continues on establishing a statutory locally led development corporation to deliver Marlcombe and the wider corridor. Report P3, 11.1

The approach is designed to keep momentum over the 18 to 24 months expected to set up a development corporation, by separating advisory, executive and operational functions. Report 5.2, 5.4

What happens next

Cabinet will receive further reports on the response to the New Towns Draft Programme consultation and on the establishment of a locally led development corporation as key milestones are reached. Report P57, P66, P67

A shared delivery team of up to eight full time equivalent posts will be set up through secondments, with the Outline Business Case for the development corporation expected to be an early item for the new Board. Report 6.2, P65

The money

  • £2.4m Revenue support ask to MHCLG for 2026/27 work programme Report P58
  • in excess of £2bn Gross development value of Marlcombe Report 5.1
  • circa £700m Infrastructure investment required for Marlcombe Report 5.1
  • £262m Annual GVA uplift in East Devon by 2042, rising to £764m once employment sites fully developed Report P20
  • £467m Annual GVA uplift for the South West by 2042, rising to £1.5bn once employment sites fully developed Report P20

Options considered

  • Chosen: Three stage model: Interim Growth Board (advisory), Interim Vehicle (jointly owned company) and statutory development corporation. Maintains delivery momentum over 18 to 24 months while the development corporation is set up Report P4, 5.2, P24

Implications

  • Financial: No allowance in the MTFS to progress this work; a £2.4m revenue ask has been made to MHCLG but is not yet confirmed and further reports will need to address the funding position. Report 8.2, P58, P69
  • Legal: The joint committee will be set up under sections 101(5) and 102 of the Local Government Act 1972; external legal advice has been secured due to project complexity. Report P45, P69
  • Equalities: Low impact at this stage; equalities impacts of individual schemes will be considered through the new governance and detailed impact assessments. Report P9
  • Climate: Medium impact; the sustainability credentials of the new community and wider growth programme will need to be addressed through ongoing technical work. Report P9
  • Risk: Medium risk; the development corporation will require substantial technical work and stakeholder engagement and a persuasive case to the Secretary of State, alongside the risk of Local Government Reorganisation distracting the programme. Report P9, P62
  • Staffing: Shared delivery team of up to eight FTE posts formed through secondments from the District and County Councils and Homes England; staff remain employed by their host authorities. Report 6.2

Who and where

  • Marlcombe new community (planned 10,000 homes with 40% affordable housing target, near the A30 and A3052) Report P15
  • Cranbrook new town and the wider Exeter and East Devon Enterprise Zone (around 15,000 new homes and over 500k sq m of new commercial space) Report 3.1, 5.6
  • Devon County Council, Exeter City Council, Devon and Torbay Combined County Authority, Homes England, MHCLG and the Department for Transport as governance partners Report 5.6
  • Key infrastructure and service stakeholders including National Highways, Network Rail, South West Water, Environment Agency, Natural England, Live West, SNG, Stagecoach, Exeter Airport, Sport England, the Integrated Care Board, GWR, South Western Railway, Active Travel England, local MPs, Exeter College, Bicton College, Devon Agricultural Association, Exeter Chiefs, Exeter City Football Club and Exeter Science Park Report 5.6

Timeline

  • 1 April 2026: Cabinet decision to support new governance and shared delivery team Report P2
  • 19th May: Close of New Towns Draft Programme consultation
  • Early summer 2026: Expected decision on which of the five Local Government Reorganisation options moves forward
  • 18 to 24 months from decision: Estimated time to establish the development corporation Report 5.2
  • 2029: Anticipated start on site for Marlcombe
  • April 2028: Target date for transition to new unitary authority under Local Government Reorganisation
  • 2042: Forecast year for delivery of the economic impact figures in the Outline Economic Impact Assessment Report P20

Plain English for the jargon

  • MHCLG: Ministry of Housing, Communities and Local Government
  • DC: Development Corporation, a statutory body proposed to deliver the new town
  • OBC: Outline Business Case, being developed on the five case model
  • MTFS: Medium Term Financial Strategy
  • FTE: Full Time Equivalent staff post
  • GVA: Gross Value Added, a measure of economic output
  • Nolan Principles: The Seven Principles of Public Life that will govern the Chair's conduct
  • DfT: Department for Transport
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item182

Resolved

RESOLVED that Cabinet; 1. Supports the proposed governance structure and formation of the shared delivery team. 2. Nominates the Portfolio Holder for Place, Infrastructure and Strategic Planning to be the Council’s representative on the Interim Growth Board. 3. Nominates the Leader and the Portfolio Holder for Place, Infrastructure and Strategic Planning to be the Council’s representatives on the Joint Committee. 4. Delegates authority to the Director of Place in consultation with the Director of Governance and Portfolio Holders for Place, Infrastructure and Strategic Planning and Council, Corporate and External Engagement to finalise the terms of reference for the Interim Growth Board and Joint Committee. 5. Delegates authority to the Director of Place in consultation with the Director of Governance and Portfolio Holders for Place, Infrastructure and Strategic Planning and Council, Corporate and External Engagement to recruit the Chair for the Interim Growth Board. 6. Receives further reports regarding the · response to the New Towns Draft Programme consultation · establishment of a locally led development corporation as key milestones are reached. REASON: To ensure that effective governance and place leadership arrangements are in place to support the successful delivery of the Marlcombe new community and wider growth corridor.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet

Date of Meeting 1 April 2026 Document classification: Part A Public Document Exemption applied: None Review date for release N/A

Towards a Delivery Vehicle for Marlcombe and Wider Growth Corridor Report summary: The Marlcombe new community is one of twelve locations shortlisted by the New Towns Taskforce in September 2025 and is the key strategic proposal in the Local Plan review. It will grow to accommodate a population of approaching 25,000 people. Despite not being selected as one of the seven high priority location in the current consultation on the New Towns Draft Programme, it is vital that this community is supported by all the requisite infrastructure and services that residents will need. This report pu ts forward proposals to both strengthen governance arrangements and put in place dedicated delivery capacity with the objective of ensuring that an exemplar development comes forward that both learns the lessons from and is integrated with the wider growth programme.

The report sets out a three-stage model for strengthening governance arrangements that will ultimately culminate in the establishment of a locally-led development corporation. The first stage proposes both the creation of an Interim Growth Board, that will act in an advisory capacity with an independent chair, together with the establishment of a formal joint committee with the County Council. Alongside this a shared delivery team will be formed including resources from both the County Council and Homes England.

Effective governance and place leadership sits at the heart of successful delivery of the growth programme. The proposals in this report are designed to ensure that the ambitious vision for the Marlcombe new community is realised alongside the ongoing development of Cranbrook and bringing forward the large scale delivery of new employment opportunities. Through building strong and enduring partnerships with key stakeholders an integrated and inclusive growth programme can be delivered that supports the achievement of sustainable development and secures lasting benefits for local residents.

Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That Cabinet; • Supports the proposed governance structure and formation of the shared delivery team • Nominates the Portfolio Holder for Place, Infrastructure and Strategic Planning to be the Council’s representative on the Interim Growth Board • Nominates the Leader and the Portfolio Holder for Place, Infrastructure and Strategic Planning to be the Council’s representatives on the Joint Committee • Delegates authority to the Director of Place in consultation with the Director of Governance and Portfolio Holders for Place, Infrastructure and Strategic Planning and Council, Corporate and External Engagement to finalise the terms of reference for the Interim Growth Board and Joint Committee • Delegates authority to the Director of Place in consultation with the Director of Governance and Portfolio Holders for Place, Infrastructure and Strategic Planning and Council, Corporate and External Engagement to recruit the Chair for the Interim Growth Board • Receives further reports regarding the o response to the New Towns Draft Programme consultation o establishment of a locally-led development corporation as key milestones are reached Reason for recommendations: To ensure that effective governance and place leadership arrangements are in place to support the successful delivery of the Marlcombe new community and wider growth corridor.

Officer: Andy Wood, Director of Place, [email protected] , Naomi Harnett, Corporate Lead – Placemaking & Major Projects, [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Towards a Delivery Vehicle for Marlcombe and Wider Growth CorridorReport 465 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 32 attended
MW
Melanie WellmanOfficer, in attendance
PA
Councillor Paul ArnottChair, present
SH
Councillor Sam HawkinsCommittee Member, present
PH
Councillor Paul HaywardCommittee Member, present
NH
Councillor Nick HookwayCommittee Member, present
SJ
Councillor Sarah JacksonCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, present
JL
Councillor John LoudounVice-Chair, present
TO
Councillor Todd OliveCommittee Member, present
RJ
Councillor Richard JefferiesCommittee Member, apologies
AC
Amanda CoombesOfficer, in attendance

All 32 on the meeting page

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open
16 Sep 2026 Green Team Project Standing Order ExemptionRESOLVED that Cabinet: 1. Notes and supports the exemption to Contract Standing Orders under the provision relating t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies