Cabinet, Wednesday 1 April 2026 at 6.00pm

Sidmouth Jacobs Ladder Platform, seawall and slipway repairs

Decided Executive 1 paper

AI summaryCabinet has given the Director of Place delegated authority to award a contract to repair Sidmouth's Jacobs Ladder platform, seawall and slipway, using up to £120,000 of new funding alongside £116,000 left over from 2022.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedDirector of Place to award contract after tender
MoneyUp to £120,000Additional BSCAP funding for coastal works
What happens nextContract award and site startAiming to begin after Easter weekend
Who it affectsSidmouth seafront and Jacobs Ladder usersPublic safety at exposed coastal structure

What was decided

Cabinet granted delegated authority to the Director of Place, in consultation with the Portfolio Holder for Environment Operations and the Portfolio Holder for Finance, to award the contract to the preferred supplier. Report P4

Why

To let the contract be entered into without another cabinet paper, so programme targets can be met. Report P5

The tender is being run through the Environment Agency's Asset Operation Maintenance and Response Framework, which the council has access to. Report P3, P9

What happens next

Complete the tender exercise and appoint a contractor through the framework. Report P5, P9

Start on site soon after the Easter weekend and finish before the summer season. Report P9

The money

  • £116k Remaining budget from the partially completed 2022 works Report P9
  • £120k Further funding secured via BSCAP, in the approved Coastal Maintenance bid Report P9
  • £48k Of the BSCAP funding, the share for the Jacob's Ladder area in isolation Report P9

Options considered

  • Chosen: Award the contract through the Environment Agency AOMR Framework with delegated authority to the Director of Place. Allows direct award via an accessed framework and meets programme targets without a further cabinet paper Report P3, P4, P5, P9, P10

Implications

  • Financial: The cost is covered within existing budgets, including £116k carried over and up to £120k of new BSCAP funding. Report P10, P9
  • Legal: Awarding through a procured framework that permits direct awards is in line with procurement law and the council's Contract Standing Orders. Report P10
  • Risk: High risk: the seawall and slipway are exposed and uneven, with steel reinforcement protruding, so works are needed urgently. Report P8
  • Climate: High impact rating recorded for climate change, linked to the resilient economy priority in the Council Plan. Report P8

Who and where

  • Members of the public using the Jacobs Ladder area, the slipway and Sidmouth's main seawall Report P8, P9
  • Local businesses on Sidmouth seafront, tied to the resilient economy priority Report P8

Timeline

  • 2022: Original works started and then abandoned after storms covered the working area with beach Report P9
  • 1 April 2026: Cabinet decision to delegate contract award Report P1, P2
  • Soon after the Easter weekend: Planned start on site Report P9
  • Prior to the summer season: Target completion of the repairs Report P9

Plain English for the jargon

  • AOMR Framework: Environment Agency Asset Operation Maintenance and Response Framework, which the council has joined and can use for direct awards.
  • BSCAP: Not defined in the supplied papers; cited as the source of the additional coastal maintenance funding.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item187

Resolved

RESOLVED that Cabinet; Grant delegated authority to the Director of Place in consultation with the Portfolio Holder Environment Operations and Portfolio Holder Finance to award the contract to the preferred supplier. REASON: To enable the Assistant Director to award the contract to the preferred supplier following completion of the tender exercise. The delegation would allow the contract to be entered without a further cabinet paper, to ensure programme targets were met.
Word for word from the decision East Devon published for this meeting. Source: democracy.eastdevon.gov.uk

Follow this further

Built from East Devon's papers

What the report saysPro

Report to Cabinet

Report to: Cabinet

Date of Meeting 1 April 2026 Document classification: Part A Public Document Exemption applied: None Review date for release N/A

Sidmouth Jacobs Ladder Platform, seawall and slipway repairs – Contract above £100k Report summary: This report is to seek delegated authority to award the Sidmouth Jacobs Ladder Platform, seawall and slipway repairs to a contractor on the Environment Agency AOMR Framework that EDDC has access to.

Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That Cabinet grant delegated authority to the Director of Place in consultation with the Portfolio Holder Environment Operations and Portfolio Holder Finance to award the contract to the preferred supplier.

Reason for recommendation: To enable the Assistant Director to award the contract to the preferred supplier following completion of the tender exercise. The delegation will allow the contract to be entered without a further cabinet paper, to ensure programme targets are met.

Officer: Tom Buxton-Smith [email protected] 01395 571630

Portfolio(s) (check which apply): ☒ Assets and Economy ☐ Communications and Democracy ☐ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☒ Environment - Nature and Climate ☒ Environment - Operational ☐ Finance ☐ Place, Infrastructure and Strategic Planning ☐ Sustainable Homes and Communities

Equalities impact Low Impact Climate change High Impact Risk: High Risk; The seawall and slipway is exposed, and in uneven with lots of steel reinforcement sticking out. Works need to be done ASAP to avoid risk to the public. Links to background information Link to Council Plan Priorities (check which apply) ☐ A supported and engaged community ☐ Carbon neutrality and ecological recovery ☒ Resilient economy that supports local business ☐ Financially secure and improving quality of services

Report in full 1. Contract with a contractor (yet to be appointed) will exceed £100k. 1.2. A framework tender has been started via the Environment Agency’s Asset Operation Maintenance and Response Framework (AOMR) which East Devon has successfully entered. 1.3. The aim is to have an appointed contractor in place to start on site soon after the Easter weekend. 1.4. The project is to finish works started in 2022, but abandoned part way through following storms on site which covered the working area up with beach. The beach has now lowered and all the hazards are exposed again. Therefore the works need to be completed as soon as possible prior to the summer season. 1.5. Whilst on site, there is a further project to complete on Sidmouth’s main seawall, which was not started in 2022 due to covering of the works area by beach. This is now exposed. 1.6. We have remaining budget from the partially completed works of 2022. This totals £116k 1.7. Due to the inefficiencies of partially completing works, as well as construction inflation, we have secured further funding via the BSCAP of up to £120k in the Coastal Maintenance bid that was approved. For the Jacob’s ladder area in isolation this is £48k. 1.8. To ensure the contract is signed swiftly to enable construction to start soon after the main Easter break, we request delegated authority be given to the Director of Place in consultation with the Portfolio Holder Environment Operations and Portfolio Holder Finance to award the contract to the preferred supplier. 2. Photo of exposed damaged wall

Financial implications: As detailed in the report this covered within existing budgets. Legal implications: The proposal in this report is to award a contract through a framework agreement that has been procured in accordance with Procurement legislation and which allows direct awards. This is in compliance with the Council’s Contract Standing Orders.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Sidmouth Jacobs Ladder Platform, seawall and slipway repairsReport 371 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 32 attended
MW
Melanie WellmanOfficer, in attendance
PA
Councillor Paul ArnottChair, present
SH
Councillor Sam HawkinsCommittee Member, present
PH
Councillor Paul HaywardCommittee Member, present
NH
Councillor Nick HookwayCommittee Member, present
SJ
Councillor Sarah JacksonCommittee Member, present
GJ
Councillor Geoff JungCommittee Member, present
DL
Councillor Dan LedgerCommittee Member, present
JL
Councillor John LoudounVice-Chair, present
TO
Councillor Todd OliveCommittee Member, present
RJ
Councillor Richard JefferiesCommittee Member, apologies
AC
Amanda CoombesOfficer, in attendance

All 32 on the meeting page

More from East Devon Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 LGR in Devon: Government Decision and Implications for EDDCRESOLVED that Cabinet: 1. Notes the Government’s July decision and the subsequent review 2. Notes the concerns regard... Agreed Open
16 Sep 2026 Financial Strategy 2027 - 2029RESOLVED that Cabinet : 2. Agrees that the 2027/28 budget process should continue to be developed within the principl... Agreed Open
16 Sep 2026 Financial Monitoring Report and Annual Treasury Management Review 2025/26RESOLVED that Cabinet: Acknowledge the variances identified as part of the Revenue and Capital Monitoring process up ... Approved Open
16 Sep 2026 Woodbury Neighbourhood Plan to be formally 'made'RESOLVED that Cabinet: 1. Agree that the Woodbury Parish Neighbourhood Plan be ‘made’. 2. Note that once made the Pla... Agreed Open