Phear Park and The Green Car Park (Broadclyst) Resurfacing Works - Contract above £100k
DecidedExecutive1 paper
AI summaryEast Devon Cabinet delegates authority to award a contract over £100k for resurfacing footpaths at Phear Park in Exmouth and The Green Car Park in Broadclyst, with a £145k budget.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedDirector of Place with two portfolio holders
Money£145k total budgetSecured in previous capital budgets
What happens nextAward contract early April 2026After 8 working day standoff period
Who it affectsUsers of both sitesPedestrians and vehicles at Phear Park and Broadclyst
What was decided
Cabinet gave the Director of Place delegated authority, in consultation with the Portfolio Holder Environment Operations and the Portfolio Holder Finance, to award the resurfacing contract to the preferred supplier. Report P4
This delegation removes the need for a further cabinet paper before the contract can be entered. Report P5
Why
The works are needed to repair surface degradation that currently poses a safety risk to pedestrians and vehicles. Report 1.2
Delegating authority allows the contract to be signed swiftly so construction can start soon after the main Easter break and programme targets are met. Report P5
What happens next
Complete tender evaluation and appoint a preferred supplier, then observe a standard 8 working day standoff.
Award the contract at the start of April 2026, with construction to follow soon after Easter.
The money
£145k Total budget for the resurfacing works, secured in previous capital budgets
Options considered
Chosen: Grant delegated authority to the Director of Place to award the contract. Avoids a further cabinet paper and lets construction start soon after Easter to meet programme targets Report P4, P5
Implications
Financial: The work sits within an existing approved budget. Report P11
Legal: The contract must be procured in line with the council's Contract Procedure Rules. Report P11
Equalities: Equalities impact assessed as low. Report P8
Climate: Climate change impact assessed as low. Report P8
Who and where
Pedestrian and vehicle users of Phear Park, Exmouth Report 1.2
Users of The Green Car Park, Broadclyst Report 1.2
The contractor to be appointed through the open tender
Timeline
11/02/26: Open tender competition issued via ProContract on Supplying The South West Portal
09/03/26: Deadline for tender returns
13/03/26: Target date for evaluation and appointment of preferred supplier
Start of April 2026: Proposed date for awarding the contract, after an 8 working day standoff
Soon after the main Easter break: Construction to start
Plain English for the jargon
ProContract: An online procurement portal used to run tender competitions.
Supplying The South West Portal: A regional procurement portal where the tender was advertised.
Standoff period: A set waiting time after choosing a supplier before the contract is formally awarded, to allow for challenges.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item183
Resolved
RESOLVED that Cabinet; Grant delegated authority to the Director of Place in consultation with the Portfolio Holder Environment Operations and Portfolio Holder Finance to award the contract to the preferred supplier. REASON: To enable the Assistant Director to award the contract to the preferred supplier following completion of the open tender competition. The delegation would allow the contract to be entered without a further cabinet paper to ensure programme targets were met.
Word for word from the decision East Devon published for this meeting.Source: democracy.eastdevon.gov.uk
Date of Meeting 1 April 2026 Document classification: Part A Public Document Exemption applied: None Review date for release N/A
Phear Park and The Green Car Park Resurfacing Works - Contract above £100k Report summary: This report is to seek delegated authority to award the Phear Park and The Green Car Park Resurfacing Works to a contractor after undertaking an open tender competition.
Is the proposed decision in accordance with: Budget Yes ☒ No ☐ Policy Framework Yes ☒ No ☐ Recommendation: That Cabinet grant delegated authority to the Director of Place in consultation with the Portfolio Holder Environment Operations and Portfolio Holder Finance to award the contract to the preferred supplier.
Reason for recommendation: To enable the Assistant Director to award the contract to the preferred supplier following completion of the open tender competition. The delegation will allow the contract to be entered without a further cabinet paper, to ensure programme targets are met.
Portfolio(s) (check which apply): ☒ Assets and Economy ☐ Communications and Democracy ☐ Council, Corporate and External Engagement ☐ Culture, Leisure, Sport and Tourism ☒ Environment - Nature and Climate ☒ Environment - Operational ☐ Finance ☒ Place, Infrastructure and Strategic Planning ☐ Sustainable Homes and Communities
Equalities impact Low Impact Climate change Low Impact Risk: Low Risk Links to background information Link to Council Plan Priorities (check which apply) ☐ A supported and engaged community ☐ Carbon neutrality and ecological recovery ☒ Resilient economy that supports local business ☐ Financially secure and improving quality of services
Report in full 1. Contract with a contractor (yet to be appointed) will exceed £100k.
1.2The works consist of resurfacing footpaths in Phear Park, Exmouth and The Green Car Park, Broadclyst. This to repair surface degradation that pose a current safety risk to both pedestrian and vehicle users. 1.3. The total budget of works is £145k, which has been secured in previous capital budgets. 1.4. An open tender competition was issued on 11/02/26 via ProContract on Supplying The South West Portal. 1.5. Deadline for tender returns was on 09/03/26 with evaluation to be undertaken and a preferred supplier to be appointed by 13/03/26. 1.6. A standard 8 working day standoff period will be observed with a proposed date of awarding the contract at the start of April. 1.7. To ensure the contract is signed swiftly to enable construction to start soon after the main Easter break, we request delegated authority be given to the Director of Place in consultation with the Portfolio Holder Environment Operations and Portfolio Holder Finance to award the contract to the preferred supplier.
Financial implications: This work is within an existing approved budget. Legal implications: The contract must be procured in accordance with the Council’s Contract Procedure Rules.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.