RESOLVED – (A) note the status of the schemes being progressed as part of the 2011/12 Discretionary Schemes Rolling Programme and the current predicted discretionary budget allocation expenditure, using additional contributions where applicable. (B) supports the additional schemes suggested to be progressed to fully utilise the 2011/12 discretionary budget allocation. (C) supports the Chairman and Vice-Chairman of the Panel to meet with Officers if required prior to the next Panel meeting to determine any further minor budget allocation re-casting prior to the final quarter to maximise both expenditure and scheme progression.
Word for word from the decision East Hertfordshire published for this meeting.Source: democracy.eastherts.gov.uk
1.1To advise the Panel on the present position with progressing the discretionary budget schemes rolling programme.
2.0Finance
2.1The 2011/12 discretionary budget allocation for works and fees is £100,000.
2.2Additional contributions to be made available this financial year 2011/12 comprise:
• £14,000 Section 106 funding to promote a proposed signing and road markings improvement scheme at Lower Road / Amwell Lane, Great Amwell.
• £27,000 routine maintenance funding to implement the new stepped access to re-establish pedestrian movements at Old Thieves Lane, Hertford (northern side of the A414).
• £9,000 routine maintenance funding to implement the supported recommended measures at Rye Street, Bishop’s Stortford.
2.3Additional contributions to be made available this financial year 2011/12, subject to concluding the application process, comprise:
• £1,000 Locality Budget funding from County Cllr Roger Beeching to joint-fund a contribution to Herts and Middlesex Wildlife Trust (HMWT) towards the development of Thorley Wash Reserve. 2.4 Further additional contributions will be sought as appropriate throughout the financial year to supplement the discretionary budget allocation.
3.02011/12 Discretionary Schemes Rolling Programme
3.1Details of the supported 2011/12 discretionary schemes schedule, including a status and expenditure update, are shown in the table below:
Scheme / Purpose Status Expenditure Area Discretionary Other 2011/12 Budget Additional Allocation £ Contribution £ 2010/11 Safety Complete See following 16,500 Nil Related TROs formal item 3.2 (Phase 3) consultation Across the and PTRO East Herts implementatio District n 2011/12 Promote and See following 17,150 Nil Junction implement item 3.2 Protection PTROs PTROs Across the East Herts District Ranking of To keep the See following 1,000 Nil parking prioritisation of item 3.2 requests parking Across the requests East Herts current District HJMP Petition Provide Panel See following 8,000 Nil Responses reports in item 3.3 response to petitions New dropped Implement Works 5,500 Nil kerbs (pram pedestrian commenced in crossings) movement September Various, enhancement 2011 Bishop’s works Stortford C43 Lower Implement Works order Nil 14,000 (Section Road / C43 supported being prepared 106 funding) Amwell Lane driver for delivery by Great Amwell awareness the end of measures March 2012. Scheme / Purpose Status Expenditure Area Discretionary Other 2011/12 Budget Additional Allocation £ Contribution £ A414 / Thieves Implement Works have 3,000 27,000 (routine Lane pedestrian been ordered maintenance Hertford access for completion funding) (northern side improvements by the end of of the A414) March 2012. Hertingfordbur Implement Works due to 8,000 (includes Nil y – St Mary’s footway and commence in 3,000 for St Lane signing November 2011 Mary’s Lane Hertingfordbur improvements signing scheme) y Scheme / Purpose Status Expenditure Area Discretionary Other 2011/12 Budget Additional Allocation £ Contribution £ A1184 London Implement Works have 13,650 Nil Road identified been ordered Spellbrook works from for completion 2010/11 by the end of feasibility March 2012. study during 2011/12 Complete To be investigation progressed from 2010/11 during 2011/12 feasibility study during 2011/12 Rye Street (at Implement Works have 11,000 (other 9,000 (routine Meadowlands) identified been ordered supported maintenance Bishop’s works from for completion recommendations funding) Stortford 2010/11 by the end of resulting from the feasibility March 2012. feasibility study study have been identified for delivery via routine maintenance works) Spellbrook Joint-funding See following 2,000 1,000 (Locality Lane East contribution to item 3.4 Budget, subject Sawbridgewort HMWT to successful h application) Totals 85,800 51,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.