Investment Fund - Projects for Pipeline Inclusion and Approvals
AgreedCommittee1 paper
AI summaryEMCCA Investment Committee delegates approval of £2.944m for Derby Market Place to a director, and notes £969,336 already approved for Giltbrook industrial units.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDirector gets authority, subject to extra information
Money£2.944mEMCCA share of £5.409m Derby Market Place project
What happens nextGrant Funding AgreementOnce GVA and benefit analysis supplied to members
Who it affectsDerby Market Place regenerationBrownfield demolition and enabling works
What was decided
The Committee agreed unanimously to delegate authority to approve £2.944m of capital investment for the Derby Marketplace project to the Director of Economic Growth and Innovation, in consultation with the Investment Committee Chair, on condition that requested GVA and economic benefit analysis information is supplied to members. Report P9
The Committee noted the progress of final business case approvals made under delegated authority since the April 2026 Investment Committee meeting, including the Greening Growth at Giltbrook project. Report P11, P12
Why
The Derby Market Place final business case is being recommended by the EMCCA Investment Panel following the project's inclusion on the investment pipeline at the EMCCA Board meeting on 9 March 2026. Report P9, 2.1
EMCCA holds £19m of annual capital funding through its Investment Fund and aims to drive inclusive growth across the region through place-based investment decisions. Report P3, P4
What happens next
The Derby Market Place project will enter into a Grant Funding Agreement with EMCCA and begin delivery once the GVA and economic benefit analysis has been provided to Committee Members. Report P9
The Greening Growth at Giltbrook grant funding agreement has been completed and the £0.97m grant is expected to be paid out in quarters 2 and 3 of 2026/27, with delivery monitored by the EMCCA Investment Team. Report P12, P23
The money
£2.944m EMCCA Investment Fund capital contribution to Derby Market Place Report 2.1, P16
£5.409m Total Derby Market Place project cost Report P16
£2.465m Derby City Council match funding for Derby Market Place Report P16
£0.99m EMCCA share profiled for 2026/27 Report P17
£1.954m EMCCA share profiled for 2027/28 Report P17
£65.14m Investment Fund capital budget for 2026/27 and 2027/28 Report P18
£27.6m Capital currently committed from the Investment Fund Report P18
£969,336 Greening Growth at Giltbrook capital investment under delegated approval Report 2.1, P12
£0.97m Giltbrook grant value expected to be paid in 2026/27 Report P23
£35 million Indicative value of 19 projects added to the Investment Fund pipeline since November 2025 Report P6
Options considered
Chosen: Delegate approval of £2.944m Derby Market Place investment to the Director of Economic Growth and Innovation, subject to GVA and benefit analysis being supplied to members. Recommended by EMCCA Investment Panel and aligns with Single Assurance Framework delegations Report P9
Chosen: Note delegated approval of the Greening Growth at Giltbrook project since the 20 April 2026 Investment Committee. For noting only, in line with the scheme of delegation under the Single Assurance Framework Report P12
Implications
Financial: The £2.944m represents a committed call on the Investment Fund capital programme, fully funded with no borrowing and no direct revenue implications for EMCCA; match funding is confirmed by Derby City Council. Report P16, P17, P19
Financial: The capital budget for 2026/27 and 2027/28 is £65.14m, of which £27.6m is committed, leaving sufficient uncommitted budget for this proposal. Report P18
Financial: Funding will be released through a Grant Funding Agreement with milestone-based payments, monitoring and clawback provisions; delivery risk is transferred to the developer and contractor. Report P20
Legal: The funding must be documented and operated as a genuine grant rather than a public contract, with conditions framed around eligible use of funds, milestones, clawback and subsidy control compliance. Report P28
Legal: Officers must confirm the award is compliant with the Subsidy Control Act 2022 before the agreement is completed. Report P28
Legal: Appendix A (Derby Market Place FBC) is commercially sensitive and is exempt from publication, subject to the public interest test. Report P27
Risk: The wider Derby Market Place regeneration programme may bring forward future funding requests for subsequent phases, which would require separate business case approvals. Report P21
Who and where
Derby City Council (match funder and project partner) Report P16, P21
Broxtowe Borough (location of Giltbrook industrial units) Report P12
Greening Growth at Giltbrook project (developer and contractor) Report P12, P20
EMCCA Investment Team (monitoring role) Report P12
Timeline
9 March 2026: Derby Market Place added to the investment pipeline at the EMCCA Board meeting Report P9
20 April 2026: Last Investment Committee meeting before this report Report P12
2026/27: £0.99m of EMCCA Derby Market Place funding profiled, plus Giltbrook grant payments in quarters 2 and 3 Report P17, P23
2027/28: £1.954m of EMCCA Derby Market Place funding profiled Report P17
29 June 2026: Investment Committee decision date
Plain English for the jargon
EMCCA: East Midlands Combined County Authority, a devolved place-based institution
FBC: Final Business Case, the last approval stage under the Single Assurance Framework
GVA: Gross Value Added, a measure of economic output used in appraisal
Single Assurance Framework: EMCCA's process for adding projects to the pipeline and approving business cases, including delegated authority limits
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
RESOLVED to unanimously agree: A) That the authority to approve the £2.944m capital investment for the Derby Marketplace project be delegated to the Director of Economic Growth and Innovation, in consultation with the Chair of the Investment Committee, subject to the requested GVA and economic benefit analysis information being provided to Committee Members. B) That the progress of Final Business Case Approvals under delegated authority since the Investment Committee in April 2026 be noted.
Word for word from the decision East Midlands Combined County Authority published for this meeting.Source: democracy.eastmidlands-cca.gov.uk
Follow this further
Built from East Midlands Combined County Authority's papers
2.1This report seeks approval of the final business case for the £2.944 million capital investment in the Derby Market Place project, following recommendation by the EMCCA Investment Panel. It also notes the delegated approval since the last meeting of the Investment Committee in April 2026 of the £969,336 capital investment in the Greening Growth at Giltbrook project.
Background
3.1Investment Fund pipeline and delivery
As a place-based institution with devolved powers, EMCCA plays a pivotal role in shaping and delivering strategic investment that aligns with long-term regional priorities. Through its convening power and role in regional strategy making, democratic mandate, and understanding of local needs gleaned in part from close engagement with regional partners, the EMCCA Board is well positioned to make informed choices about the deployment of public funds for investment. These decisions are not only about economic return, but also about fulfilling the Board’s self-confirmed ambition to drive inclusive growth across the region.
EMCCA has capital funding capacity for bringing forward public investment to achieve the priorities to be set out in the East Midlands Growth Plan and at the centre of this funding is the £19m capital investment received each year through its Investment Fund to invest in growth.
A process to identify projects for investment in Autumn 2025 funding round was initiated and is being delivered in conjunction with the Board’s decision to continue to develop longer-term strategic interventions to be developed over the following years, which is now happening through the Local Growth Fund (see separate paper). Following extensive proposals submitted for funding, projects have been brought forward that largely focus on shorter term and more deliverable and were invited to enter the EMCCA Investment Pipeline.
Following the process to identify projects to be brought forward for development the Investment Committee and EMCCA Board have since November 2025 added 19 projects to the pipeline for the Investment Fund with an indicative value of approximately £35 million (see Investment Portfolio report paper on this agenda).
4. Investment Decisions
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Committee at East Midlands Combined County Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingRESOLVED to unanimously agree: That the minutes of the meeting of the Investment Committee held on 29 June 2026 be ap...
Investment Committee Work ProgrammeRESOLVED to unanimously agree: A) That the draft Work Programme attached at Appendix A be approved and that regular u...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.