AI summaryEMCCA Investment Committee approved 17 of 18 Local Growth Fund Concept Initiation Documents for the Investment Pipeline, paving the way for £107m over four years across five intervention areas to support the East Midlands Growth Plan.
Money£107m over four yearsLocal Growth Fund: £60m capital and £47m revenue
What happens nextFull Business Case approval neededEach project progresses under Single Assurance Framework
Who it affectsEast Midlands residents, businesses, young peopleFive intervention areas across skills, growth, places
What was decided
The Committee approved 17 of the 18 Concept Initiation Documents set out in Appendix A for inclusion on the EMCCA Investment Pipeline, following delegation by the EMCCA Board on 8 June 2026. Report 6.1, P34
The Committee noted that individual project approval and delivery will be progressed in accordance with the EMCCA Constitution and Single Assurance Framework. Report P42
Why
The Local Growth Fund gives EMCCA a four year £107m flexible settlement to support the East Midlands Growth Plan and Inclusive Growth Framework, and an Investment Plan setting out outcomes has now been agreed by the EMCCA Board and Government. Report 2.1, 3.2
Five intervention areas were derived through a gap analysis of existing programmes and funding already in place, and were approved by the EMCCA Board on 8 June 2026 with indicative allocations of the £107m. Report P12, P13, P18
The approach moves away from open calls and competitive bidding towards a strategic commissioning and co design model with partners, directing funding to high impact activity that reflects regional strategy and place based need. Report P8, P9, P10
What happens next
Approved Concept Initiation Documents will progress through the EMCCA Investment Pipeline to Final Business Case development and delivery under the Single Assurance Framework or EMCCA Constitution. Report 2.2, P42
Future approvals will be subject to full affordability, value for money, subsidy control, procurement, and due diligence assessments at Full Business Case stage. Report P39, 6.4
A separate report will be brought forward for the £3.4m Skills Capital workstream, which is not included in this approval. Report P37
The money
£107m Total Local Growth Fund over four years (£60m capital and £47m revenue) Report 2.1, P34
£3.12m Overhead provision for programme management, overheads, and support service costs, including EMCCA staffing Report P18, P35
£3.4m Skills Capital workstream, not included in this approval and to come back in a separate report Report P37
£24m Year 1 funding already received, so approved programmes will not be delivered at EMCCA financial risk Report P36
Options considered
Chosen: Approve 17 of 18 Concept Initiation Documents onto the EMCCA Investment Pipeline. Sets the strategic framework for the £107m Local Growth Fund following Board delegation on 8 June 2026 Report P19, 6.1
Rejected: Include the £3.4m Skills Capital workstream in this approval. A separate report will be brought forward for the Skills Capital workstream Report P37
Implications
Financial: Approval represents a contingent commitment against the £107m Local Growth Fund, not a final funding or contractual commitment, and is subject to Full Business Case approval. Report 6.1, P34
Financial: Funding profiles are indicative; Local Growth Fund terms allow up to 30% reprofiling between financial years across the life of the programme. Report P36
Financial: The programme is weighted towards revenue in early years and capital in later years, requiring active financial management to align with delivery capacity and affordability. Report P34
Staffing: Staffing needed to deliver the programme is funded from the Local Growth Fund allocation but must be absorbed within existing budgets beyond the life of the programme. Report P35
Legal: Each project will be subject to a subsidy control assessment and/or procurement consideration prior to approval, under the EMCCA Constitution, Scheme of Delegation and Single Assurance Framework. Report 6.4
Risk: The pipeline approach is designed to manage financial risk by sequencing delivery and only committing funding to schemes that meet assurance requirements and fit the Local Growth Fund envelope. Report P38
Who and where
East Midlands residents, including those who are economically inactive and young people, through Opportunity Escalator interventions on skills and employment Report P21, P22
Businesses across the region, through an expanded business support offer, a Business Investment Fund, and visitor economy investment Report P23, P24
High growth businesses and cluster sectors, including advanced manufacturing and clean industries, through cluster development and innovation support Report P25, P26
Sites and growth areas for strategic development, including brownfield housing and the three East Midlands Investment Zone sites Report P27, P28
Communities across the region, including rural areas, through the Thriving Places Fund, Rural Development Fund, Community Energy and Community Development programmes Report P29, P30
Local authorities and accountable bodies acting on behalf of EMCCA, who may use a proportion of funding for programme management costs Report P35
Timeline
23 February 2026: Strategic Investment Next Steps report published, signalling a shift towards strategic, collaborative investment based on thematic commissioning Report P8
8 June 2026: EMCCA Board approved the Local Growth Fund Investment Plan and the five intervention areas with indicative allocations Report P12, 6.6
Plain English for the jargon
CID: Concept Initiation Document, the early stage document for a project or programme on the EMCCA Investment Pipeline.
LGF: Local Growth Fund, a multi year flexible funding settlement for Mayoral Strategic Authorities.
EMCCA: East Midlands Combined County Authority, the Mayoral Strategic Authority for the region.
EMGP: East Midlands Growth Plan, the regional growth strategy that Local Growth Fund projects align to.
EMIZ: East Midlands Investment Zone, with up to £160m of funding to support advanced manufacturing and clean industries.
FBC: Full Business Case, the later stage of approval each project must reach under the Single Assurance Framework.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
RESOLVED to unanimously agree: a) That the Concept Initiation Documents in Appendix A be approved and that the projects and programmes be entered onto the EMCCA Investment Pipeline, following delegation by the EMCCA Board on 8 June 2026. b) That it be noted that individual project approval and delivery would be progressed in accordance with the EMCCA Constitution and Single Assurance Framework.
Word for word from the decision East Midlands Combined County Authority published for this meeting.Source: democracy.eastmidlands-cca.gov.uk
Follow this further
Built from East Midlands Combined County Authority's papers
2.1The Local Growth Fund gives EMCCA a four-year £107m flexible settlement to support delivery of the East Midlands Growth Plan and Inclusive Growth Framework. Following Board approval of the Investment Plan and agreement with Government, the programme now has an agreed framework for investment and delivery from 2026/27.
2.2The approved programme brings forward thematic programmes of delivery across five intervention areas: Opportunity Escalator, Business Growth and Investment, Cluster Development and Innovation, Strategic Development, and Thriving Places. Funding is profiled across four years, with Concept Initiation Documents for those programmes now able to progress through the EMCCA Investment Pipeline to Final Business Case development and delivery under the Single Assurance Framework or EMCCA Constitution.
Background
3.1Government has announced a multi-year Local Growth Fund (LGF) intended to provide Mayoral Strategic Authorities with a flexible funding settlement to support local Growth Plans. A total of £900m is being targeted at 11 Mayoral Strategic Authorities across the Midlands and the North. Allocations have been based on productivity and agglomeration potential, with all eligible areas receiving some level of funding. The funding is intended to complement wider reforms to local government finance and sit alongside existing delegated funding streams, including Transport for City Regions and Pride in Place. LGF is explicitly designed to be used alongside other public and private funding sources to progress priority projects tailored to deliver local growth plans.
3.2EMCCA has prepared an Investment Plan outlining how the funding will be deployed, drawing on the Government’s published logic model. Although LGF provides flexibility, areas without an integrated settlement, such as EMCCA at present are required to set out a clear and coherent plan for investment, including defining the outcomes to be achieved in a framework within the Investment Plan. This has been agreed by the EMCCA Board and Government now, meaning that funds can be delivered to enable delivery in the 2026/27 financial year.
3.3The £107m funding has been split across four years for the total programme and contains a mixture of Capital and Revenue funding. The balance of funding moves from revenue heavy at the beginning of the profile to capital heavy in the later years. The allocations are shown in the table below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Investment Committee at East Midlands Combined County Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingRESOLVED to unanimously agree: That the minutes of the meeting of the Investment Committee held on 29 June 2026 be ap...
Investment Committee Work ProgrammeRESOLVED to unanimously agree: A) That the draft Work Programme attached at Appendix A be approved and that regular u...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.