Resolved
View the decision text for item 94/18
Cabinet decided this item on Wednesday 13 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 94/18
On 5 July 2017, Cabinet discussed and recommended that the CIL Allocation Process be changed to include ringfencing within CIL a Strategic Infrastructure Project Programme (SIPP) fund.
The SIPP fund allows the Council to address larger issues through priority projects which have a longer-term approach, and to give partners certainty to progress schemes. It also increases the Council’s eligibility to access other sources of funding for infrastructure projects including Local Enterprise Partnership (LEP) funding.
One of the projects discussed in July 2017 that would require the Strategic Infrastructure Project Programme funding was the Brooklands Business Park Accessibility Project. The project is being delivered in partnership with Surrey County Council (SCC) and has received Enterprise M3 LEP funding of £2,172,000. However, this award of funding is reliant on £625,000 of local match funding from the Council, which has been proposed to come from the CIL Strategic Infrastructure Project Programme.
The Business Case for the project has been approved, and the project now requires the allocation of the CIL funds to the Brooklands Business Park Accessibility Project.
Recommended: that
(a) Cabinet approve the allocation of £625,000 from the CIL Strategic Infrastructure Project Programme to the Brooklands Business Park Accessibility Project.
Report:
1. CIL Background
1.1The Council adopted CIL in April 2013. CIL allows the Council to raise funds from some forms of new development to pay for infrastructure that is, or will be, needed to mitigate the impacts of development. As set out in the CIL Regulations, an initial 5% is retained by the Borough Council for administration costs. The remaining CIL receipts are spent in accordance with the regulations and the approach adopted by Cabinet and Council in July 2017. That is:
40% top slice of CIL collected (post allocation to administration and Suitable Alternative Natural Greenspace (SANG)) is ring fenced to fund a programme of strategic infrastructure projects; 35% of CIL is allocated through the Strategic Spending Board to more ad- hoc strategic improvements required to address the impacts arising from development across the Borough; 15% is allocated through the Local Spending Boards (and in the case of Claygate, to the Parish Council); and 10% of CIL is ringfenced (post allocation to administration and SANG) for maintenance purposes.
1.2The River Thames Scheme was also discussed in July 2017 as a project that would require the Strategic Infrastructure Project Programme structure. On 15 November 2017, the River Thames Scheme was discussed again by Cabinet due to an urgency around flood protection and it was resolved: (b) the Council’s ‘in principle’ agreement to fund Elmbridge’s contribution of £1.8 million from the Community Infrastructure Levy (CIL) Strategic Infrastructure Projects Fund be supported.
2. Brooklands Business Park Accessibility Project
2.1The primary focus of the project is to improve accessibility to the Brooklands Business Park, the Borough’s principal strategic employment area.
The Brooklands Business Park is home to approximately 250 businesses and provides 9,000 jobs with the likes of Sony, Proctor & Gamble, LG Electronics located on the park alongside leading tourism assets such as Brooklands Museum and Mercedes-Benz World.
Improving connectivity and accessibility is key to supporting future growth, ensuring the retention of world class high value businesses and better linking the business park to the station and the town centre to ensure Weybridge remains a great place to live and work.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Community Infrastructure Levy (CIL) Strategic Project Programme: Brooklands Business Park Accessibility ProjectReport | 5 pages | DownloadRead as text |
PDF |
Enc. 1 for Community Infrastructure Levy (CIL) Strategic Project Programme: Brooklands Business Park Accessibility Project /18Report | 8 pages | Download |
PDF |
Enc. 2 for Community Infrastructure Levy (CIL) Strategic Project Programme: Brooklands Business Park Accessibility Project /18Report | 4 pages | Download |
PDF |
Enc. 3 for Community Infrastructure Levy (CIL) Strategic Project Programme: Brooklands Business Park Accessibility Project /18Report | 1 pages | Download |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.