Resolved
View the decision text for item 74/22
Cabinet decided this item on Wednesday 15 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 74/22
Through the Council’s Strategic Priority Programme (SPP), projects delivering borough-wide infrastructure that support development and enable future growth are invited to submit an application for Community Infrastructure Levy (CIL) funding from the strategic pot. Two applications for strategic funding for Cabinet’s consideration are set out within this report. The total amount requested through these applications is £1,132,500. At the end of Q3 2022-23, there was £11,198,000 (unallocated) in the strategic pot.
Recommended: that
(a) Cabinet considers the applications for Strategic CIL funding and determines the amounts to be awarded.
Report:
1. Community Infrastructure Levy – Strategic Spending
1.1In Elmbridge Borough, the Council has determined that its CIL receipts for strategic borough-wide infrastructure to bring forward development and enable future growth are to be administered through the Strategic Priority Programme (SPP).
1.2For the 2022/23 CIL funding round, Cabinet agreed the SPP list at their meeting on 6 July 2022, the list includes infrastructure to improve walking and cycling in the borough.
1.3Subsequently, two applications for CIL funding are being presented to Cabinet. These are: CIL Project CIL Request Application: 1 Cobham Core Walking Zone (Local Cycling £352,500 and Walking Infrastructure Plan (LCWIP)): Surrey County Council (SCC) (Appendix 2) 2 Hampton Court Way Cycle Route (LCWIP): £780,000 SCC (Appendix 3) Total requested £1,132,500
1.4Both applications are on the SPP list as imminent (2022-23) to short-term (2023-24) projects, however, were not considered by Cabinet on 16 November 2022 with the other project for this year as the SCILWG requested that additional engagement with Councillors be undertaken. Initial engagement has now been completed including Member Briefing Sessions held on 26 January 2023. As outlined below, further engagement will continue as the projects progress.
2. A background to LCWIPs
2.1The County Council is working to develop an LCWIP for every borough and district to cover the whole county by the end of 2023. LCWIPs are key transport planning documents, setting out a ten-year plan for a defined area (such as a town, district, or borough) identifying where investment should be prioritised in order to create a strategic network of walking and cycling routes.
2.2The overarching vision behind the LCWIP is one which supports strong and sustainable growth and a high quality of life through investment in active travel and an enhanced public realm. By making active travel modes a more attractive and safer means of travel, it is envisioned that projects will help contribute to reduced levels of congestion due to residents opting to replace short car trips with active travel modes. Thus, also contributing to decarbonisation targets, improved health and wellbeing due to physical activity, and providing placemaking benefits.
2.3LCWIPs are a primary delivery mechanism for achieving SCC’s newly adopted Local Transport Plan 4 and are integrated with Elmbridge Borough Council’s Vision 2030. The delivery of LCWIPs will help contribute towards the guiding principles and objectives for new development as set out in the draft Local Plan 2037. LCWIPs will be key to helping create more ‘liveable neighbourhood’; connecting people and the neighbourhoods they live, work and visit to the wider active travel network through streets that are safe, easy, comfortable and accessible for people of all abilities, ages and confidence levels.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Application for Strategic CIL Funding for the Cobham Core Walking Zone /22Appendix 2 | 13 pages | Download |
PDF |
Application for Strategic CIL Funding for the Hampton Court Way Cycle Route /22Appendix 3 | 14 pages | Download |
PDF |
Elmbridge LCWIP Report /22Appendix A | 178 pages | Download |
PDF |
Strategic Community Infrastructure Levy (CIL) ApplicationsReport | 8 pages | DownloadRead as text |
Follow Cabinet at Elmbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Oct 2026 | Old Post Office EsherView the decision text for item 22/26 | Decided | Open |
| 16 Sep 2026 | Disposal of land in Oaken Lane, Claygate, EsherView the decision text for item 15/26 | Decided | Open |
| 16 Sep 2026 | Water Play Strategy UpdateView the decision text for item 16/26 | Decided | Open |
| 16 Sep 2026 | Elmbridge Local Plan 2039: Notice of commencement of plan-making and Local Plan timetableView the decision text for item 17/26 | Decided | Open |
| 16 Sep 2026 | 2026/27 Revenue and Capital Budget Update - Quarter 1View the decision text for item 19/26 | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.