(1) That Arts and Heritage Society (“the Society”) be selected as the preferred bidder for the refurbishment of for community use; (2) That, subject to the Society being successful in its bid for funding to the Heritage Lottery Fund, Officers be authorised, in consultation with the Vice Chairman of the Strategy and Resources Committee, to conclude an agreement with the Society on such terms as thought fit, covering matters related to the above, to include: a) Terms for the release of up to £1.45million in grant funding to support the refurbishment of the Chapel; b) Terms for the transfer of the Chapel to the Society for nil consideration.
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
2.1The Council has, for several years, been grappling with the issue of how to bring Horton Chapel into community use. Details of what has been done over the years were set out in previous reports to committee. Most recently, in January 2016, the Committee gave approval to a bid process prioritising at first bids from those wishing to refurbish the Chapel for a community purpose.
2.2A report in June 2016 set out the progress which had been made and put draft assessment criteria before members for consideration. This report outlines the outcome of that bid process and seeks a decision to take the project to the next stage.
3 Proposals
3.1Four proposals have been submitted, from the following:
3.1.1 Horton Chapel Arts & Heritage Society
3.1.2 Hindu Mauritian Sabha (UK) Limited
3.1.3 Oasis Church
3.1.4 Councillor Omer Kokou-Tchri (Horton International Creative & Design Centre – from “Epsom First”)
3.2Each of these has been evaluated against the criteria which the committee considered at the meeting on 21 June 2016. A summary of the proposal and assessment of each bid is attached at Annexe 1.
3.3As a result, the highest scoring bid is that from the Horton Chapel Arts & Heritage Society.
3.4The main assumption in scoring this bid is in relation to the availability of funding. It has been assumed that the Society will be successful in obtaining funding from the Heritage Lottery Fund. Acceptance of the bid is proposed conditionally on that funding being secured. If it is not, then we will approach the second highest scoring bid, or, failing that, report back to Committee. STRATEGY AND RESOURCES COMMITTEE 27 SEPTEMBER 2016
4 Asset Management Plan
4.1Appendix 4 to the Plan deals with acquisitions and disposals.
4.2In summary, the disposal criteria are set out below, with a comment as to the position in this case:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.