The Committee: (1) Accepted the Four Year Settlement for Central Government in conjunction with the following actions: a) That the approved cost reduction plan is renamed the Efficiency Plan and the MTFS is retitled the MTFS and Efficiency Plan b) That the Chief Executive, in consultation with the Chairman and Vice Chairman of the Strategy and Resources Committee be authorised to make such further changes as they consider appropriate to the MTFS and Efficiency Plan, for example, to enable the Council to respond to any emerging guidance or good practice and meet the 14 October deadline; c) That Members and Leadership Team develop the Efficiency Plan during October to January as part of the 2017/18 budget setting process. (2) The following overall revenue budget target for 2017/18: a) The preparation of estimates including options to reduce organisational costs by £556,000 to minimise the use of working balances and maintain a minimum working balance of £2.5m in accordance with the medium term financial strategy; b) The generation of at least £200,000 additional revenue from an increase in discretionary fees and charges, based on minimum overall increase in yield of 3% in 2017/18; c) That a provision for 2017/18 pay award is made of £180,000 which represents a 1% pay increase and 0.6% progression; (3) That further efficiencies be identified to address the budget shortfalls of £220,000 in 2017/18, £374,000 in 2018/19 and £688,000 in 2019/20; (4) That Capital Member Group seek to limit schemes included within the capital expenditure programme that enable retention of agreed minimum level of capital reserves
Word for word from the decision Epsom and Ewell published for this meeting.Source: democracy.epsom-ewell.gov.uk
STRATEGY AND RESOURCES COMMITTEE 27 SEPTEMBER 2016
BUDGET TARGETS 2017/18
Report of the: Chief Accountant Contact: Michael Smith Urgent Decision?(yes/no) No If yes, reason urgent decision required: N/A Annexes/Appendices (attached): Annexe 1 – Four Year Settlement Brief Annexe 2 – Updated Four Year Plan Other available papers (not attached): Policy Book 2016/17
REPORT SUMMARY This report updates the financial forecast and recommends financial targets for preparing the draft budget for 2017/18 and financial planning for 2018/19 & 2019/20.
Notes RECOMMENDATION (S)
That the Panel recommends to the Strategy and Resources Committee:-
1) That the Council accepts the Four Year Settlement from Central Government with the following actions:
a) That the approved cost reduction plan is renamed the Efficiency Plan and the MTFS is retitled MTFS and Efficiency Plan.
b) That the Chief Executive in consultation with the Chairman and Vice Chairman of Strategy and Resources be authorised to make such further changes as they consider appropriate to the MTFS and Efficiency Plan, for example, to enable the Council to respond to any emerging guidance or good practice and meet the 14 October 2016 deadline.
c) That Members and Leadership Team develop the Efficiency Plan during October to January as part of the 2017/18 budget setting process. STRATEGY AND RESOURCES COMMITTEE 27 SEPTEMBER 2016
2) The following overall revenue budget target for 2017/18: a) Estimates are prepared including options to reduce organisational costs by £556,000, to minimise the use of working balances and maintain a minimum working balance of £2.5m in accordance with the medium term financial strategy; b) That at least £200,000 additional revenue is generated from an increase in discretionary fees and charges, based on minimum overall increase in yield of 3% in 2017/18; c) That a provision for 2017/18 pay award is made of £180,000 which represents 1% pay increase and 0.6% for progression. 3) That further efficiencies be identified to address the budget shortfalls of £220,000 in 17/18, £374,000 in 18/19 and £688,000 in 19/20. 4) That Capital Member Group seek to limit schemes included within the capital expenditure programme that enable the retention of agreed minimum level of capital reserves.
1 Implications for the Council’s Key Priorities, Service Plans and Sustainable Community Strategy 1.1 The Medium Term Financial Strategy aims to maintain the financial health of the Council whilst delivering the priorities in the Corporate Plan. 2 Background 2.1 The Strategy and Resources Committee has agreed the following key service priority: 2.1.1 Set budget targets for 2017/18 that keeps the tax level below the Surrey average. 2.1.2 Delivery of the Financial Plan for 2016-2020 whilst limiting use of New Homes Bonus. 2.2 It is the Financial Policy Panel’s role to advise the Strategy and Resources Committee on all matters relating to the budget and policy framework. 3 Introduction 3.1 The Council carried out a comprehensive review of its finances leading to the approval of the Four Year Financial Plan 2016-20. STRATEGY AND RESOURCES COMMITTEE 27 SEPTEMBER 2016
3.2The major challenge for the Council is to deliver year-on-year savings to achieve a balanced budget during the funding cuts faced in the four year settlement.
3.3To address the funding shortfall the Council has reported a new medium term financial strategy and an efficiency saving programme to reduce actual spending in cash terms.
4 Government Four Year Settlement
4.1The funding outlook for the Council has changed significantly for the four years following the final financial settlement in early 2016. A widely expected phased cut to funding was front loaded and leaves the Council with no Revenue Support Grant from 2017/18 onwards, and an overall 66% reduction in funding between 15/16 and 19/20. The baseline funding for 2017/18 is £1.4m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Committee at Epsom and Ewell and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.