P/25/1272/FP - Former HCC Depot Land Adjoining Cartwright Drive and Southampton Road Titchfield Fareham

Agreed Planning 1 paper

AI summaryFareham Planning Committee grants permission for a Lidl foodstore of 2,164 sqm on the former HCC depot at Titchfield, subject to a Section 106 agreement including £189,195.80 for sustainable transport improvements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFull planning permission, subject to conditions and S106
Money£189,195.80 S106 contributionIndex-linked to April 2026, for transport improvements
What happens nextS106 agreement then conditionsAuthority delegated to Head of Planning
Who it affectsFormer HCC depot, Titchfield1.3 ha site adjoining Cartwright Drive and A27

What was decided

The committee granted full planning permission for a Class E retail store of 2,164 sqm gross (1,457 sqm net sales), 121 car parking spaces, access works, cycle parking and a delivery bay. Report P3, 3.4

Permission is subject to the conditions in the report, the additional condition and amendment to the Section 106 Head of Term set out in the Update Report, and delegated authority to the Head of Planning to finalise conditions and obligations.

The development must begin within three years of the decision notice. Report P152

Why

Officers concluded the proposal satisfies the sequential test and retail impact assessment under Policies R1 and R2 and the NPPF, with no significant adverse effect on defined centres; the independent retail consultant agreed. Report 8.37, 8.38, 8.39, P47

The Local Highway Authority, LLFA, Southern Water, ecology, tree, environmental health, urban design, conservation and archaeology consultees raised no objection subject to conditions; the highway contribution resolves walking and cycling improvements at St Margaret's Roundabout and Cartwright Drive. Report P34, P35, 7.2, P37, P38, P39, P42, P43, P44, P45, P46, P49

Although the site is allocated for employment under Policies E1 and E4a, officers gave this limited weight because the borough has a confirmed oversupply of about 120,000 sqm of employment floorspace, and the proposal delivers direct and indirect jobs equivalent to 25 to 30 full-time posts. Report 8.6, 8.7, 3.3, 8.75

What happens next

The applicant must first enter into a Section 106 agreement covering the £189,195.80 sustainable transport contribution, HCC travel plan fees of £1,500 approval and £15,000 monitoring, a £16,555 travel plan bond, and biodiversity net gain monitoring. Report P141, P142, P143, P144, P145, P146, P147, P148, P149, 9.2

Pre-commencement conditions require a Construction Environment Management Plan, drainage details, a Biodiversity Gain Plan and, if significant on-site habitat gain is proposed, a Habitat Management and Monitoring Plan. Report P163, P164, P165, P166

Conditions restrict use to Class E(a) retail with a maximum 1,457 sqm net sales area (no more than 20% comparison goods) and prevent subdivision of the store. Report P154, P155

The money

  • £189,195.80 Section 106 financial contribution (index-linked to April 2026) for sustainable transport improvements under the Fareham LCWIP Report P35, P143
  • £1,500 HCC fee for approval of the Staff Travel Plan Report P147
  • £15,000 HCC fee for monitoring of the Staff Travel Plan Report P147
  • £16,555 Bond or cash deposit (including 10% surety) for costed measures in the travel plan Report P148

Options considered

  • Chosen: Grant full planning permission subject to conditions and Section 106 agreement (officer recommendation). Sequential test and retail impact satisfied; no severe highway impact; design, amenity, ecology, flood risk and BNG acceptable; employment land conflict limited by borough oversupply Report 9.0, 8.38, 8.75, 8.76, P135, P150
  • Rejected: Refuse on retail policy, highway or amenity grounds. Not supported by the planning balance in the report Report 8.75, 8.81

Implications

  • Financial: Section 106 secures £189,195.80 for walking and cycling improvements around St Margaret's Roundabout and Cartwright Drive, plus BNG monitoring contributions and HCC travel plan fees. Report P35, P143, P147, P149
  • Legal: A Section 106 legal agreement must be completed before permission is issued; delegated authority allows the Head of Planning to vary conditions and heads of terms. Report 9.0, 9.2
  • Equalities: The store is not considered incompatible with surrounding land uses; controls on deliveries, plant noise and lighting protect nearby residents on Farm Road. Report 8.52, 8.53, 8.54, P107
  • Climate: A roof-mounted photovoltaic array is designed to produce more than the store's regulated annual energy demand, with surplus exported; air source heat pumps, LED lighting and heat recovery are specified. Report 8.67, P124
  • Risk: Mandatory 10% Biodiversity Net Gain is delivered on-site at 10.48% area habitat units and 26.399% hedgerow units, secured by condition and S106 monitoring for at least 30 years. Report 8.60, 8.61, 8.62, P115
  • Other: Officers identify moderate weight conflict with employment allocation policies E1 and E4a, partly offset by a borough-wide oversupply of about 120,000 sqm of employment floorspace. Report 8.6, 8.7

Who and where

  • Lidl Great Britain Ltd (applicant) Report P2
  • Residents of Farm Road and other nearby properties Report 2.3, P29, 8.52
  • Users of St Margaret's Roundabout, Cartwright Drive and the A27 Report P27, P143
  • Fareham Town Centre retailers, including Tesco and Waitrose Report 8.30, 8.33, P90
  • District and local centres of Portchester, Stubbington, Whiteley and Locks Heath Report 8.32, 8.35, 8.36
  • Hampshire County Council as Local Highway Authority and Lead Local Flood Authority Report P34, P37

Timeline

  • 9 January 2026: Additional noise information submitted to Environmental Health Officer Report P45
  • 13 February 2026: Applicant submitted further sequential and impact information Report 8.11
  • 2 March 2026: Further information submitted on cumulative retail impacts Report 8.11
  • 31 March 2026: Lead Local Flood Authority consultation response received, no objection subject to conditions Report P37
  • 27 April 2026: Drainage easements confirmation letter issued Report P153
  • 20 May 2026: Planning Committee resolves to grant permission, subject to S106 and conditions Report P1
  • Within 3 years of the decision notice: Development must begin Report P152

Plain English for the jargon

  • Section 106 agreement: A legal agreement between a developer and the local authority, used to secure planning obligations such as financial contributions or works.
  • Sequential test: A planning test for main town centre uses outside defined centres, requiring applicants to demonstrate no suitable, available or viable town centre or edge-of-centre sites exist.
  • Biodiversity Net Gain (BNG): A requirement that development delivers at least a 10% measured improvement in habitat value, maintained for at least 30 years.
  • Class E(a): Use class covering the retail sale of goods other than hot food, to visiting members of the public.
  • LCWIP: Local Cycling and Walking Infrastructure Plan, identifying priority routes for improvement.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6(1)

Resolved

RESOLVED that: - (i) GRANT planning permission, subject to: - (a) the Conditions in the report; (b) the additional condition and amendment to the Section 106 Head of Term as set out in the Update Report. THEN (ii) Authority DELEGATED to the Head of Planning to: - (a) Make any necessary modification, deletion or additions to the proposed conditions or heads of terms for the section 106 legal agreement; and (b) Make any necessary changes arising out of detailed negotiations with the applicant which may necessitate the variation, addition or deletion of the conditions and heads of terms as drafted to ensure consistency between the two sets of provisions.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Planning Committee

OFFICER REPORT FOR COMMITTEE DATE: 20/05/26

P/25/1272/FP TITCHFIELD WARD LIDL GREAT BRITAIN LTD AGENT: MR C TOOKEY

DEVELOPMENT OF CLASS E RETAIL STORE WITH ASSOCIATED PARKING, LANDSCAPING AND ACCESS WORKS.

FORMER HCC DEPOT, LAND ADJOINING CARTWRIGHT DRIVE AND SOUTHAMPTON ROAD, FAREHAM

Report By Heather Lealan – direct dial 01329 824595

1.0Introduction 1.1 This major planning application is being brought before the Planning Committee for determination due to the number of third-party representations received.

2.0Site Description 2.1 The application site comprises an area of open land, triangular in shape, and predominantly laid to hardstanding. The site measures approximately 1.3 ha and is located to the north of St Margaret’s Roundabout, occupying the corner formed by the junction of Southampton Road (A27) and Cartwright Drive.

2.2The land was previously used as a temporary highway’s depot, including associated temporary office accommodation. Vehicular access to the site is currently taken from Cartwright Drive, along the eastern boundary.

2.3The northern boundary of the site adjoins residential properties on Farm Road, beyond which lie a series of industrial units. The site is enclosed on all boundaries by a combination of fencing and mature vegetation. Internally, several mature trees are located adjacent to the northern boundary.

2.4To the southwest, across Southampton Road, is a petrol filling station with an associated convenience store, along with the Kites Croft Business Park and Industrial Estate. To the southeast, across Cartwright Drive, is a hotel and health club.

2.5The site lies within the urban area but outside any defined centre as shown on the Local Plan Policies Map.

2.6The site lies within Flood Zone 1, indicating that it is at low risk of flooding. 3.0 Description of Proposal 3.1 The proposal seeks planning permission for the erection of a 2,164 sqm Lidl retail store with a 1,457 sqm sales area, along with 121 car parking spaces, cycle parking, a delivery bay, and alterations to the site access.

3.2The application is supported by a range of submitted documents and drawings, including ecological assessments, transport assessments, and other technical reports.

3.3The development would employ up to 40 members of staff, equivalent to approximately 25–30 full-time posts.

3.4Access to the site would be taken from Cartwright Drive via a new access point created at the northeastern corner of the site. Car parking would be located to the south and east of the store, providing a total of 121 spaces, including 7 disabled spaces, 2 for electric vehicle charging spaces, as well as 5 spaces for motorcycles. Spaces will also be provided for 12 cycles for customers with additional spaces for staff.

3.5To the west of the proposed retail store are the warehouse, loading bay and external plant and substation.

3.6Landscaping and tree planting will be provided within the western corner of the site. The existing tree screening along the northern boundary would be retained, and the existing hedging along the remaining site boundaries would also be retained at varying heights.

4.0Policies 4.1 The following policies apply to this application:

Adopted Fareham Local Plan 2037

R1 Retail Hierarchy and Protecting the Vitality and Viability of Centres R2 Out-of-Town Proposals for Town Centre Uses E1 Employment Land Provision E4a Land North of St Margaret’s Roundabout TIN1 Sustainable Transport TIN2 Highway Safety & Road Network TIN4 Infrastructure Delivery D1 High Quality Design & Place Making D2 Ensuring Good Environmental Conditions D4 Water Quality & Resources HE4 Archaeology CC2 Managing Flood Risk and Sustainable Drainage Systems NE1 Protection of Nature Conservation, Biodiversity, and the Local Ecological Network NE2 Biodiversity Net Gain NE6 Trees, Woodland, and Hedgerows NE8 Air Quality

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/25/1272/FP: Former HCC Depot Land Adjoining Cartwright Drive and Southampton Road Titchfield FarehamReport 1.7 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
IB
Councillor Ian BastableVice-Chairman, present
JB
Councillor Joanne BurtonCommittee Member, present
SD
Councillor Steve DuganChairman, present
GF
Councillor Gemma FurnivallCommittee Member, present
SI
Councillor Stephen IngramCommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
JN
Councillor Jacquie NeedhamCommittee Member, present
PN
Councillor Paul NotherCommittee Member, present
KW
Councillor Kirsten WiltshireCommittee Member, present
AF
Anna FloyerCommittee Officer, expected
LS
Lee SmithOfficer, expected

More from Fareham Planning Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... Decided Open
9 Sep 2026 Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDRESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, ... Agreed Open
9 Sep 2026 P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... Decided Open
9 Sep 2026 P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... Decided Open