P/26/0474/CC - Welborne Northern Primary School Site Welborne Fareham
DecidedPlanning1 paper
AI summaryFareham Planning Committee raises no objection to Hampshire County Council's plan for a new 2-form entry primary school for 420 pupils at Welborne, subject to three boundary treatment conditions.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to three boundary treatment conditions
MoneyNot stated
What happens nextHampshire County Council to determineConsidering suggested boundary amendments
Who it affectsWelborne Garden Village communityFirst primary school for the new development
What was decided
Members raised no objection to the proposed 2-form entry primary school with 420 pupil places and SEN resource provision for an additional 10 pupils serving Welborne Garden Village. Report 3.0, 6.16
The response is subject to three conditions covering boundary treatments: the eastern boundary, the height at the main northern entrance, and submission of all boundary treatment details. Report P103, P104, P105
Why
Officers considered the proposals largely comply with the Welborne Plan, the Welborne Design Guide SPD, the Outline Planning Permission, the Strategic Design Code and the Chesterfield Neighbourhood Design Code. Report P101, 6.31, 6.49, 6.78
The eastern boundary does not align with the code because hedging is proposed on the inside of the fence with no detailing to break up the long expanse, and the main entrance would benefit from a lower railing to better respond to Dashwood Park. Report P101, 6.65, 6.75
A two-form entry school is acceptable rather than three-form entry because forecast pupil numbers justify 420 places plus 10 SEN places, and the Section 106 agreement specifies a 2FE northern primary school. Report 6.16, 6.30
What happens next
Hampshire County Council Officers are to suggest an amendment to move the eastern boundary fencing inside the proposed hedging. Report P103
Hampshire County Council Officers are to suggest an amendment to lower the boundary treatment height at the main northern entrance to better respond to Dashwood Park. Report P104
Hampshire County Council Officers are to request that detail of all boundary treatments is submitted. Report P105
Options considered
Chosen: Raise no objection subject to three boundary treatment conditions. Proposals largely comply with relevant plans and design codes; only boundary treatment details need amendment. Report 7.0, P101, P103, P104, P105
Implications
Other: The school is intended to open in 2028, alongside the first phase of housing, to meet the Section 106 requirement of opening prior to occupation of 600 residential units. Report 6.30
Other: The design includes spaces intended for flexible community use, such as the main hall, music and drama studio, and playing field pitches. Report 6.17, 6.35
Other: 41 staff car parking spaces are proposed, exceeding the 38-space minimum under Fareham's Non-Residential Parking Standards SPD. Report 6.38
Climate: The building design includes measures to optimise energy efficiency, including thermal performance and photovoltaic panels. Report 6.28
Who and where
Future primary school pupils of Welborne Garden Village (up to 420 plus 10 SEN) Report 3.0, 6.16
Residents of Welborne Garden Village, including those in Thakeham and Pye Homes housing developments under construction Report 1.3, 6.40
Hampshire County Council as applicant and determining authority Report 1.4, P2
The wider Welborne community who may use the school facilities outside school hours Report 6.17, 6.35
Timeline
30 September 2021: Outline planning permission for Welborne (P/17/0266/OA) granted, including provision of primary schools. Report 5.0
10 January 2024: Strategic Design Code and Streets Manual details approved (P/17/0266/DP/I). Report P18
20 May 2026: Fareham Borough Council Planning Committee considers consultation response to HCC application P/26/0474/CC. Report P1, 1.2
2028: Proposed opening year of the school, intended to be operational before occupation of 600 residential units under the Section 106 agreement. Report 6.30
Plain English for the jargon
2FE (two-form entry): A primary school intake size with two classes per year group, totalling 420 pupil places across seven year groups.
SEN resource provision: Special Educational Needs facilities within a mainstream school, in this case for an additional 10 pupils.
Section 106 agreement: A legal agreement between a developer and a local authority under which the developer agrees to provide infrastructure or contributions, here requiring the first primary school to open before a set housing threshold.
Strategic Design Code: A detailed design document required by the outline planning permission, setting out design standards for the whole Welborne development.
Neighbourhood Design Code: A more detailed design document for a specific neighbourhood within Welborne, in this case Chesterfield.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6(6)
Resolved
RESOLVED that Members RAISE NO OBJECTION to the Proposed New Build 2 Form Entry (2fe), 420 Pupil Place Primary School with SEN Resource Provision for an Additional 10 Pupils Serving the Welborne Garden Village Development to the North of Fareham subject to a) Hampshire County Council Officers suggesting an amendment to the eastern boundary to move the boundary fencing inside of the proposed hedging, and; b) Hampshire County Council Officers suggesting an amendment to the height of the boundary treatment at the main northern entrance to better respond to the adjacent Dashwood Park. c) Hampshire County Council Officers requesting detail is submitted of all boundary treatments.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
P/26/0474/CC UPLANDS & FUNTLEY WARD HAMPSHIRE COUNTY COUNCIL
PROPOSED NEW BUILD 2 FORM ENTRY (2FE), 420 PUPIL PLACE PRIMARY SCHOOL WITH SEN RESOURCE PROVISION FOR AN ADDITIONAL 10 PUPILS SERVING THE WELBORNE GARDEN VILLAGE DEVELOPMENT TO THE NORTH OF FAREHAM
WELBORNE NORTHERN PRIMARY SCHOOL SITE, WELBORNE, FAREHAM
Report By Lucy Knight – direct dial 01329 824579
1.0Introduction 1.1 Outline planning permission for Welborne (application reference P/17/0266/OA) was granted on 30th September 2021. Since then, the Strategic Design Code for Welborne required by the outline permission has also been approved as has a Neighbourhood Design Code for the part of Welborne to which this application relates (the Chesterfield neighbourhood).
1.2This application, which is being determined by Hampshire County Council (HCC), is the first application for the first primary school at Welborne and is presented to the Planning Committee given the significance of the proposal in the delivery of the new community.
1.3The Welborne development site is currently under construction. Work is underway on three areas of residential development and the Village Centre, with some of the houses now occupied.
1.4This application has been submitted by HCC. The County Council is able to determine its own planning applications and, in this instance HCC is the determining Authority. Fareham Borough Council has been consulted on the application as the site is located within its administrative boundary.
1.5The school is required in order to meet the needs of the first phase of development at Welborne. The Section 106 legal agreement entered into by the master developer and HCC amongst other parties when outline planning permission was granted in 2021 requires the delivery of various infrastructure at Welborne, including this first primary school before a certain stage is reached in the development. 1.6 This report details if officers consider that the proposal complies with the relevant local plan policies and the Welborne Design Guide SPD. It also considers whether the application is in alignment with the outline planning permission and the approved Strategic Design Code and Neighbourhood Design Code for Chesterfield. The report concludes by setting out a recommendation of what FBC’s response to HCC should be in response to being consulted on this application.
2.0Site Description 2.1 The application site is located within the northern area of the Welborne site, within the Chesterfield Neighbourhood north of Knowle Road. The site is located to the north-west of the Village Centre, to the north of the housing development currently under construction by Thakeham, and to the east of the housing development being delivered by Pye Homes.
2.2The site is currently an open grassed area and will soon be fronting on to residential streets to the south and east with Dashwood Park located to the north of the site.
3.0Description of Proposal 3.1 This application relates to the proposed development of a new two-form entry primary school with an SEN (Special Educational Needs) resource provision for an additional 10 pupils (430 pupils in total).
3.2The proposed school would be two storey in height finished with a tiled pitched roof and traditional brickwork cladding. The building includes classrooms, a hall, a kitchen and other indoor spaces such as staff rooms. There are playgrounds externally as well as a staff parking area and playing fields.
4.0Policies 4.1 The following policies apply to this application Adopted Fareham Local Plan Part 3 – Welborne WEL1 Sustainable Development WEL2 High Level Development Principles WEL3 Allocation of Land WEL4 Comprehensive Approach WEL6 General Design Principles WEL7 Strategic Design Codes WEL15 Primary and Pre-School Provision WEL27 Encouraging Sustainable Choices WEL28 Walking and Cycling WEL32 Strategic Green Corridors and Connections WEL33 Structural Landscaping WEL34 Detailed Landscaping WEL36 Energy WEL41 Phasing and Delivery
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.