P/26/0250/VC - Land off Tanners Lane Tanners Lane Newlands Farm Fareham PO14 1BL
DecidedPlanning1 paper
AI summaryFareham Planning Committee grants permission to extend Phase 1 of the Tanners Lane battery storage facility to November 2061, with an amended landscaping scheme.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedVariation of conditions 2, 3 and 8 approved, subject to conditions
MoneyNot stated
What happens nextDelegated to Head of PlanningTo amend, add or delete the proposed conditions as needed
Who it affectsStubbington ward countryside siteBattery storage facility on land off Tanners Lane
What was decided
The committee granted planning permission for variation of conditions 2, 3 and 8 of P/20/1563/VC, extending the use of Phase 1 of the battery energy storage facility to 26 November 2061 and approving an amended landscaping scheme. Report 9.0, P50
The committee delegated authority to the Head of Planning to make any necessary modification, deletion or addition to the proposed conditions. Report P57, P58
Why
Officers considered the site to be previously developed land providing renewable energy infrastructure that supports the UK's net zero target and grid resilience, and that an amended landscaping scheme mitigates the impact on the strategic gap and landscape character. Report 8.3, 8.10, P45, 8.13, P48
No objections were received from consultees or the public, and Environmental Health raised no adverse comments on noise or pollution. Report 6.0, 7.0, P30
What happens next
The development will be subject to five conditions covering time limit, approved plans, contamination, external lighting, and implementation of the amended soft landscaping scheme within the first planting season. Report 9.0, P50, P51, P52, P53, P54, P55
Any replacement planting required after five years must be carried out in the next available planting season, in line with the approved landscape management plan from P/20/1563/DP/A approved on 16 March 2026. Report P55
Options considered
Chosen: Grant planning permission subject to conditions and delegate to Head of Planning. Officers concluded the proposal met policy on countryside development, renewable energy and landscape impact, with mitigation secured by an amended landscaping scheme. Report 9.0, 8.10, 8.13, P48
Implications
Climate: Extending the battery storage facility supports renewable energy generation and the UK's net zero by 2050 target. Report 8.7, P40, 8.10
Environment and climate: An amended landscaping scheme, including native hedgerow, tree planting and meadow grassland, must be implemented to mitigate impact on the strategic gap and landscape character. Report 8.13, P55
Legal: Use must cease and the site restored to its former condition on or before 26 November 2061. Report P50
Risk: If unexpected contamination is found during works, development must stop until a risk assessment and remediation scheme are approved in writing by the Local Planning Authority. Report P53
Who and where
Opium Power Ltd (applicant), represented by Enzygo Ltd Report P2
Residents and businesses near the site in Stubbington ward Report P2, 8.9
Users of footpath number 68 along Tanners Lane Report 2.2
Operator of the adjacent Newlands solar farm (P/13/0528/FP) Report 2.2
HMS Collingwood, adjacent to the north of the site Report 2.2
Timeline
26 November 2019: Planning permission P/19/1019/FP granted for Phase 1 battery energy storage facility for 25 years. Report P26
26 January 2021: Planning permissions P/20/1562/FP (Phase 2) and P/20/1563/VC (variation) granted. Report P23, P25, 3.2
16 March 2026: Landscape management and maintenance plan approved under P/20/1563/DP/A. Report P55
20 May 2026: Planning Committee resolves to grant P/26/0250/VC extending Phase 1 to November 2061. Report P1
26 November 2061: Expiry date for the extended use of Phase 1, by which the site must be decommissioned and restored. Report 3.4, P50
Plain English for the jargon
Variation of Condition (VC): A planning application to change the wording or requirements of conditions attached to an existing planning permission.
Battery Energy Storage System (BESS): A facility that stores electricity from the grid or generators such as solar farms and releases it when demand is high or supply is low.
Strategic Gap: An area of countryside between settlements, in this case the Fareham/Stubbington Strategic Gap, protected from coalescence of built form.
Net Zero: The UK government target to balance greenhouse gas emissions produced with those removed from the atmosphere by 2050.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6(7)
Resolved
RESOLVED that: - (i) GRANT planning permission, subject to: - (a) the Conditions in the report; THEN (ii) Authority DELEGATED to the Head of Planning to: - (a) Make any necessary modification, deletion or addition to the proposed conditions.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
P/26/0250/VC STUBBINGTON WARD SSDC OPIUM POWER LTD AGENT: ENZYGO LTD
VARIATION OF CONDITION 2, 3 AND 8 OF P/20/1563/VC (BATTERY ENERGY STORAGE FACILITY FOR A TEMPORARY PERIOD OF 25 YEARS) TO EXTEND USE OF SITE AND RETENTION OF DEVELOPMENT UNTIL NOVEMEBER 2061 (PHASE 1) & AMEND LANDSCAPING SCHEME
LAND OFF TANNERS LANE, TANNERS LANE, FAREHAM, PO14 1BL
Report By Susannah Emery – direct dial 01329 824526
1.0Introduction 1.1 This application has been called on to the Planning Committee agenda by Councillor Needham. The reason given by Councillor Needham was that temporary planning permission at this site was granted for a limited period of 25 years. Councillor Needham considers that if the land is not to be reverted to agricultural land at the end of this period then the future use of this land should be considered by the Planning Committee.
2.0Site Description 2.1 The site lies within the countryside and the Fareham/Stubbington Strategic Gap to the south of Tanners Lane.
2.2The site abuts the Newlands solar farm (planning permission reference P/13/0528/FP) to the south. To the north of the site and Tanners Lane is a row of mature trees which provide screening along the southern boundary of HMS Collingwood. Vegetation and trees continue along Tanners Lane to the east of the application site. Footpath number 68 runs along Tanners Lane which is a public right of way. The application site is relatively flat.
2.3This application relates to Phase 1 of the existing battery storage facility development which comprises the area in the eastern half of the wider site.
2.4The battery energy storage site comprises battery containers, inverter stations, switchgear, and a substation. An acoustic fence extends along the northern boundary and there is sufficient space around the perimeter of the development for landscape planting.
3.0Description of Proposal 3.1 Planning permission (reference P/19/1019/FP) was previously granted in November 2019 for the battery energy storage facility (labelled by the developer as Phase 1). The proposal involved the construction and operation of a 40 MW battery energy storage facility for a temporary period of 25 years expiring on 26 November 2044.
3.2Planning permission (reference P/20/1562/FP) was subsequently granted to extend and enlarge the battery energy storage facility (Phase 2) on land immediately to the west of the permitted development (Phase 1). Based on the revised operational requirements of both Phase 1 and Phase 2 of the development, an application (reference P/20/1563/VC) was submitted and subsequently approved to amend the site layout and landscape plans for Phase 1. The two planning permissions for Phase 1 & 2 were implemented simultaneously.
3.3This application seeks to vary condition 2 of P/20/1563/VC for Phase 1 which states;
The development hereby permitted is granted for a limited period only expiring on 26 November 2044. On or before this date, the use shall cease and any development carried out in pursuance of this permission shall be demolished, materials removed from the site, and the land restored to its former condition. REASON: To retain planning control over the development hereby permitted and to enable the circumstances leading to the grant of permission to be reviewed.
3.4Permission is sought to retain Phase 1 of the battery storage facility for an additional 17 years from 26 November 2044 until 26 November 2061. There is a similar application under consideration and included on this agenda for Phase 2 (reference P/26/0252/VC) to extend the lifetime of the site as a whole.
3.5This application also seeks to vary conditions 3 (Approved Plans) and 8 of P/20/1563/VC (Landscaping Scheme) as an alternative landscaping scheme is proposed.
4.0Policies 4.1 The following policies apply to this application
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.