Resolved
To note the progress of actions identified within the Corporate Risk Register.
Audit Committee noted this item on Tuesday 23 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the progress of actions identified within the Corporate Risk Register.
To update members of the Audit Committee on the current level of assurance that can be provided against each corporate risk.
That Members:
note the progress of actions identified within the Corporate Risk Register.
The current Risk Management Strategy & Framework was last considered and approved by the Cabinet in October 2017.
The purpose of the Strategy and Framework is to define how risks are managed by the Council. It provides guidance on the processes, procedures, roles and responsibilities for risk, and it sets out the context on how risks are to be managed. It defines the key role for the Audit Committee as providing independent assurance to the Council with regard to the effectiveness of the risk management framework and the associated control environment. This includes the monitoring of the framework and ensuring the implementation of all audit actions.
The Corporate Risk Register is a key enabler of the Strategy and Framework, and provides assurance on the key risks identified as corporate risks.
Existing risks identified within both the Council’s corporate and operational service risk registers are subject to quarterly review by senior management and on an ongoing basis through the work of Internal Audit. 3. Corporate Risk Register
This approach has meant that some of the risks included within the corporate risk register have been set at a relatively high score with the expectation that as mitigation measures are properly recorded or actions taken, then these risks should start to improve over the coming months. This is not to say that all risks will return to ‘green’, as mitigation measures can only go so far, and some risks may always be inherently ‘red’ or ‘amber’ as the score reflects the potential impact on the Council and the likelihood of that event occurring.
The Corporate Risk Register and supporting comments as at the end of June 2019 are appended to this report, and this includes a summary of all control gaps currently identified on the Council’s Corporate Risk Register.
4. Resource Implications
To be delivered within existing budgets.
Appendix 1 - Corporate Risk Register Monitoring – Quarter 1, June 2019
Appendix 2 - Risk Management Scoring Matrix Appendix 1 - Corporate Risk Register Monitoring – Quarter 1, June 2019
1 FAILURE TO PREVENT BUDGET OVERHEATING ONCE THE BUDGET HAS BEEN SET
Owner: Mike Hill
Current Risk and Direction of Travel: GREEN – NO CHANGE
Definition:
Shorter term implications of overspending budgets or not collecting as much income as forecasted. This can cause adverse impact on Council balances.
Key Risk Driver: Financial Impact
Raw Risk Value: Serious - £50k - £500k
Corporate Risk Register Outstanding Controls:
Actions completed during quarter 1:
A minor deterioration in the current risk level has been recognised, however this still remains within the ‘Green’ level and the assessed risk remains low. This deterioration reflects the increased risks inherent in the budget arising from increased service demands and the increased efficiency programme as approved by Council in March 2019. The total efficiency programme is £2.6m to be delivered between 2019/20 to 2022/23, with £1.1m planned for 2019/20.
Actions outstanding: Regular quarterly budget monitoring reports will be presented to Cabinet to highlight at the earliest opportunity any potential overspends which need to be addressed, ensuring that timely and effective management action can be taken. Quarter 1 budget monitoring is underway and will be reported to Cabinet in August.
The Council’s budget monitoring processes are robust and whilst the budget reduction programme adds an increased risk to achievement of the annual budget this is not considered to be significant. 2 FAILURE TO MAINTAIN FINANCIAL INTEGRITY
Owner: Mike Hill
Current Risk and Direction of Travel: RED – NO CHANGE
Definition:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Management ScorecardReport | 155 KB | DownloadRead as text |
Follow Audit Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 20 Oct 2026 | BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... | Noted | Open |
| 20 Oct 2026 | Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... | Noted | Open |
| 20 Oct 2026 | Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... | Noted | Open |
| 20 Oct 2026 | Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.