Gedling Borough Council
Audit Committee, Tuesday 24 February 2026 at 5.30pm

External Audit Combined Audit Strategy & Completion Report 2024/2025

Noted Finance 2 papers

AI summaryAudit Committee notes the 2024/25 external audit findings, including a disclaimer of opinion on the accounts, and refers the report to Full Council for information.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAudit Strategy and Completion Report 2024/25 noted
MoneyNot stated
What happens nextReferred to Full CouncilFor information
Who it affectsCouncil audit assuranceAffects 2024/25 financial statements sign-off

What was decided

The Committee noted the Audit Strategy and Completion Report for 2024/25.

The Committee referred the report to Full Council for information.

The auditor, Forvis Mazars, was unable to obtain sufficient evidence to form an opinion on the 2024/25 financial statements, issuing a disclaimer of opinion. Report P36, P39, P53

Why

The 2026 backstop date of 27 February 2026, set by the Accounts and Audit (Amendment) Regulations 2024, did not allow enough time to complete the procedures needed to rebuild assurance. Report P37, P39

Unresolved IT control weaknesses linked to a previously identified fraud affecting the financial ledger needed to be addressed before an opinion could be reached. Report P39

Prior year disclaimers were issued for 2022 and 2023 on 13 December 2024, and for 2024 on 25 February 2025, meaning assurance had to be rebuilt under the Local Audit Reset and Recovery Implementation Guidance 06 (LARRIG 06). Report P38, P39

What happens next

The report is to be referred to Full Council for information.

The audit cannot be formally concluded or an audit certificate issued until the National Audit Office confirms completion of the Whole of Government Accounts group audit. Report P51

The draft Auditor's Annual Report was issued on 11 November 2025, ahead of the 30 November 2025 deadline set by the 2024 Code of Audit Practice. Report P57

Implications

  • Financial: A disclaimer of opinion means no audit assurance is provided on the 2024/25 financial statements, the fourth consecutive year without an opinion for the Council. Report P36, P38, P39
  • Legal: The Council must publish its Accountability Statements, including the financial statements and auditor's opinion, by the 27 February 2026 backstop date under the 2024 Amendment Regulations. Report P37
  • Risk: Unresolved IT control weaknesses over the financial ledger, linked to a known fraud, remain an open matter requiring further audit work. Report P39
  • Other: The auditor reported nothing by exception on the Council's arrangements for securing economy, efficiency and effectiveness in its use of resources. Report P45

Who and where

  • Members of Gedling Borough Council Report P50
  • The Chief Finance and Section 151 Officer (Tina Adams) Report P33, P40
  • Council taxpayers and residents, who rely on audited accounts for assurance Report P34, P50

Timeline

  • 30 September 2024: Accounts and Audit (Amendment) Regulations 2024 came into force. Report P37
  • 13 December 2024: Auditor issued disclaimers of opinion for years ended 31 March 2022 and 2023. Report P38
  • 25 February 2025: Auditor issued a disclaimer of opinion for year ended 31 March 2024. Report P39
  • 11 November 2025: Draft Auditor's Annual Report issued, ahead of the 30 November 2025 deadline. Report P57
  • 24 February 2026: Audit Committee meeting at which the report was noted.
  • 27 February 2026: Statutory backstop date for publishing 2024/25 Accountability Statements. Report P37

Plain English for the jargon

  • Disclaimer of opinion: Auditor's statement that no opinion can be given because sufficient evidence could not be obtained.
  • Backstop date: Statutory deadline under the 2024 Amendment Regulations by which audited accounts must be published.
  • LARRIG 06: Local Audit Reset and Recovery Implementation Guidance 06, issued by the National Audit Office in June 2025 to guide auditors rebuilding assurance after backstop disclaimers.
  • Section 151 Officer: The council's statutory chief finance officer, responsible for financial administration.
  • Accountability Statements: The financial statements and the auditor's opinion, which must be published together.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item30

Resolved

To note the Audit Strategy and Completion Report for 2024/25 and refer to Full Council for information.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Audit Committee

Audit Strategy and Completion Report Gedling Borough Council – Year ended 31 March 2025

February 2026 Audit Committee Gedling Borough Council Civic Centre Forvis Mazars Arnot Hill Park 2 Chamberlain Square Arnold Birmingham Nottingham B3 3AX NG5 6LU

24th February 2026

Dear Committee Members,

Audit Strategy and Completion Report – Year ended 31 March 2025 We are pleased to present our Audit Strategy and Completion Report for Gedling Borough Council for the year We appreciate the courtesy and co-operation extended to us by Gedling Borough Council throughout our audit. ended 31 March 2025. The purpose of this document is to summarise our audit and to explain how the We would be happy to discuss the contents of this report, or any other matters regarding our audit, with you in statutory backstop arrangements introduced by the Accounts and Audit (Amendment) Regulations 2024, have more detail. affected the completion of our work and the reporting consequences. We consider two-way communication with We will continue to work closely with you and management to take the necessary steps to rebuild assurance you to be key to a successful audit and particularly important in the context of the backstop arrangements as it over future accounting periods. facilitates: • reaching a mutual understanding of the scope of the audit and the responsibilities of each of us; Yours faithfully • sharing information to assist each of us to fulfil our respective responsibilities; and • providing you with constructive observations arising from the audit process even though this has been Mark Surridge curtailed by the backstopped arrangements. Forvis Mazars LLP We would usually report the results of our planning work, including the significant risks identified and our planned procedures, in our Audit Strategy Memorandum. The results of our audit, including significant matters identified would usually be reported to you in our Audit Completion Report. As a result of the backstop arrangements, we have determined that the most appropriate way to communicate each of the matters required under auditing standards, in this single Audit Strategy and Completion Report. As it is a fundamental requirement that an auditor is, and is seen to be, independent of audited bodies, section 8 of this document summarises our considerations and conclusions on our independence as auditors.

Forvis Mazars LLP – www.forvismazars.com/uk Forvis Mazars LLP is the UK firm of Forvis Mazars Global, a leading global professional services network. Forvis Mazars LLP is a limited liability partnership registered in England and Wales with registered number OC308299 and with its registered office at 30 Old Bailey, London, EC4M 7AU. Registered to carry on audit work in the UK by the Institute of Chartered Accountants in England and Wales. Details about our audit registration can be viewed at www.auditregister.org.uk under reference number C001139861. VAT number: GB 839 8356 73 Contents

01 Our audit and the implications of the statutory backstop 02 Your audit team 03 Our audit approach 04 Materiality 05 Significant findings 06 Value for Money arrangements 07 Audit fees and other services 08 Confirmation of our independence

Appendices A Draft management representation letter B Draft audit report C Key communication points

Our reports are prepared in the context of the ‘Statement of Responsibilities of auditors and audited bodies’ and the ‘Appointing Person Terms of Appointment’ issued by Public Sector Audit Appointments Limited. Reports and letters prepared by appointed auditors and addressed to the Council are prepared for the sole use of the Council and we take no responsibility to any member or officer in their individual capacity or to any third party.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4a. Combined Audit Strategy and Completion Report 24-25: GedlingReport 615 KB DownloadRead as text
PDF
External Audit Combined Audit Strategy & Completion Report 2024/2025Report 155 KB Download

At this meeting

Whole meeting

Who was there

7 of 17 attended
RM
Councillor Ron McCrossenChair, apologies
SB
Councillor Sandra BarnesChair, present
SB
Councillor Stuart BestwickCommittee Member, present
HG
Councillor Helen GreensmithCommittee Member, present
PH
Councillor Paul HughesCommittee Member, present
AH
Councillor Alison HuntCommittee Member, present
RS
Councillor Ruth StrongCommittee Member, present
JC
Jonathan CaustonCo-Optee, present
TA
Tina AdamsOfficer, in attendance
CG
Cayte GoodallOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
MA
Max ArmstrongPublic, in attendance

All 17 on the meeting page

On this subject at Gedling

Search all
  1. External Audit Combined Audit Strategy & Completion Report 2024/2025This decision
  2. Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026Noted
  3. External Audit Progress Report 2025Noted
  4. External Audit Fees for the 2025/26 Statement of AccountsNoted
  5. External Auditors (Mazars) - Draft Annual ReportNoted
  6. External Audit Progress Report 2024/25Noted

More from Gedling Audit Committee

All decisions
MeetingDecisionOutcome
20 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
20 Oct 2026 BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... Noted Open
20 Oct 2026 Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... Noted Open
20 Oct 2026 Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... Noted Open