Gedling Borough Council
Audit Committee, Tuesday 24 February 2026 at 5.30pm

Internal Audit Progress Report 2025/2026

Noted Finance 2 papers

AI summaryGedling Audit Committee noted BDO's 2025/26 internal audit progress, including a 'Moderate' assurance rating for management of commercial property assets totalling £1.066m in rent.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAudit plan delivery noted, three reports received
Money£1.066m total annual rentFrom 85 commercial estates properties in spreadsheet
What happens nextFurther audit reports to comeResidential assets, governance, FOI audits in fieldwork
Who it affectsCouncil's commercial property portfolioAsset management, rent reviews and invoicing

What was decided

The committee noted the progress of delivery against the 2025/26 Internal Audit Plan, including the Main Financial Systems, Asset Management, Commercial Assets, and Cyber Security reports.

BDO reported good progress, with all audit reviews fully scoped and either finalised or in the fieldwork phase. Report P4

The Asset Management, Commercial Assets review received a 'Moderate' opinion for both design and effectiveness of controls. Report P18, P32, P33, P34

Why

The report is intended to inform the Audit Committee of progress against the 2025/26 internal audit plan and summarise work done, systems reviewed and recommendations raised. Report P4

BDO's work complies with Global Internal Audit Standards in the UK Public Sector and is designed to provide assurance on risk management and internal control processes. Report P4

The commercial assets review was triggered by risks including loss or damage to infrastructure assets (CR007) and the need to assess longer-term strategy for operational, commercial and investment assets. Report P20

What happens next

Draft Asset Management Strategy and Action Plan to be enhanced with governance arrangements, SMART metrics, and clearer asset management approach, with target date 27 February 2026. Report P27, P29

Property Team to log actual rent review dates on the master tracker and conduct root cause analysis on delays, with target date 31 March 2026. Report P30, P31

Asset Management - Residential Assets, Corporate Governance, and Complaints and Freedom of Information Requests audits are in fieldwork and will be reported to future Audit Committee meetings. Report P4, P11, P12, P13

The money

  • £1.066m Current total annual rent from 85 estates properties recorded in the Council's commercial assets spreadsheet Report P22
  • £179,708 Total annual rent across the sample of 10 investment property leases reviewed by BDO Report P22

Options considered

  • Chosen: Note the audit progress report as presented. The committee's decision was to note the report, including the three audit outputs presented

Implications

  • Risk: Non-compliance with some rent review procedures may put system objectives at risk, though financial impact was generally low. Report P33, P34
  • Financial: Local Government Reorganisation is imminent, so a streamlined asset management approach is being adopted rather than a standalone Asset Management Policy. Report P20, P27, P29
  • Legal: BDO's report is subject to Freedom of Information Act 2000 disclosure rules and BDO must be consulted before any release. Report P69
  • Staffing: A historic backlog of rent reviews has been addressed through additional procedures, structure and resource in the Property Team. Report P31
  • Other: Two Medium-priority recommendations raised: embed asset management approach into AMS/AMAP, and ensure rent reviews are timely and per lease terms. Report P19, P27, P29, P30, P31

Who and where

  • Gedling Borough Council's Property Services Team Report P22, P24, P27, P31
  • Tenants of Council commercial and investment properties Report P22, P26, P34
  • Council tenants and residents using community centres, parks and open spaces Report P20
  • Senior Leadership Team and Smarter Working Board (governance oversight) Report P20, P27, P29

Timeline

  • September 2025: Risk Management and People Services audits reported Report P8, P14
  • December 2025: Main Financial Systems (Fraud) audit completed (confidential) Report P9
  • 27 February 2026: Target date to incorporate asset management approach into AMS and AMAP Report P27, P29
  • March 2026: Asset Management, Commercial Assets, Residential Assets (draft), and Cyber Security (confidential) audits reported or in progress Report P10, P11, P15
  • 31 March 2026: Target date to log actual rent review dates and conduct root cause analysis on delays Report P30, P31
  • June 2026: Freedom of Information Requests and Complaints, and Corporate Governance audits scheduled Report P12, P13

Plain English for the jargon

  • AMS: Asset Management Strategy, a strategic planning document setting direction for property assets
  • AMAP: Asset Management Action Plan, the delivery plan for property assets with timescales, costs and responsibilities
  • AMP: Asset Management Policy, the rules by which assets are deployed and managed
  • BDO: The Council's appointed Internal Audit Partner
  • LGR: Local Government Reorganisation, restructuring of councils into new unitary authorities
  • RICS: Royal Institution of Chartered Surveyors
  • RAG: Red, Amber, Green status indicators used in the commercial property master tracker
  • RPI: Retail Price Index, used to calculate rent increases in some lease agreements
  • SLT: Senior Leadership Team
  • SMART: Specific, Measurable, Achievable, Realistic, Time-bound
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item35

Resolved

To note the progress of the delivery against the 2025/26 Internal Audit Plan, including the Main Financial Systems Report, the Asset Management – Commercial Assets Report and the Cyber Security Report.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Audit Committee

OFFICIAL

Gedling Borough Council Internal Audit Progress Report February 2026 1 INTERNAL AUDIT PROGRESS REPORT

Summary of 2025/26 work

Internal Audit This report is intended to inform the Audit Committee of progress made against the 2025/26 internal audit plan. It summarises the work we have done, together with our assessment of the systems reviewed and the recommendations we have raised. Our work complies with Global Internal Audit Standards in the UK Public Sector. As part of our audit approach, we have agreed terms of reference for each piece of work with the risk owner, identifying the headline and sub-risks, which have been covered as part of the assignment. This approach is designed to enable us to give assurance on the risk management and internal control processes in place to mitigate the risks identified. Internal audit methodology Our methodology is based on four assurance levels in respect of our overall conclusion as to the design and operational effectiveness of controls within the system reviewed. The assurance levels are set out in Appendix 1 of this report and are based on us giving either ‘substantial’, ‘moderate’, ‘limited’ or ‘no’ opinion. The four assurance levels are designed to ensure that the opinion given does not gravitate to a ‘satisfactory’ or middle band grading. Under any system we are required to make a judgement when making our overall assessment. Internal audit plan 2025/26 We are making good progress in the delivery of the audit plan with all of our audit reviews fully scoped and either finalised or in the fieldwork phase. We are pleased to present the following reports to this Audit Committee meeting:  Main Financial Systems – this is a confidential report  Cyber Security – this is a confidential report  Asset Management – Commercial Assets. Fieldwork is in progress in respect of the following audits:  Asset Management - Residential Assets (draft report phase)  Corporate Governance  Complaints and Freedom of Information Requests. We anticipate presenting these reports at future Audit Committee meetings.

1 2 INTERNAL AUDIT PROGRESS REPORT

Review of 2025/26 work

AUDIT AUDIT PLANNING FIELDWORK REPORTING DESIGN EFFECTIVENESS COMMITTEE

Risk Management September 2025 S M

Main Financial December 2025 Confidential Systems (Fraud)

Asset Management – Commercial March 2026 M M Assets

Asset Management – Residential March 2026 Assets Draft

Freedom of Information June 2026 Requests and Complaints

Corporate June 2026 Governance

People Services September 2025 L M

Cyber Security March 2026 Confidential

2 3 INTERNAL AUDIT PROGRESS REPORT

Asset Management – Commercial Assets

CRR Reference: CR002, CR007 and CR013 Effectiveness Design Opinion M Moderate M Moderate Opinion

Recommendations 0 2 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
9a. BDO: GBC: Internal Audit Progress Report: February 2026Report 657 KB DownloadRead as text
PDF
Internal Audit Progress Report 2025/2026Report 436 KB Download

At this meeting

Whole meeting

Who was there

7 of 17 attended
RM
Councillor Ron McCrossenChair, apologies
SB
Councillor Sandra BarnesChair, present
SB
Councillor Stuart BestwickCommittee Member, present
HG
Councillor Helen GreensmithCommittee Member, present
PH
Councillor Paul HughesCommittee Member, present
AH
Councillor Alison HuntCommittee Member, present
RS
Councillor Ruth StrongCommittee Member, present
JC
Jonathan CaustonCo-Optee, present
TA
Tina AdamsOfficer, in attendance
CG
Cayte GoodallOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
MA
Max ArmstrongPublic, in attendance

All 17 on the meeting page

On this subject at Gedling

Search all
  1. Internal Audit Progress Report 2025/2026This decision
  2. BDO Internal Audit Progress ReportNoted
  3. Internal Audit Progress ReportNoted
  4. Internal Audit Annual ReportNoted
  5. Internal Audit Annual Plan - 2026/27Approved
  6. Internal Auditors (BDO) - Progress ReportNoted

More from Gedling Audit Committee

All decisions
MeetingDecisionOutcome
20 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
20 Oct 2026 BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... Noted Open
20 Oct 2026 Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... Noted Open
20 Oct 2026 Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... Noted Open
20 Oct 2026 Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies