Audit Committee, Tuesday 24 February 2026 at 5.30pm

Internal Audit Annual Plan - 2026/27

Approved Finance 4 papers

AI summaryGedling Borough Council's Audit Committee has approved the 2026/27 Internal Audit Plan totalling 150 days, covering financial systems, housing, waste, local government reorganisation and digital projects.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedInternal Audit Plan 2026/27, Charter, Strategy and QAIP
Money150 days totalOf internal audit resource for 2026/27
What happens nextPlan delivered in 2026/27Reviews scheduled across quarters 1 to 4
Who it affectsAll council services auditedBDO delivers the internal audit function

What was decided

The committee approved the Internal Audit Plan for 2026/27, with 150 audit days covering core assurance, future focused reviews, flexible resource and contract management. Report P7, P101

The committee approved the Internal Audit Charter, which defines the function's purpose, authority, independence and reporting lines. Report P142, P145

The committee approved the Internal Audit Strategy and the Quality Assurance and Improvement Programme, setting out how conformance with professional standards is maintained and reviewed. Report P164

Why

The plan is based on the council's own corporate risk register, with input from the Senior Leadership Team and Assistant Directors, and follows a three year audit cycle. Report P6, P7, P22

High risk areas such as capacity and workforce planning are being addressed within individual audit scopes rather than as a separate review, and cyber security was reviewed in 2025/26 so is not repeated. Report P8, P105, P106

Local government reorganisation is identified as the most significant structural change facing the council, with a decision on the future structure of Nottinghamshire authorities expected in July 2026. Report P78

What happens next

BDO will deliver the plan during 2026/27, keeping it under continuous review and seeking approval from the Deputy Chief Executive and Chief Finance Officer for any scope revisions. Report P7, P9

The plan and Corporate Risk Register will be reviewed periodically during 2026/27, with any changes reported to the Audit Committee. Report P22

An external quality assessment of internal audit conformance with the Global Internal Audit Standards in the UK Public Sector will be carried out at least once every five years. Report P160, P164

The money

  • 150 Total internal audit days for 2026/27 Report P101
  • 65 Days for core assurance reviews Report P75, P96
  • 60 Days for future focused assurance reviews Report P84, P98
  • 20 Days for contract management activities Report P94, P100
  • 5 Days held as flexible contingency resource Report P88, P99
  • over £1m Unspent Section 106 and CIL funds held by the council Report P72

Options considered

  • Chosen: Approve the Internal Audit Plan 2026/27 and Internal Audit Charter. Plan meets risk based requirements and follows three year cycle Report P7
  • Chosen: Approve the Internal Audit Strategy and QAIP. Required for conformance with professional standards Report P164
  • Rejected: Include a separate review of Capacity and Workforce Planning. Risk is covered within scope of individual audit assignments Report P8, P106
  • Rejected: Include a review of Cyber Security in 2026/27. Cyber security was reviewed in 2025/26, no further review needed Report P8, P105
  • Rejected: Include a review of the Planning and Infrastructure Act in 2026/27. Scheduled for 2027/28 due to legislative change in 2026 Report P8, P107

Implications

  • Risk: Local government reorganisation is flagged as the most significant structural change in decades, with audit days held flexibly pending clarity on the new authority. Report P78
  • Risk: Cyber security, though not in the 2026/27 plan, is acknowledged as one of the highest risks for public sector organisations. Report P105
  • Legal: The plan must comply with the Global Internal Audit Standards in the UK Public Sector, including the IIA standards and the IASAB application note. Report P21, P143
  • Legal: Internal audit is also required to comply with the CIPFA Code of Practice for the Governance of Internal Audit in UK Local Government. Report P143
  • Financial: Simpler Recycling requirements under the Environment Act 2021 create new compliance obligations from 31 March 2026, with transitional food waste collections later in 2026 and plastic film from 31 March 2027. Report P70, P71
  • Staffing: BDO confirms sufficient human, financial and technological resources to deliver the plan, with a core team of qualified staff supported by wider specialists. Report P11, P12
  • Other: Internal audit work must follow the Nolan Principles of public life and the principles of ethics and professionalism set out in the standards. Report P162

Who and where

  • Gedling Borough Council as a whole, including all activities, assets and personnel within the scope of internal audit Report P165
  • The Audit Committee, which holds oversight of the internal audit function Report P146, P147
  • BDO, the outsourced internal audit provider and de facto Head of Internal Audit Report P11, P143
  • Senior Leadership Team and Assistant Directors, who provided input to the plan Report P7, P22
  • Future unitary authority in Nottinghamshire, depending on the LGR decision expected in July 2026 Report P78

Timeline

  • 2026/27: Plan period: delivery of 150 audit days across core assurance, future focused reviews, flexible resource and contract management Report P7, P101
  • Q1 2026/27: Digital Strategy review (20 days) and contract management planning and liaison work Report P80, P91
  • Q2 2026/27: Housing and Homelessness follow up (15 days), Section 106 and CIL review (15 days), Leisure Transformation review (20 days) Report P67, P72, P79
  • Q3 2026/27: Main Financial Systems review (15 days) and Waste and Recycling review (20 days) Report P66, P70
  • Q3 or Q4 2026/27: Local Government Reorganisation Preparedness support (20 days, flexible scope) Report P78
  • Q1 to Q4 2026/27: Recommendations follow up (7 days) and Audit Committee attendance and liaison (5 days) Report P92, P93
  • 31 March 2026: Simpler Recycling: local authorities required to collect core recyclable waste streams for all households in England Report P70
  • July 2026: Decision expected on the future structure of local government in Nottinghamshire Report P78
  • 2027/28: Review of the Planning and Infrastructure Act scheduled Report P8, P55, P107
  • At least once every five years: External quality assessment of internal audit against the Global Internal Audit Standards Report P160, P164

Plain English for the jargon

  • BDO: The external firm appointed to deliver the council's internal audit function, acting as the Head of Internal Audit.
  • CRR: Corporate Risk Register, listing the council's strategic risks and their likelihood, consequence and net score.
  • GIAS: Global Internal Audit Standards issued by the Institute of Internal Auditors, applied in the UK Public Sector alongside the IASAB application note.
  • CIPFA: Chartered Institute of Public Finance and Accountancy, whose Code of Practice sets additional standards for local government internal audit.
  • HoIA: Head of Internal Audit, the role fulfilled by the BDO-assigned partner responsible for the internal audit function.
  • QAIP: Quality Assurance and Improvement Programme, covering internal and external assessments of internal audit conformance and performance.
  • S106 and CIL: Section 106 planning obligations and Community Infrastructure Levy, developer contributions used to fund local infrastructure.
  • LGR: Local Government Reorganisation, structural change to local authority arrangements; a decision on Nottinghamshire's future structure is expected in July 2026.
  • Simpler Recycling: New requirements under the Environment Act 2021 requiring collection of core recyclable waste streams, with food waste and plastic film collection requirements in 2026 and 2027.
  • s151 Officer: The council's Chief Finance Officer, to whom the Head of Internal Audit reports administratively.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item32

Resolved

RESOLVED to: 1) Approve the Internal Audit Plan for 2026/27 and the Internal Audit Charter. 2) Approve the Internal Audit Strategy and the Quality Assurance and Improvement Programme.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Audit Committee

INTERNAL AUDIT PLAN GEDLING BOROUGH COUNCIL

2026/27 INTERNAL AUDIT PLAN |

CONTENTS

INTERNAL AUDIT APPROACH .................................................... 1 OUR APPROACH TO PLANNING ................................................. 3 OUR NEXT GEN FRAMEWORK ................................................... 5 MAPPING YOUR STRATEGIC RISKS ............................................. 6 MAPPING YOUR CRR TO THE STRATEGIC PLAN .............................. 7 INTERNAL AUDIT OPERATIONAL PLAN 2026/27 ............................. 10 AREAS CONSIDERED BUT NOT INCLUDED IN 2026/27 ..................... 17 APPENDIX I ....................................................................... 18 APPENDIX II ...................................................................... 20 1 INTERNAL AUDIT PLAN |

INTERNAL AUDIT APPROACH

BACKGROUND Our risk-based approach to internal audit uses Gedling Borough Council’s (the Council’s) own risk management process and risk register as a starting point for audit planning as this represents the Council’s own assessment of the risks to it achieving its strategic objectives. The extent to which we can rely on management’s own perception of risk largely depends on the maturity and effectiveness of the Council’s own risk management arrangements. In estimating the amount of audit resource required to address the most significant risks, we have also sought to confirm that senior management’s own assessment of risk accurately reflects the Council’s current risk profile.

PLANNED APPROACH TO INTERNAL AUDIT 2026/27 The Internal Audit programme for 2026/27 is set out on pages 10 to 16. We met with the Senior Leadership Team and Assistant Directors to bring together a full plan which will be presented to the Audit Committee (AC) meeting for formal review and approval. We will keep the programme under continuous review during the year and will introduce to the plan any significant areas of risk identified by management during that period. The plan is set within the context of a multi-year approach to internal audit planning, such that all areas of key risks would be looked at over a three-year audit cycle. We have suggested future areas of focus as part of the three-year strategic internal audit plan, set out on pages 7 to 9.

HIGH RISK AREAS NOT INCLUDED The following high-risk areas have not been included in our audit plan for 2026/27:  Cyber Security - Cyber security is one of the highest risks facing public sector organisations due to the nature of threats and the increasing hostile actors targeting public sector organisations. We have considered this as part of our risk-based audit plan, however, as cyber security has been reviewed in 25/26, we do not feel that another review in 26/27 is necessary.  Capacity and Workforce Planning - The Council’s highest risk is capacity and service delivery. This risk is incorporated into the scope of individual audit assignments; therefore, we do not propose a separate review of this topic.  Planning and Infrastructure - Planning is a key risk for all local planning authorities. There is legislative change to planning that comes into force in 2026, so we have scheduled a review of the Planning and Infrastructure Act in 2027/28. Further detail is included on page 17.

INDIVIDUAL AUDITS When we scope each review, we will reconsider our estimate for the number of days needed to achieve the objectives established for the work and to complete it to a satisfactory standard in light of the control environment identified within the Council. Where revisions are required, we will obtain approval from the Deputy Chief Executive and the Chief Finance Officer prior to commencing fieldwork. In determining the timing of our individual audits, we will seek to agree a date which is convenient to the Council, and which ensures availability of key management and staff and takes account of any operational pressures being experienced. 2 INTERNAL AUDIT PLAN |

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
6a. Gedling BC: Annual Plan and Charter: February 2026: V2Report 872 KB DownloadRead as text
PDF
6b. Appendix 1: Internal Audit Strategy: February 2026Appendix 2.4 MB Download
PDF
6c. Appendix 2: QAIP: February 2026Appendix 2.4 MB Download
PDF
Internal Audit Annual Plan: 2026/27Report 250 KB Download

At this meeting

Whole meeting

Who was there

7 of 17 attended
RM
Councillor Ron McCrossenChair, apologies
SB
Councillor Sandra BarnesChair, present
SB
Councillor Stuart BestwickCommittee Member, present
HG
Councillor Helen GreensmithCommittee Member, present
PH
Councillor Paul HughesCommittee Member, present
AH
Councillor Alison HuntCommittee Member, present
RS
Councillor Ruth StrongCommittee Member, present
JC
Jonathan CaustonCo-Optee, present
TA
Tina AdamsOfficer, in attendance
CG
Cayte GoodallOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
MA
Max ArmstrongPublic, in attendance

All 17 on the meeting page

On this subject at Gedling

Search all
  1. Internal Audit Annual Plan - 2026/27This decision
  2. BDO Internal Audit Progress ReportNoted
  3. Internal Audit Progress ReportNoted
  4. Internal Audit Annual ReportNoted
  5. Internal Audit Progress Report 2025/2026Noted
  6. Internal Auditors (BDO) - Progress ReportNoted

More from Gedling Audit Committee

All decisions
MeetingDecisionOutcome
20 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
20 Oct 2026 BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... Noted Open
20 Oct 2026 Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... Noted Open
20 Oct 2026 Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... Noted Open
20 Oct 2026 Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies