CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gedling Borough Council
Audit Committee, Tuesday 23 June 2026 at 5.30pm

Internal Audit Progress Report

Noted Finance 2 papers

AI summaryGedling's Audit Committee noted BDO's completion of the 2025/26 Internal Audit Plan, covering three reports on residential assets, complaints and FOIs, and corporate governance. Control ratings were moderate or substantial, with management actions agreed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThree reports presented to the committee
Money£1.1m planned, £320,000 annual rentCapital spend and rental income from residential properties
What happens nextImplement agreed recommendationsTarget dates between June 2026 and October 2027
Who it affectsCouncil tenants, residents, FOI requestersPlus council staff and decision-makers

What was decided

The committee noted completion of the 2025/26 Internal Audit Plan, with all audit reviews finalised and work on the 2026/27 plan commenced. Report P4

Three reports were received: Asset Management (Residential Assets), Complaints and FOIs, and Corporate Governance. Report P4

The Residential Assets audit was given a Moderate rating for both design and effectiveness; the Complaints and FOIs audit was Substantial design and Moderate effectiveness; Corporate Governance was Substantial design and Moderate effectiveness. Report P18, P34, P62, P31, P57, P73

Why

The report is intended to inform the Audit Committee of progress made against the 2025/26 internal audit plan, summarising work done, assessments of systems reviewed and recommendations raised. Report P4

The work complies with Global Internal Audit Standards in the UK Public Sector, and assurance is based on four levels: substantial, moderate, limited or no opinion. Report P4, P85

What happens next

Management has agreed actions with target dates ranging from 30 June 2026 to 31 October 2027, including a formal procurement exercise for maintenance contractors and adoption of the Netcall customer relationship management system. Report P27, P47, P50, P54, P70, P72

BDO has commenced work on the 2026/27 internal audit plan. Report P4

The money

  • £1.1m Planned capital investment to purchase more temporary accommodation properties over a two-year period Report P20
  • £320,000 per annum Estimated rental income from residential temporary accommodation properties Report P20
  • £450 or 2.5 days' work Council threshold above which FOI requests are not processed Report P36

Options considered

  • Chosen: Asset Management (Residential Assets) recommendations accepted by management. Includes setting monetary threshold for inspection, formal procurement exercise, maintenance priority ratings, and a rent arrears procedure note Report P25, P27, P29
  • Rejected: Netcall system change for FOI request fields rejected. Council judged training and guidance more proportionate than system-based constraints Report P50, P51
  • Chosen: Adopt standard FOI refusal templates and re-perform Section 12 calculations. Templates already exist; errors were due to incorrect use; interim guidance issued Report P52, P53, P54, P55
  • Chosen: Formal evaluation of the Making Meetings Matter structure. SLT and Assistant Directors to lead a review with target date September 2026 Report P70, P71

Implications

  • Financial: Planned £1.1m capital investment in additional temporary accommodation properties, generating an estimated £320,000 per annum in rental income. Report P20
  • Legal: FOI Act 2000 compliance issues identified: incomplete responses, incorrect exemption citations and Section 12 cost calculation errors; corrective guidance and training agreed. Report P50, P52, P54, P55
  • Risk: Reactive maintenance inspections not consistently evidenced before contractor payment, and the certified providers register not kept up to date, affecting safety-critical and specialist works. Report P25, P27
  • Staffing: Resource limitations cited as the reason maintenance inspection gaps exist; Housing and Resettlement Team to develop a written procedure for managing rental arrears. Report P25, P29
  • Other: New Netcall customer relationship management system being implemented, with complaints and FOI workflows expected by June 2027 to embed templates and automated notifications. Report P50, P55, P59
  • Risk: Corporate governance RAID logs show inconsistent recording of action owners, dates and status; the Making Meetings Matter structure has not yet been formally evaluated. Report P70, P75

Who and where

  • Tenants of the council's c29 purchased and 8 leased temporary accommodation properties Report P20
  • Residents making complaints to the council via service areas Report P36, P38
  • Members of the public submitting Freedom of Information requests Report P36, P38
  • Council staff handling complaints, FOI requests and maintenance Report P36, P38, P27
  • Audit Committee members and the Senior Leadership Team Report P4, P64

Timeline

  • 13 February 2025: Cabinet received annual budget report including plans for £1.1m capital investment in temporary accommodation properties Report P20
  • 18 March 2025: Audit Committee approved the Local Code of Corporate Governance for 2025/26 Report P64
  • September 2025: Risk Management audit fieldwork completed Report P8
  • 4 September 2025: Cabinet decided on the Temporary Maintenance Policy Report P20
  • December 2025: Main Financial Systems (Fraud) audit fieldwork completed Report P9
  • February 2026: Asset Management (Commercial Assets) and Cyber Security audits completed Report P10, P15
  • June 2026: Asset Management (Residential), FOIs and Complaints, and Corporate Governance audits finalised and reported to this committee Report P11, P12, P13, P4
  • 30 June 2026: Target date: immediate FOI guidance issued and templates reissued to staff Report P45, P50, P54, P55
  • 31 July 2026: Target date: document completion dates for maintenance works Report P28, P29
  • 31 August 2026: Target date: inspections of reactive maintenance, KPIs, and rent arrears case notes Report P25, P28, P29
  • September 2026: Target date: corporate governance action log communications, formal evaluation, and terms of reference revisions Report P70, P72
  • 30 September 2026: Target date: written procedure note for rental arrears management Report P29
  • 31 October 2026: Target date: maintenance contractor register review and complaints training on audit trail Report P27, P43
  • June 2027: Target date: full implementation of Netcall CRM system with associated training Report P50, P55
  • 30 June 2027: Target date: staff training on standard complaint response templates within the new system Report P47
  • 31 October 2027: Target date: explore automated notifications and KPI monitoring for complaint response times Report P47, P49

Plain English for the jargon

  • FOI: Freedom of Information request, governed by the Freedom of Information Act 2000
  • ICO: Information Commissioner's Office, the UK regulator for data protection and information rights
  • LGSCO: Local Government and Social Care Ombudsman
  • RAID log: Risk, Action, Issue and Decision log used to track governance discussions
  • SLT: Senior Leadership Team, led by the Chief Executive
  • Netcall: Customer relationship management system being implemented by the council
  • CRR: Corporate Risk Report, listing the council's strategic risks
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

To note the progress (completion) of the delivery against the 2025/26 Internal Audit Plan, including executive summaries of the Asset Management – Residential Assets Report, Complaints and FOIs Report, and the Corporate Governance Report.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Audit Committee

OFFICIAL

Gedling Borough Council Internal Audit Progress Report June 2026 1 INTERNAL AUDIT PROGRESS REPORT

Summary of 2025/26 work

Internal Audit This report is intended to inform the Audit Committee of progress made against the 2025/26 internal audit plan. It summarises the work we have done, together with our assessment of the systems reviewed and the recommendations we have raised. Our work complies with Global Internal Audit Standards in the UK Public Sector. As part of our audit approach, we have agreed terms of reference for each piece of work with the risk owner, identifying the headline and sub-risks, which have been covered as part of the assignment. This approach is designed to enable us to give assurance on the risk management and internal control processes in place to mitigate the risks identified. Internal audit methodology Our methodology is based on four assurance levels in respect of our overall conclusion as to the design and operational effectiveness of controls within the system reviewed. The assurance levels are set out in Appendix 1 of this report and are based on us giving either ‘substantial’, ‘moderate’, ‘limited’ or ‘no’ opinion. The four assurance levels are designed to ensure that the opinion given does not gravitate to a ‘satisfactory’ or middle band grading. Under any system we are required to make a judgement when making our overall assessment. Internal audit plan 2025/26 We have now completed our delivery of the audit plan with all audit reviews finalised. We are pleased to present the following reports to this Audit Committee meeting:  Asset Management - Residential Assets  Corporate Governance  Complaints and Freedom of Information Requests. This concludes our delivery of the 2025/26 Internal Audit Plan and we have commenced our work on the 2026/27 work.

1 2 INTERNAL AUDIT PROGRESS REPORT

Review of 2025/26 work

AUDIT AUDIT PLANNING FIELDWORK REPORTING DESIGN EFFECTIVENESS COMMITTEE

Risk Management September 2025 S M

Main Financial December 2025 Confidential Systems (Fraud)

Asset Management – Commercial February 2026 M M Assets

Asset Management – Residential June 2026 M M Assets

Freedom of Information June 2026 S M Requests and Complaints

Corporate June 2026 S M Governance

People Services September 2025 L M

Cyber Security February 2026 Confidential

2 3 INTERNAL AUDIT PROGRESS REPORT

Asset Management – Residential Assets

CRR Reference: CR002, CR007 and CR013 Effectiveness Design Opinion M Moderate M Moderate Opinion

Recommendations 0 2 1

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4a. BDO: Progress Report: June 2026Report 813 KB DownloadRead as text
PDF
Internal Audit Progress ReportReport 182 KB Download

At this meeting

Whole meeting

Who was there

9 of 17 attended
RM
Councillor Ron McCrossenChair, present
RS
Councillor Ruth StrongVice-Chair, present
SB
Councillor Stuart BestwickCommittee Member, apologies, sent representative
DB
Councillor David BrocklebankCommittee Member, present
HG
Councillor Helen GreensmithCommittee Member, present
PH
Councillor Paul HughesCommittee Member, present
JN
Councillor Julie NajukCommittee Member, present
MS
Councillor Martin SmithCommittee Member, present
JC
Jonathan CaustonCo-Optee, present
FW
Francesca WhyleyOfficer, in attendance
TA
Tina AdamsOfficer, in attendance
CG
Cayte GoodallOfficer, in attendance

All 17 on the meeting page

On this subject at Gedling

Search all
  1. Internal Audit Progress ReportThis decision
  2. BDO Internal Audit Progress ReportNoted
  3. Internal Audit Annual ReportNoted
  4. Internal Audit Annual Plan - 2026/27Approved
  5. Internal Audit Progress Report 2025/2026Noted
  6. Internal Auditors (BDO) - Progress ReportNoted

More from Gedling Audit Committee

All decisions
MeetingDecisionOutcome
20 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
20 Oct 2026 BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... Noted Open
20 Oct 2026 Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... Noted Open
20 Oct 2026 Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... Noted Open
20 Oct 2026 Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... Noted Open