To: Gravesham Joint Transportation Board
By: Spencer Palmer, Head of Highway Operations
Date: 21 March 2012
Subject: Highway Works Programme 2011/12
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2011/12
1. Introduction
This report is an update on that made to previous meetings of the board and summarises the identified schemes that have been programmed for construction by Kent County Council in 2011/12
Highway Maintenance Schemes
Carriageway Schemes – see Appendix A1
Other Works
Drainage – see Appendix B1 Development Update – see Appendix B2 Major Capital Projects – see Appendix B3
4. Conclusion
This report is for Members information.
Contact Officers:
The following contact officers can be contacted on 0845 8247 800
Carol Valentine Highway Manager (West) John Farmer Major Capital Project Manager Tony Ambrose Structures Manager Alan Casson District Manager Mary Gillett Resurfacing Manager Katie Lewis Drainage Manager Appendix A – Carriageway Schemes
Appendix A1
Please note that this is an estimated date that Kent County Council plan for the works to commence however if emergency situations occur then dates are likely to change.
Road Name Area Rd Section Affected Diversion District Start Date End Date Duration Times Notes Notes
From its junction with Oak Drive to Ash Crescent Gravesham Higham Beech Grove 06.05.11 11.05.11 5 Days 07:00 – 19:00 Road Closure Complete Higham From its junction with Taylors Lane to Beech Grove Gravesham Oak Drive 05.05.11 08.05.11 4 Days 07:00 – 18:00 Road Closure Complete From its junction with St Francis Cerne Road Gravesham Gravesend Avenue to Cambria Crescent 09.05.11 12.05.11 4 Days 07:00 – 18:00 Road Closure Complete
Church Lane Gravesham Chalk Whole Length 06.05.11 06.05.11 1 Day 09:00 – 17:00 Road Closure Complete
Cobhambury Rd Gravesham Cobham Whole Length 04.05.11 06.05.11 3 Days 07:00 – 19:00 Road Closure Complete From its junction with Huntingfield Evenden Road Gravesham Meopham Road for its entire length 04.05.11 06.05.11 3 Days 07:00 – 19:00 Road Closure Complete From its junction with Oak Drive for its Fairview Drive Gravesham Higham entire length 05.05.11 07.05.11 3 Days 07:00 – 19:00 Road Closure Complete From its junction with Erskine Road Highview Gravesham Meopham for its entire length 28.04.11 10.05.11 13 Days 07:00 – 19:00 Road Closure Complete Highwoods From its junction with Fairview Drive Close Gravesham Higham for its entire length 04.05.11 06.05.11 3 Days 07:00 – 19:00 Road Closure Complete
Jeskyns Road Gravesham Cobham Whole Length 05.05.11 05.05.11 1 Day 09:00 – 17:00 Road Closure Complete
From its junction with Norah Lane to Oak Drive Gravesham Higham Taylors Lane 06.05.11 11.05.11 5 Days 07:00 – 19:00 Road Closure Complete Pickwick From its junction with Dene Holm Gardens Gravesham Northfleet Road to Masefield Road 10.05.11 15.05.11 3 Days 07:00 – 19:00 Road Closure Complete
Shorne lfield Road Gravesham Shorne Whole Length 06.05.11 06.05.11 1 Day 09:00 – 17:00 Road Closure Complete
Telegraph Hill Gravesham Higham Whole Length 06.05.11 06.05.11 1 Day 09:00 – 17:00 Road Closure Complete
Waterlow Road From its junction with Erskine Rd to Gravesham Vigo Harvel Road TBC TBC TBC TBC Road Closure Complete White Post Lane Gravesham Meopham Whole Length 05.05.11 05.05.11 1 Day 09:00 – 17:00 Road Closure Complete
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Works Programme 2011/12Report | 150 KB | DownloadRead as text |
Follow Gravesham Joint Transportation Board at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2021 | Bath Street - Fastrack Infrastructure SchemeResolved that the report be noted. | Noted | Open |
| 10 Mar 2021 | Highway Forward Works Programme - 2019/20 onwardsResolved the report be noted. | Noted | Open |
| 10 Mar 2021 | Issues raised by Councillors with the approval of the ChairIt was agreed that the results of the ATC be shared with Cllr Rana. It was noted that the officer had previously disc... | Agreed | Open |
| 14 Mar 2018 | Gravesham Highway Works Programme 2017/18Resolved that the Board noted the information contained within the report and agreed the following: · The Gravesham D... | Noted | Open |
| 14 Mar 2018 | Petitions from residents at the JTB (KCC Petition Scheme)Resolved that the Board look at the original JTB Legal Agreement between KCC and GBC with the view to amending it to ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.